ARTICLE 15 - SUSPENSION OF WORK AND B. If one or more of the events identified in paragraphTERMINATION15.02.A occur, OWNER may, after giving CONTRACTOR(and the surety, if any) seven days written notice, terminate15.01 OWNER May Suspend Work the services of CONTRACTOR, exclude CONTRACTORfrom the Site, and take possession of the Work and of allA. At any time and without cause, OWNER may CONTRACTOR's tools, appliances, construction equipsuspendthe Work or any portion thereof for a period of not ment, and machinery at the Site, and use the same to the fullmore than 90 consecutive days by notice in writing to CON- extent they could be used by CONTRACTOR (withoutTRACTOR and ENGINEER which will fix the date on liability to CONTRACTOR for trespass or conversion),which Work will be resumed. CONTRACTOR shall incorporate in the Work all materials and equipment storedresume the Work on the date so fixed. CONTRACTOR at the Site or for which OWNER has paid CONTRACTORshall be allowed an adjustment in the Contract Price or an but which are stored elsewhere, and finish the Work asextension of the Contract Times, or both, directly OWNER may deem expedient. In such case,attributable to any such suspension if CONTRACTORmakes a Claim therefor as provided in paragraph 10.05.CONTRACTOR shall not be entitled to receive any furtherpayment until the Work is finished. If the unpaid balance ofthe Contract Price exceeds all claims, costs, losses, and15.02 OWNER May Terminate for Cause damages (including but not limited to all fees and charges ofengineers, architects, attorneys, and other professionals andA. The occurrence of any one or more of the all court or arbitration or other dispute resolution costs)following events will justify termination for cause:sustained by OWNER arising out of or relating tocompleting the Work, such excess will be paid to1. CONTRACTOR's persistent failure to perform the CONTRACTOR. If such claims, costs, losses, andWork in accordance with the Contract Documents damages exceed such unpaid balance, CONTRACTOR(including, but not limited to, failure to supply sufficient shall pay the difference to OWNER. Such claims, costs,skilled workers or suitable materials or equipment or failure losses, and damages incurred by OWNER will be reviewedto adhere to the progress schedule established under by ENGINEER as to their reasonableness and, when soparagraph 2.07 as adjusted from time to time pursuant toparagraph 6.04);approved by ENGINEER, incorporated in a Change Order.When exercising any rights or remedies under thisparagraph OWNER shall not be required to obtain the2. CONTRACTOR's disregard of Laws or Regulations lowest price for the Work performed.of any public body having jurisdiction;C. Where CONTRACTOR's services have been so3. CONTRACTOR's disregard of the authority of terminated by OWNER, the termination will not affect anyENGINEER; orrights or remedies of OWNER against CONTRACTORthen existing or which may thereafter accrue. Any retention4. CONTRACTOR's violation in any substantial way of or payment of moneys due CONTRACTOR by OWNERany provisions of the Contract Documents.will not release CONTRACTOR from liability.5. CONTRACTOR is adiudged bankrupt or insolvent: 15.03 OWNER May Terminate For Convenience6. CONTRACTOR makes a general assignment for the A. Upon seven days written notice to CONbenefitof creditors:TRACTOR and ENGINEER, OWNER may, without causeand without prejudice to any other right or remedy of7. Trustee or receiver is appointed for the OWNER, elect to terminate or discontinue, in whole or inCONTRACTOR or for any of CONTRACTOR'S pgq,-the Contract. In such case, CONTRACTOR shall beproperty:paid (without duplication of any items):8. CONTRACTOR files a petition to take advantage of 1. for completed and acceptable Work executed inany debtor's act, or to reor.ganize under the accordance with the Contract Documents prior to thebankruptcy or applicable laws:effective date of termination, including fair and reasonablesums for overhead and profit on such Work;9. CONTRACTOR repeatedly fails to make promptpayments to <strong>Subcontractors</strong> or Material Suppliers 2. for expenses sustained prior to the effective date offor labor, materials or equipment:termination in performing services and furnishing labor,materials, or equipment as required by the ContractEJCDC No. 1910-8 (1996 Edition) 00 72 00 -46w/ JJG Modifications (Rev03/06109)
