engineers, architects, attorneys, and other professionals andA. If CONTRACTOR fails within 48 hoursMiri-aall court or arbitration or other dispute resolution costs) recsnable time after written notice from ENGINEER toarising out of or relating to such correction or repair or such correct defective Work or to remove and replace rejectedremoval and replacement (including but not limited to all Work as required by ENGINEER in accordance with paracostsof repair or replacement of work of others) will be graph 13.06.A, or if CONTRACTOR fails to perform thepaid by CONTRACTOR.Work in accordance with the Contract Documents, or ifCONTRACTOR fails to comply with any other provision ofB. In special circumstances where a particular item of the Contract Documents, OWNER may, after seven daysequipment is placed in continuous service before written notice to CONTRACTOR, correct and remedy anySubstantial Completion of all the Work, the correction such deficiency.period for that item may start to run from an earlier date ifso provided in the Specifications or by Written Amendment. B. In exercising the rights and remedies under thisparagraph, OWNER shall proceed expeditiously. InC. Where defective Work (and damage to other Work connection with such corrective and remedial action,resulting therefrom) has been corrected or removed and OWNER may exclude CONTRACTOR from all or part ofreplaced under this paragraph 13.07, the correction period the Site, take possession of all or part of the Work andhereunder with respect to such Work will be extended for suspend CONTRACTOR's services related thereto, takean additional period of one year after such correction or possession of CONTRACTOR's tools, appliances, conremovaland replacement has been satisfactorily completed. struction equipment and machinery at the Site, and incorporatein the Work all materials and equipment stored at theD. CONTRACTOR's obligations under this Site or for which OWNER has paid CONTRACTOR butparagraph 13.07 are in addition to any other obligation or which are stored elsewhere. CONTRACTOR shall allowwarranty. The provisions of this paragraph 13.07 shall not OWNER, OWNER's representatives, agents and employbeconstrued as a substitute for or a waiver of the provisions ees, OWNER's other contractors, and ENGINEER andof any applicable statute of limitation or repose.ENGINEER's Consultants access to the Site to enableOWNER to exercise the rights and remedies under this13.08 Acceptance of Defective Work paragraph.A. If, instead of requiring correction or removal and C. All Claims, costs, losses, and damages (includingreplacement of defective Work, OWNER (and, prior to but not limited to all fees and charges of engineers,ENGINEER's recommendation of final payment, architects, attorneys, and other professionals and all court orENGINEER) prefers to accept it, OWNER may do so. arbitration or other dispute resolution costs) incurred orCONTRACTOR shall pay all Claims, costs, losses, and sustained by OWNER in exercising the rights and remediesdamages (including but not limited to all fees and charges of under this paragraph 13.09 will be charged against CONengineers,architects, attorneys, and other professionals and TRACTOR, and a Change Order will be issued incorpoallcourt or arbitration or other dispute resolution costs) rating the necessary revisions in the Contract Documentsattributable to OWNER's evaluation of and determination with respect to the Work; and OWNER shall be entitled toto accept such defective Work (such costs to be approved an appropriate decrease in the Contract Price. If the partiesby ENGINEER as to reasonableness) and the diminished are unable to agree as to the amount of the adjustment,value of the Work to the extent not otherwise paid by OWNER may make