10.02 Unauthorized Changes in the Work2. the Change Order constitutes fill mutual accord andA. CONTRACTOR shall not be entitled to an satisfaction for the change to the Work:increase in the Contract Price or an extension of theContract Times with respect to any work performed that is 3. no reservation of rights to pursue subsequent claimsnot required by the Contract Documents as amended, on the Change Order will be made by either party; andmodified, or supplemented as provided in paragraph 3.04,except in the case of an emergency as provided in paragraph 4. no subsequent claim or amendment of the Contract6.16 or in the case of uncovering Work as provided in Documents will arise out of or as a result of the Changeparagraph 13.04.B.Order.10.03 Execution of Change Orders 10.04 Notification to SuretyA. OWNER and CONTRACTOR shall execute A. If notice of any change affecting the general scopeappropriate Change Orders recommended by ENGINEER of the Work or the provisions of the Contract Documents(or Written Amendments) covering:(including, but not limited to, Contract Price or ContractTimes) is required by the provisions of any Bond to be1. changes in the Work which are: (i) ordered by given to a surety, the giving of any such notice will beOWNER pursuant to paragraph 10.0l.A, (ii) required CONTRACTOR's responsibility. The amount of eachbecause of acceptance of defective Work under paragraph applicable Bond will be adjusted to reflect the effect of any13.08.A or OWNER's correction of defective Work under such change.paragraph 13.09, or (iii) agreed to by the parties;10.05 Claims and Disputes2. changes in the Contract Price or Contract Times whichare agreed to by the parties, including any undisputed sumA. Notice: Written notice stating the general natureor amount of time for Work actually performed in of each Claim, dispute, or other matter shall be delivered byaccordance with a Work Change Directive; andthe claimant to ENGINEER and the other party to theContract promptly (but in no event later than 10 days) after3. changes in the Contract Price or Contract Times which the start of the occurrence or event3 days) after thF4 seaofembody the substance of any written decision rendered by ;hp-event giving rise thereto. Notice of the amount or extentENGINEER pursuant to paragraph 10.05; provided that, in of the Claim, dispute, or other matter with supporting datalieu of executing any such Change Order, an appeal may be shall be delivered to the ENGINEER and the other party totaken from any such decision in accordance with the the Contract promptly but not later than twenty days afterprovisions of the Contract Documents and applicable Laws the start of the occurrence or event and monthly therafterand Regulations, but during any such appeal, for continuing eventswithin 60 days after the start of schCONTRACTOR shall carry on the Work and adhere to the etent (unless ENGINEER allows additional time forprogress schedule as provided in paragraph 6. 18.A.claimant to submit additional or more accurate data insupport of such Claim, dispute, or other matter). A ClaimB. In signing a Change Order, the OWNER and for an adjustment in Contract Price shall be prepared inCONTRACTOR acknowledge and agree that: accordance with the provisions of paragraph 12.01,B. AClaim for an adjustment in Contract Time shall be preparedi. the stipulated compensation (chanae in Contract Price in accordance with the provisions of paragraph 12.02.B.or Contract Time, or both) set forth in the Change Order Each Claim shall be accompanied by claimant's writtenincludes payment for (i) the Cost of the Work covered by statement that the adjustment claimed is the entirethe Change Order, (iii CONTRACTOR's fee for overhead adjustment to which the claimant believes it is entitled as aand profit, (iii) interruption