Documents in connection with uncompleted Work, plus fair 10.05, OWNER and CONTRACTOR may exercise suchand reasonable sums for overhead and profit on such rights or remedies as either may otherwise have under theexpenses;Contract Documents or by Laws or Regulations in respectof any dispute. CONTRACTOR shall carry on the Work3. for all claims, costs, losses, and damages (including but and maintain the progress schedule during the disputenot limited to all fees and charges of engineers, architects, resolution proceedings, unless otherwise agreed byattorneys, and other professionals and all court or arbitration CONTRACTOR and OWNER in writing.or other dispute resolution costs) incurred in settlement ofterminated contracts with <strong>Subcontractors</strong>, Suppliers, and ARTICLE 17 - MISCELLANEOUSothers; and17.01 Giving Notice4. for reasonable expenses directly attributable totermination. A. Whenever any provision of the ContractDocuments requires the giving of written notice, it will beB. CONTRACTOR shall not be paid on account of deemed to have been validly given if delivered in person toloss of anticipated profits or revenue or other economic loss the individual or to a member of the firm or to an officer ofarising out of or resulting from such termination,the corporation for whom it is intended, or if delivered at orsent by registered or certified mail, postage prepaid, to the15.04 CONTRACTOR May Stop Work or Terminate last business address known to the giver of the notice.A. If, through no act or fault of CONTRACTOR, the B. All notices required of the CONTRACTOR shall beWork is suspended for more than 90 consecutive days by performed in writing to the appropriate entityOWNER or under an order of court or other publicauthority, or ENGINEER fails to act on any Application for 17.02 Computation of TimesPayment within 30 days after it is submitted, or OWNERfails for 30 days to pay CONTRACTOR any sum finallyA. When any period of time is referred to in thedetermined to be due, then CONTRACTOR may, upon Contract Documents by days, it will be computed to excludeseven days written notice to OWNER and ENGINEER, and the first and include the last day of such period. If the lastprovided OWNER or ENGINEER do not remedy such day of any such period falls on a Saturday or Sunday or on asuspension or failure within that time, terminate the day made a legal holiday by the law of the applicableContract and recover from OWNER payment on the same jurisdiction, such day will be omitted from the computation.terms as provided in paragraph 15.03. In lieu of terminatingthe Contract and without prejudice to any other right or 17.03 Cumulative Remediesremedy, if ENGINEER has failed to act on an Applicationfor Payment within 30 days after it is submitted, orA. The duties and obligations imposed by theseOWNER has failed for 30 days to pay CONTRACTOR any General Conditions and the rights and remedies availablesum finally determined to be due, CONTRACTOR may, hereunder to the parties hereto are in addition to, and are notseven days after written notice to OWNER and to be construed in any way as a limitation of, any rights andENGINEER, stop the Work until payment is made of all remedies available to any or all of them which are otherwisesuch amounts due CONTRACTOR, including interest imposed or available by Laws or Regulations, by specialthereon. The provisions of this paragraph 15.04 are not warranty or guarantee, or by other provisions of theintended to preclude CONTRACTOR from making a Claim Contract Documents, and the provisions of this paragraphunder paragraph 10.05 for an adjustment in Contract Price will be as effective as if repeated specifically in the Contractor Contract Times or otherwise for expenses or damage Documents in connection with each particular duty,directly attributable to CONTRACTOR's stopping the obligation, right, and remedy to which they apply.Work as permitted by this paragraph.17.04 Survival of ObligationsARTICLE 16 - DISPUTE RESOLUTIONA. All representations, indemnifications, warranties,16.01 Methods and Procedures and guarantees made in, required by, or given in accordancewith the Contract Documents, as well as all continuingA. Dispute resolution methods and proce- obligations indicated in the Contract Documents, willdures, if any, shall be as set forth in the Supplementary survive final payment, completion, and acceptance of theConditions. If no method and procedure has been set Work or termination or completion of the Agreement.forth, and subject to the provisions of paragraphs 9.09 andEJCDC No. 1910-8 (1996 Edition) 00 7200-47w/ JJG Modifications (Rev03/06/08)
- Page 1 and 2:
ADDENDUM XDATE: May 19, 2008TO:FROM
- Page 3 and 4:
( 0ORO t'The Unified Government of
- Page 5 and 6:
R: No change to bid date.3- Q: (AG)
- Page 7 and 8:
Part IGeneralSection 01 57 00Enviro
- Page 9 and 10:
005700-3Environmental and Property
- Page 11 and 12:
JORDANJONES &SGOULDINGList of Planh
- Page 13 and 14:
List of Planholders, Athens North O
- Page 15 and 16:
RADDENDUM IXDATE: May 16, 2008TO:FR
- Page 17 and 18:
AGREEMENT BETWEENBUYER AND SELLERFO
- Page 19 and 20:
* Delete page 00520-5 and replace w
- Page 21 and 22:
otherwise.F. Should either party re
- Page 23 and 24:
4gas well as construction of the la
- Page 25 and 26:
QUESTIONS AND RESPONSES NO. 5NORTH
- Page 27 and 28:
Also on drawing 05-CD-1 typical roa
- Page 29 and 30:
R: No change will be made to the do
- Page 31 and 32:
R: Apply protective liner to all in
- Page 33 and 34:
16. Q: (AS)Section 0421.13 - Page 5
- Page 35 and 36:
induction motor data sheet.a) Is th
- Page 37 and 38:
conduit size for P39 to be 1-1/2".