a Claim therefor as provided inCONTRACTOR pursuant to this sentence. If any such paragraph 10.05. Such claims, costs, losses and damagesacceptance occurs prior to ENGINEER's recommendation will include but not be limited to all costs of repair, orof final payment, a Change Order will be issued replacement of work of others destroyed or damaged byincorporating the necessary revisions in the Contract correction, removal, or replacement of CONTRACTOR'sDocuments with respect to the Work, and OWNER shall be defective Work.entitled to an appropriate decrease in the Contract Price,reflecting the diminished value of Work so accepted. If theD. CONTRACTOR shall not be allowed an extensionparties are unable to agree as to the amount thereof, of the Contract Times (or Milestones) because of any delayOWNER may make a Claim therefor as provided in in the performance of the Work attributable to the exerciseparagraph 10.05. If the acceptance occurs after such by OWNER of OWNER's rights and remedies under thisrecommendation, an appropriate amount will be paid by paragraph 13.09.CONTRACTOR to OWNER.13.09 OWNER May Correct Defective WorkEJCDC No. 1910-8 (1996 Edition) 00 72 00 - 40w/ JJG Modifications (Rev03/06/08)
ARTICLE 14 - PAYMENTS TO CONTRACTOR ANDCOMPLETION5. The OWNER will retain the following amounts fromeach properly certified estimate:14.01 Schedule of Valuesa. Until the value of the Work completed, includingA. The schedule of values established as provided in stored materials, is at least 50 percent of the Contractparagraph 2.07.A will serve as the basis for progress amount, 10 percent of the value of all Work satisfactorilypayments and will be incorporated into a form of Applica- completed, including stored materials.tion for Payment acceptable to ENGINEER. Progresspayments on account of Unit Price Work will be based on b. When the value of the completed Work totals at least 50the number of units completed.percent of the Contract amount, the Owner will discontinueretaining additional amounts provided the Work is14.02 Progress Payments progressing satisfactorily and there is no specific cause forretaining a larger sum. The total amount retained will be atA. Applicationsfor Payments least 5 percent of the Contract amount. adiusted for ChangeOrders, until the date of final payment.1. At least 20 days before the date established for eachprogress payment (but not more often than once a month), c. The Owner may elect to reinstate retainage of 10 percentCONTRACTOR shall submit to ENGINEER for review an of the value of the Work completed if at any time theApplication for Payment filled out and signed by Contractor fails to make satisfactory progress or if there isCONTRACTOR covering the Work completed as of the other specific cause. Satisfactory progress is identified asdate of the Application and accompanied by such sup- conforming to the construction progress schedule asporting documentation as is required by the Contract Docu- required in Article 24, as modified by the Supplementaryments. If payment is requested on the basis of materials and Conditions.equipment not incorporated in the Work but delivered andsuitably stored at the Site or at anzther 196atin agFred to in 6. No form of collateral in lieu of cash will bewriting, the Application for Payment shall also be acceptable as retainage.accompanied by a bill of sale, invoice, or other documentationwarranting that OWNER has received the materials 7- Amounts retained by the Contractor from paymentsand equipment free and clear of all Liens and evidence that due to suppliers and subcontractors (expressed as athe materials and equipment are covered by appropriate percentage) shall not exceed that being retained by theproperty insurance or other arrangements to protect Owner.OWNER's interest therein, all of which must be satisfactoryto OWNER. 