of progress schedules, (iv) result of said event. The opposing party shall submit anydelay and impact, includine cumulative impact, on other response to ENGINEER and the claimant within 34-10 dayswork under the Contract Documents, and (v) extended after receipt of the claimant's last submittal (unlessoverheads-ENGINEER allows additional time).B. ENGINEER ' Decision: ENGINEER will rendera formal decision in writing within 30 days after receipt ofthe last submittal of the claimant or the last submittal of theopposing party, if any. ENGINEER's written decision onEJCDC No. 1910-8 (1996 Edition) 007200-32wI JJG Modifications (Rev03/06/08)
such Claim, dispute, or other matter will be final and and CONTRACTOR. Such employees shall includebinding upon OWNER and CONTRACTOR unless:without limitation superintendents, foremen, and otherpersonnel employed full time at the Site. Payroll costs for1. an appeal from ENGINEER's decision is taken within employees not employed full time on the Work shall bethe time limits and in accordance with the dispute resolution apportioned on the basis of their time spent on the Work.procedures set forth in Article 16; orPayroll costs shall include, but not be limited to, salariesand wages plus the cost of fringe benefits, which shall2. if no such dispute resolution procedures have been set include social security contributions, unemployment, excise,forth in Article 16, a written notice of intention to appeal and payroll taxes, workers' compensation, health andfrom ENGINEER's written decision is delivered by retirement benefits,-benweqe sick leave, vacation andOWNER or CONTRACTOR to the other and to holiday pay applicable thereto. The expenses of performingENGINEER within 30 days after the date of such decision, Work outside of regular working hours, on Saturday,and a formal proceeding is instituted by the appealing party Sunday, or legal holidays, shall be included in the above toin a forum of competent jurisdiction within 60 days after the the extent authorized by OWNER.date of such decision or within 60 days after SubstantialCompletion, whichever is later (unless otherwise agreed in 2. Cost of all materials and equipment furnished andwriting by OWNER and CONTRACTOR), to exercise such incorporated in the Work, including costs of transportationrights or remedies as the appealing party may have with and storage thereof, and Suppliers' field services required inrespect to such Claim, dispute, or other matter in connection therewith. All cash discounts shall accrue toaccordance with applicable Laws and Regulations.CONTRACTOR unless OWNER deposits funds withCONTRACTOR with which to make payments, in whichC. If ENGINEER does not render a formal decision case the cash discounts shall accrue to OWNER. All tradein writing within the time stated in paragraph 10.05,B, a discounts, rebates and refunds and returns from sale ofdecision denying the Claim in its entirety shall be deemed to surplus materials and equipment shall accrue to OWNER,have been issued 31 days after receipt of the last submittal and CONTRACTOR shall make provisions so that theyof -the claimant or the last submittal of the opposing party, may be obtained.if any.3. Payments made by CONTRACTOR to <strong>Subcontractors</strong>D. No Claim for an adjustment in Contract Price or for Work performed by <strong>Subcontractors</strong>. If required byContract Times (or Milestones) will be valid if not OWNER, CONTRACTOR shall obtain competitive bidssubmitted in accordance with this paragraph 10.05.from subcontractors acceptable to OWNER and CON-TRACTOR and shall deliver such bids to OWNER, whoARTICLE 1 - COST OF THE WORK; CASH will then determine, with the advice of ENGINEER, whichALLOWANCES: UNIT PRICE WORKbids, if any, will be acceptable. If any subcontract