WORKSHEET #34: VERIFICATION (STEP 1) PROCESS TABLE<br />

This worksheet describes the processes that will be followed to verify project data quality.<br />

The table below describes how each item will be verified, when the activity will occur,<br />

what documentation is necessary, and who the responsible person is.<br />

Verification<br />

Input<br />

Chain-of-<br />

Custody<br />

Audit<br />

Reports<br />

<strong>Field</strong> Notes<br />

Analytical<br />

Data<br />

Packages<br />

Table 34-1. Verification Process<br />

Description<br />

Chain-of-custody <strong>for</strong>ms will be reviewed by the project team in the<br />

field upon completion and verified against the packed sample<br />

coolers they represent. The shipper’s signature on the chain-ofcustody<br />

will be initialed by the reviewer, a copy of the chain-ofcustody<br />

retained in the project file, and the original and remaining<br />

copies taped inside the cooler <strong>for</strong> shipment.<br />

A copy of all audit reports will be placed in the project file upon<br />

completion. If corrective actions are required, a copy of the<br />

documented corrective action taken will be attached to the<br />

appropriate audit report in the project file. At the beginning of each<br />

week and at the completion of the site work, project file audit reports<br />

will be reviewed internally to ensure that all appropriate corrective<br />

actions have been taken and that corrective action reports have<br />

been attached. If corrective actions have not been taken, the project<br />

manager will be notified to ensure action is taken.<br />

<strong>Field</strong> notes will be reviewed internally and placed in the project file.<br />

A copy of the field notes will be attached to the final report.<br />

All laboratory data packages will be verified internally by the<br />

laboratory per<strong>for</strong>ming the work <strong>for</strong> completeness and technical<br />

accuracy prior to submittal.<br />

All data packages will be verified externally by data validator who is<br />

not associated with the collection and analysis of samples,<br />

interpretation of sample data, or with any decision-making process<br />

within the scope of this investigation. The EWI #1 3EN2.1-specified<br />

data validation strategy <strong>for</strong> this project is 20% Level IV data<br />

validation and 80% Level III data validation <strong>for</strong> all laboratory data. In<br />

Level III data validation, data quality is assessed evaluating<br />

parameters by the appropriate criteria (or limits) specified in<br />

Worksheets 12, 19, and 28 of the project SAP, Contract Laboratory<br />

Program (CLP) requirements, EWI 3EN2.1 requirements, or the<br />

analytical methods. If calculations <strong>for</strong> quantitation are verified, it is<br />

done on a limited basis and may require raw data in addition to the<br />

standard data <strong>for</strong>ms normally present in a data package.<br />

Level IV data validation follows the EPA protocols and CLP criteria<br />

set <strong>for</strong>th in the functional guidelines <strong>for</strong> evaluating organic and<br />

inorganic analyses (EPA 1999, 2004). Level IV data validation<br />

consists of Level III data validation as well as checking calculations<br />

of quantified analytical data, including routine field samples and field<br />

and laboratory QC samples. Additionally, instrument per<strong>for</strong>mance,<br />

calibration, and calibration standard data are evaluated to ensure<br />

that detection limits and data values are appropriate.<br />

Internal/External<br />

Internal<br />

Internal<br />

Internal<br />

Internal and<br />

External<br />

Responsible<br />

<strong>for</strong><br />

Verification<br />

(name,<br />

organization)<br />

<strong>Field</strong><br />

Personnel<br />

Ann<br />

Bernhardt,<br />

AMEC<br />

Program<br />

QCM<br />

<strong>Field</strong><br />

Personnel<br />

Internal:<br />

Tina Green/<br />

BC Labs<br />

External:<br />

Jeanne<br />

Peterson/<br />

AQA<br />

Final Sampling and Analysis Plan<br />

Installation Restoration Site 29, Hangar 1<br />

Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>, Cali<strong>for</strong>nia<br />

DCN: AMEC-8816-0005-0039<br />

April 2010<br />

Page 34-1