8. Payments Withheld: The Engineer may decline toapprove an Application for Payment and may withhold2. Beginning with the second Application for Payment, certificate, in whole or in part. as may be necessary toeach Application shall include an affidavit of protect the Owner from loss because of.CONTRACTOR stating that all previous progress paymentsreceived on account of the Work have been applied on a. Failure of the Contractor to make payments proerlaccount to discharge CONTRACTOR's legitimate to subcontractors or for labor or products.obligations associated with prior Applications for Payment.b. Unsatisfactory prosecution of the Work by the3. The amount of retainage with respect to progress pay- Contractor either due to quality of the Work or if thements will be as stipulated in the Ageementbelow.Contractor is behind the currently approved construction4. If requested, CONTRACTOR shall furnish evidence schedule.that payment received on the basis of materials and 9. When the above reasons for nonpayment areequipment not incorporated and suitably stored, has in fact corrected, then payment will be made for amounts withheldbeen paid to the respective suoplier(s) within fifteen days because of such reasons, not later than the next payment.of payment by OWNER. Failure to provide such evidenceof payment may result in the withdrawal of previousapproval(s) and removal of the cost of related materials . Review of Applicationsand equipment from the next submitted Application forPayment.1. ENGINEER will, within 10 days after receipt of eachApplication for Payment, either indicate in writing arecommendation of payment and present the Application toEJCDC No. 1910-8 (1996 Edition) 00 72 00 - 41wI JJG Modifications (Reo03/06/08)
- Page 1 and 2:
ADDENDUM XDATE: May 19, 2008TO:FROM
- Page 3 and 4:
( 0ORO t'The Unified Government of
- Page 5 and 6:
R: No change to bid date.3- Q: (AG)
- Page 7 and 8:
Part IGeneralSection 01 57 00Enviro
- Page 9 and 10:
005700-3Environmental and Property
- Page 11 and 12:
JORDANJONES &SGOULDINGList of Planh
- Page 13 and 14:
List of Planholders, Athens North O
- Page 15 and 16:
RADDENDUM IXDATE: May 16, 2008TO:FR
- Page 17 and 18:
AGREEMENT BETWEENBUYER AND SELLERFO
- Page 19 and 20:
* Delete page 00520-5 and replace w
- Page 21 and 22:
otherwise.F. Should either party re
- Page 23 and 24:
4gas well as construction of the la
- Page 25 and 26:
QUESTIONS AND RESPONSES NO. 5NORTH
- Page 27 and 28:
Also on drawing 05-CD-1 typical roa
- Page 29 and 30:
R: No change will be made to the do
- Page 31 and 32:
R: Apply protective liner to all in
- Page 33 and 34:
16. Q: (AS)Section 0421.13 - Page 5
- Page 35 and 36:
induction motor data sheet.a) Is th
- Page 37 and 38:
conduit size for P39 to be 1-1/2".
- Page 39 and 40:
R: No change will be made to the do
- Page 41 and 42:
(TC)(TDC)(TDH)(TF)(TI)(TJL)(WGH)(WS
- Page 43 and 44:
(1)Section 00 41 00BidTO:UNIFIED GO
- Page 45 and 46:
004100-3Bidf. Utility Location Allo
- Page 47 and 48:
004100-5BidIte No Decito Qty uni Un
- Page 49 and 50:
0041 00-7BidIte No. Decito t.UiSUi
- Page 51 and 52:
004100-9BidMAJOR PRODUCT OR SYSTEM
- Page 53 and 54:
0041 00-11BidThe Bidder agrees here
- Page 55 and 56:
EQUIPMENT ALLOWANCE SCOPE OF WORKRE
- Page 57 and 58:
March 7, 2008 Amended May 13, 2008T
- Page 59 and 60:
System Controls:Not included in thi
- Page 61 and 62:
* No performance and laboratory tes
- Page 63 and 64:
C. Seller is familiar with and is s
- Page 65 and 66:
Project: Athens, GA North Oconee Ma
- Page 67 and 68:
ARTICLE 4 -BASIS OF PROPOSAL4.01 Pr
- Page 69 and 70:
Weir Specialty PumpsP.O. Box209 (84
- Page 71 and 72:
ATHENS, GA 7 NORTH OCONEE May 12,20
- Page 73 and 74:
Weir Specialty PumpsWEiRco PUMPWEMI