providesthat the Subcontractor is to be paid on the basis of Cost of11.01 Cost of the Work the Work plus a fee, the Subcontractor's Cost of the Workand fee shall be determined in the same manner asA. Costs Included: The term Cost of the Work means CONTRACTOR's Cost of the Work and fee as provided inthe sum of all costs necessarily incurred and paid by CON- this paragraph 11.01.TRACTOR in the proper performance of the Work. Whenthe value of any Work covered by a Change Order or when 4. Costs of special consultants (including but not limiteda Claim for an adjustment in Contract Price is determined to engineers, architects, testing laboratories, surveyors,on the basis of Cost of the Work, the costs to be reimbursed attorneys, and accountants) employed for servicesto CONTRACTOR will be only those additional or specifically related to the Work.incremental costs required because of the change in theWork or because of the evcnt giving rise to the Claim. 5. Supplemental costs including the following:Except as otherwise may be agreed to in writing byOWNER, such costs shall be in amounts no higher than a. The proportion of necessary transportation, travel, andthose prevailing in the locality of the Project, shall include subsistence expenses of CONTRACTOR's employeesonly the following items, and shall not include any of the incurred in discharge of duties connected with the Work.costs itemized in paragraph 11.01 .B.b. Cost, including transportation and maintenance, of all1. Payroll costs for employees in the direct employ of materials, supplies, equipment, machinery, appliances,CONTRACTOR in the performance of the Work under office, and temporary facilities at the Site, and hand toolsschedules of job classifications agreed upon by OWNER not owned by the workers, which are consumned in theEJCDC No. 1910-8 (1996 Edition) 007200-33w/ JJG Modifications (Rev03/06/08)
- Page 1 and 2:
ADDENDUM XDATE: May 19, 2008TO:FROM
- Page 3 and 4:
( 0ORO t'The Unified Government of
- Page 5 and 6:
R: No change to bid date.3- Q: (AG)
- Page 7 and 8:
Part IGeneralSection 01 57 00Enviro
- Page 9 and 10:
005700-3Environmental and Property
- Page 11 and 12:
JORDANJONES &SGOULDINGList of Planh
- Page 13 and 14:
List of Planholders, Athens North O
- Page 15 and 16:
RADDENDUM IXDATE: May 16, 2008TO:FR
- Page 17 and 18:
AGREEMENT BETWEENBUYER AND SELLERFO
- Page 19 and 20:
* Delete page 00520-5 and replace w
- Page 21 and 22:
otherwise.F. Should either party re
- Page 23 and 24:
4gas well as construction of the la
- Page 25 and 26:
QUESTIONS AND RESPONSES NO. 5NORTH
- Page 27 and 28:
Also on drawing 05-CD-1 typical roa
- Page 29 and 30:
R: No change will be made to the do
- Page 31 and 32:
R: Apply protective liner to all in
- Page 33 and 34:
16. Q: (AS)Section 0421.13 - Page 5
- Page 35 and 36:
induction motor data sheet.a) Is th
- Page 37 and 38:
conduit size for P39 to be 1-1/2".
- Page 39 and 40:
R: No change will be made to the do
- Page 41 and 42:
(TC)(TDC)(TDH)(TF)(TI)(TJL)(WGH)(WS
- Page 43 and 44:
(1)Section 00 41 00BidTO:UNIFIED GO
- Page 45 and 46:
004100-3Bidf. Utility Location Allo
- Page 47 and 48:
004100-5BidIte No Decito Qty uni Un
- Page 49 and 50:
0041 00-7BidIte No. Decito t.UiSUi
- Page 51 and 52:
004100-9BidMAJOR PRODUCT OR SYSTEM
- Page 53 and 54:
0041 00-11BidThe Bidder agrees here
- Page 55 and 56:
EQUIPMENT ALLOWANCE SCOPE OF WORKRE
- Page 57 and 58:
March 7, 2008 Amended May 13, 2008T
- Page 59 and 60:
System Controls:Not included in thi
- Page 61 and 62:
* No performance and laboratory tes
- Page 63 and 64:
C. Seller is familiar with and is s
- Page 65 and 66:
Project: Athens, GA North Oconee Ma
- Page 67 and 68:
ARTICLE 4 -BASIS OF PROPOSAL4.01 Pr
- Page 69 and 70:
Weir Specialty PumpsP.O. Box209 (84
- Page 71 and 72:
ATHENS, GA 7 NORTH OCONEE May 12,20
