FINAL SAMPLING AND ANALYSIS PLAN - Documents for Moffett Field
FINAL SAMPLING AND ANALYSIS PLAN - Documents for Moffett Field
FINAL SAMPLING AND ANALYSIS PLAN - Documents for Moffett Field
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
WORKSHEET #17: <strong>SAMPLING</strong> DESIGN <strong>AND</strong> RATIONALE<br />
Samples collected during this project will include baseline soil/sediment samples collected<br />
prior to construction and confirmation soil, wipe, and sediment samples collected once the<br />
removal action is completed. Details on the sampling design and rationale are presented<br />
below.<br />
Baseline/Pre-Construction Samples:<br />
Pre-construction samples will be collected from soil areas immediately adjacent to Hangar<br />
1 and from the sediment in the stormwater trench/conveyance system around the perimeter<br />
of Hangar 1. The purpose of the pre-construction soil and sediment samples is to establish<br />
baseline concentrations of PCBs, lead, and asbestos. Baseline/pre-construction<br />
concentrations will be compared to confirmation soil samples to verify that contaminants<br />
were not released into the environment as the result of the removal action.<br />
The scope of the soil sampling ef<strong>for</strong>t is restricted to the area of the soil immediately<br />
adjacent to (east of) Hangar 1. This area is approximately 21,000 ft 2 . The rationale <strong>for</strong><br />
limiting the soil sampling ef<strong>for</strong>t to this area is based on the following:<br />
• This is the only unpaved area within the project site.<br />
• Hangar 1 is surrounded by a perimeter storm water collection trench which<br />
prevents surface water from leaving the project site.<br />
• The nearest unpaved area is 300 feet North of Hangar 1.<br />
• Hangar 1 is in an industrial land use area and there are no sensitive habitats nearby<br />
(see Worksheet 10).<br />
Soil samples will be collected from 51 locations from soil areas on the east side of the<br />
Hangar. Sample locations are shown in Figure 11-1. At each location, soil samples will be<br />
collected from 0-6 inches (surface) and 6-12 inches below ground surface (bgs). Surface<br />
samples will be analyzed <strong>for</strong> PCBs, lead, and asbestos. If the concentration of PCBs in the<br />
surface sample is above 1000 ug/kg, then the 6-12 inch sample will be analyzed <strong>for</strong> PCBs<br />
to determine the vertical extent of the PCB contamination. Additional samples will be<br />
collected at 6-inch intervals to determine the depth of PCB contamination. Results of<br />
baseline/pre-construction samples will be provided to EPA and Water Board <strong>for</strong><br />
consultation and concurrence on areas requiring soil removal if PCB concentrations exceed<br />
1000 ug/kg.<br />
Four baseline/pre-construction sediment samples will also be collected from the<br />
stormwater trench/conveyance system. Locations will be selected based on where there is a<br />
sufficient amount of sediment present <strong>for</strong> sample collection. Soil and sediment samples<br />
will be collected using the procedure described in Worsheet 14.<br />
Final Sampling and Analysis Plan<br />
Installation Restoration Site 29, Hangar 1<br />
Former Naval Air Station, <strong>Moffett</strong> <strong>Field</strong>, <strong>Moffett</strong> <strong>Field</strong>,<br />
Cali<strong>for</strong>nia<br />
DCN: AMEC-8816-0005-0039<br />
April 2010<br />
Page 17-1