- Page 75 and 76:
1635W. Walnut StreetTU R B LEX Spri
- Page 77 and 78:
B. $ 33,658.00 The Seller's monthly
- Page 79 and 80:
Quotation # 08RAS-027-01Yancey Powe
- Page 81 and 82:
-k 0Quotation # O8RAS-027-01Yancey
- Page 83 and 84:
Quotation # OBRAS-027-01Yaney Power
- Page 85 and 86:
- Quotation # O8RAS-027-01Yaney pow
- Page 87 and 88:
Quotation #- OSRAS-027-01' Yancey25
- Page 89 and 90:
Quotation # 08RAS-027-01Yancey Povw
- Page 91 and 92:
NPMwerSystms.259 I.eeilndustrW Bilv
- Page 93 and 94:
Dubin, GregFrom:Sent:To:Cc:Subject:
- Page 95 and 96:
SUPPLEMENTARY CONDITIONS (Rev. 1)Th
- Page 97 and 98:
SC 15: Add the followtng paragraph:
- Page 99 and 100:
0 0 0C3) cm C C Ccm 0ES 20 ESw'-a m
- Page 101 and 102:
U) SL ct )0 nm 0UCV 0 LC,9 . Q o1 f
- Page 103 and 104:
QUESTIONS AND RESPONSES NO. 4NORTH
- Page 105 and 106:
would the OCP policy not be enough
- Page 107 and 108: properties used in it methods allow
- Page 109 and 110: 12. Q: (TC) SECTION 31 23 60 - 5 ME
- Page 111 and 112: R: Refer to 05-CU drawings and Spec
- Page 113 and 114: R: See subsequent addenda.Zone 2 84
- Page 115 and 116: actually a refractor 545 or if a re
- Page 117 and 118: ~vRk0 oRADDENDUM IIDATE: April 15,
- Page 119 and 120: STANDARDGENERAL CONDITIONSOF THECON
- Page 121 and 122: GENERAL CONDITIONSARTICLE 1 - DEFIN
- Page 123 and 124: 29. Notice to Proceed--A written no
- Page 125 and 126: within the Contract Time, or extend
- Page 127 and 128: others as appropriate will be held
- Page 129 and 130: 3.04 Amending and Supplementing Con
- Page 131 and 132: a. reviewing and checking all such
- Page 133 and 134: Documents. CONTRACTOR shall also fu
- Page 135 and 136: 5. allow for partial utilization of
- Page 137 and 138: ARTICLE 6 - CONTRACTOR'S RESPONSIBI
- Page 139 and 140: substitte item will perform adequat
- Page 141 and 142: permits and licenses. CONTRACTOR sh
- Page 143 and 144: esponse to such an emergency, a Wor
- Page 145 and 146: 1. is attributable to bodily injury
- Page 147 and 148: 8-05 Lands andEasements; Reports an
- Page 149 and 150: accordance with the provisions of p
- Page 151 and 152: such Claim, dispute, or other matte
- Page 153 and 154: equipment brought to the Project if
- Page 155 and 156: the ENGINEER and the other party to
- Page 157: incorporation in the Work. Such ins
- Page 161 and 162: 2. Should CONTRACTOR neglect to pay
- Page 163 and 164: 14.07 Final Payment ENGINEER will r
- Page 165 and 166: Documents in connection with uncomp
- Page 167 and 168: ADDENDUM VillDATE: May 15, 2008TO:F
- Page 169 and 170: tRkzZRDrawings1. Delete Sheet 05-SE
- Page 171 and 172: Copyright C 2 000National Society o
- Page 173 and 174: AGREEMENT... THIS AGREEMENTi betwee
- Page 175 and 176: 6.04 Seller and Buyer shall execute
- Page 177 and 178: D. The Contract Documents may only
- Page 179 and 180: ATTACHMENT ASnecificationsSection T
- Page 181 and 182: PROPOSAL FORMPRESELECTED EQUIPMENT
- Page 183 and 184: ARTICLE 4 - BASIS OF PROPOSAL4.01 P
- Page 185 and 186: PARKSON CORPORATIONUnanimous Writte
- Page 187 and 188: Hanson, RickFrom:MAHONEY770@aol.com
- Page 189 and 190: Furt-her,.p ease advise me ifyou wi
- Page 191 and 192: Copyright 02000National Society of
- Page 193 and 194: AGREEMENTTHIS AGREEMENT is between(
- Page 195 and 196: 6.04 Seller and Buyer shalt execute
- Page 197 and 198: ARTICLE 11 - MISCELLANEOUS11.01 Def
- Page 199 and 200: ATTACHMENT ASpecificationsSection T
- Page 201 and 202: SIEMENSCOST PROPOSALOdor Control (B
- Page 203 and 204: SIEMENSTABLE OF CONTENTSNo.Item Des
- Page 205 and 206: ARTICLE 1- PROPOSAL RECIPIENT1.01 T
- Page 207 and 208: 6,02 The following documents are in
- Page 209 and 210:
SIEMENSSECTION 2SIEMENS' DETAILED S
- Page 211 and 212:
SIEMENSTransfbrmer, Circuit breaker