- Page 73 and 74:
Weir Specialty PumpsWEiRco PUMPWEMI
- Page 75 and 76:
1635W. Walnut StreetTU R B LEX Spri
- Page 77 and 78:
B. $ 33,658.00 The Seller's monthly
- Page 79 and 80:
Quotation # 08RAS-027-01Yancey Powe
- Page 81 and 82:
-k 0Quotation # O8RAS-027-01Yancey
- Page 83 and 84:
Quotation # OBRAS-027-01Yaney Power
- Page 85 and 86:
- Quotation # O8RAS-027-01Yaney pow
- Page 87 and 88:
Quotation #- OSRAS-027-01' Yancey25
- Page 89 and 90:
Quotation # 08RAS-027-01Yancey Povw
- Page 91 and 92:
NPMwerSystms.259 I.eeilndustrW Bilv
- Page 93 and 94:
Dubin, GregFrom:Sent:To:Cc:Subject:
- Page 95 and 96:
SUPPLEMENTARY CONDITIONS (Rev. 1)Th
- Page 97 and 98:
SC 15: Add the followtng paragraph:
- Page 99 and 100: 0 0 0C3) cm C C Ccm 0ES 20 ESw'-a m
- Page 101 and 102: U) SL ct )0 nm 0UCV 0 LC,9 . Q o1 f
- Page 103 and 104: QUESTIONS AND RESPONSES NO. 4NORTH
- Page 105 and 106: would the OCP policy not be enough
- Page 107 and 108: properties used in it methods allow
- Page 109 and 110: 12. Q: (TC) SECTION 31 23 60 - 5 ME
- Page 111 and 112: R: Refer to 05-CU drawings and Spec
- Page 113 and 114: R: See subsequent addenda.Zone 2 84
- Page 115 and 116: actually a refractor 545 or if a re
- Page 117 and 118: ~vRk0 oRADDENDUM IIDATE: April 15,
- Page 119 and 120: STANDARDGENERAL CONDITIONSOF THECON
- Page 121 and 122: GENERAL CONDITIONSARTICLE 1 - DEFIN
- Page 123 and 124: 29. Notice to Proceed--A written no
- Page 125 and 126: within the Contract Time, or extend
- Page 127 and 128: others as appropriate will be held
- Page 129 and 130: 3.04 Amending and Supplementing Con
- Page 131 and 132: a. reviewing and checking all such
- Page 133 and 134: Documents. CONTRACTOR shall also fu
- Page 135 and 136: 5. allow for partial utilization of
- Page 137 and 138: ARTICLE 6 - CONTRACTOR'S RESPONSIBI
- Page 139 and 140: substitte item will perform adequat
- Page 141 and 142: permits and licenses. CONTRACTOR sh
- Page 143 and 144: esponse to such an emergency, a Wor
- Page 145 and 146: 1. is attributable to bodily injury
- Page 147 and 148: 8-05 Lands andEasements; Reports an
- Page 149: accordance with the provisions of p
- Page 153 and 154: equipment brought to the Project if
- Page 155 and 156: the ENGINEER and the other party to
- Page 157 and 158: incorporation in the Work. Such ins
- Page 159 and 160: ARTICLE 14 - PAYMENTS TO CONTRACTOR
- Page 161 and 162: 2. Should CONTRACTOR neglect to pay
- Page 163 and 164: 14.07 Final Payment ENGINEER will r
- Page 165 and 166: Documents in connection with uncomp
- Page 167 and 168: ADDENDUM VillDATE: May 15, 2008TO:F
- Page 169 and 170: tRkzZRDrawings1. Delete Sheet 05-SE
- Page 171 and 172: Copyright C 2 000National Society o
- Page 173 and 174: AGREEMENT... THIS AGREEMENTi betwee
- Page 175 and 176: 6.04 Seller and Buyer shall execute
- Page 177 and 178: D. The Contract Documents may only
- Page 179 and 180: ATTACHMENT ASnecificationsSection T
- Page 181 and 182: PROPOSAL FORMPRESELECTED EQUIPMENT
- Page 183 and 184: ARTICLE 4 - BASIS OF PROPOSAL4.01 P
- Page 185 and 186: PARKSON CORPORATIONUnanimous Writte
- Page 187 and 188: Hanson, RickFrom:MAHONEY770@aol.com
- Page 189 and 190: Furt-her,.p ease advise me ifyou wi
- Page 191 and 192: Copyright 02000National Society of
- Page 193 and 194: AGREEMENTTHIS AGREEMENT is between(
- Page 195 and 196: 6.04 Seller and Buyer shalt execute
- Page 197 and 198: ARTICLE 11 - MISCELLANEOUS11.01 Def
- Page 199 and 200: ATTACHMENT ASpecificationsSection T
- Page 201 and 202:
SIEMENSCOST PROPOSALOdor Control (B
- Page 203 and 204:
SIEMENSTABLE OF CONTENTSNo.Item Des
- Page 205 and 206:
ARTICLE 1- PROPOSAL RECIPIENT1.01 T
- Page 207 and 208:
6,02 The following documents are in
- Page 209 and 210:
SIEMENSSECTION 2SIEMENS' DETAILED S
- Page 211 and 212:
SIEMENSTransfbrmer, Circuit breaker