- Page 39 and 40:
R: No change will be made to the do
- Page 41 and 42:
(TC)(TDC)(TDH)(TF)(TI)(TJL)(WGH)(WS
- Page 43 and 44:
(1)Section 00 41 00BidTO:UNIFIED GO
- Page 45 and 46:
004100-3Bidf. Utility Location Allo
- Page 47 and 48:
004100-5BidIte No Decito Qty uni Un
- Page 49 and 50:
0041 00-7BidIte No. Decito t.UiSUi
- Page 51 and 52:
004100-9BidMAJOR PRODUCT OR SYSTEM
- Page 53 and 54:
0041 00-11BidThe Bidder agrees here
- Page 55 and 56:
EQUIPMENT ALLOWANCE SCOPE OF WORKRE
- Page 57 and 58:
March 7, 2008 Amended May 13, 2008T
- Page 59 and 60:
System Controls:Not included in thi
- Page 61 and 62:
* No performance and laboratory tes
- Page 63 and 64:
C. Seller is familiar with and is s
- Page 65 and 66:
Project: Athens, GA North Oconee Ma
- Page 67 and 68:
ARTICLE 4 -BASIS OF PROPOSAL4.01 Pr
- Page 69 and 70:
Weir Specialty PumpsP.O. Box209 (84
- Page 71 and 72:
ATHENS, GA 7 NORTH OCONEE May 12,20
- Page 73 and 74:
Weir Specialty PumpsWEiRco PUMPWEMI
- Page 75 and 76:
1635W. Walnut StreetTU R B LEX Spri
- Page 77 and 78:
B. $ 33,658.00 The Seller's monthly
- Page 79 and 80:
Quotation # 08RAS-027-01Yancey Powe
- Page 81 and 82:
-k 0Quotation # O8RAS-027-01Yancey
- Page 83 and 84:
Quotation # OBRAS-027-01Yaney Power
- Page 85 and 86:
- Quotation # O8RAS-027-01Yaney pow
- Page 87 and 88:
Quotation #- OSRAS-027-01' Yancey25
- Page 89 and 90:
Quotation # 08RAS-027-01Yancey Povw
- Page 91 and 92:
NPMwerSystms.259 I.eeilndustrW Bilv
- Page 93 and 94:
Dubin, GregFrom:Sent:To:Cc:Subject:
- Page 95 and 96:
SUPPLEMENTARY CONDITIONS (Rev. 1)Th
- Page 97 and 98:
SC 15: Add the followtng paragraph:
- Page 99 and 100:
0 0 0C3) cm C C Ccm 0ES 20 ESw'-a m
- Page 101 and 102:
U) SL ct )0 nm 0UCV 0 LC,9 . Q o1 f
- Page 103 and 104:
QUESTIONS AND RESPONSES NO. 4NORTH
- Page 105 and 106:
would the OCP policy not be enough
- Page 107 and 108:
properties used in it methods allow
- Page 109 and 110:
12. Q: (TC) SECTION 31 23 60 - 5 ME
- Page 111 and 112:
R: Refer to 05-CU drawings and Spec
- Page 113 and 114: R: See subsequent addenda.Zone 2 84
- Page 115 and 116: actually a refractor 545 or if a re
- Page 117 and 118: ~vRk0 oRADDENDUM IIDATE: April 15,
- Page 119 and 120: STANDARDGENERAL CONDITIONSOF THECON
- Page 121 and 122: GENERAL CONDITIONSARTICLE 1 - DEFIN
- Page 123 and 124: 29. Notice to Proceed--A written no
- Page 125 and 126: within the Contract Time, or extend
- Page 127 and 128: others as appropriate will be held
- Page 129 and 130: 3.04 Amending and Supplementing Con
- Page 131 and 132: a. reviewing and checking all such
- Page 133 and 134: Documents. CONTRACTOR shall also fu
- Page 135 and 136: 5. allow for partial utilization of
- Page 137 and 138: ARTICLE 6 - CONTRACTOR'S RESPONSIBI
- Page 139 and 140: substitte item will perform adequat
- Page 141 and 142: permits and licenses. CONTRACTOR sh
- Page 143 and 144: esponse to such an emergency, a Wor
- Page 145 and 146: 1. is attributable to bodily injury
- Page 147 and 148: 8-05 Lands andEasements; Reports an
- Page 149 and 150: accordance with the provisions of p
- Page 151 and 152: such Claim, dispute, or other matte
- Page 153 and 154: equipment brought to the Project if
- Page 155 and 156: the ENGINEER and the other party to
- Page 157 and 158: incorporation in the Work. Such ins
- Page 159 and 160: ARTICLE 14 - PAYMENTS TO CONTRACTOR
- Page 161 and 162: 2. Should CONTRACTOR neglect to pay
- Page 163: 14.07 Final Payment ENGINEER will r
- Page 167 and 168: ADDENDUM VillDATE: May 15, 2008TO:F
- Page 169 and 170: tRkzZRDrawings1. Delete Sheet 05-SE
- Page 171 and 172: Copyright C 2 000National Society o
- Page 173 and 174: AGREEMENT... THIS AGREEMENTi betwee
- Page 175 and 176: 6.04 Seller and Buyer shall execute
- Page 177 and 178: D. The Contract Documents may only
- Page 179 and 180: ATTACHMENT ASnecificationsSection T
- Page 181 and 182: PROPOSAL FORMPRESELECTED EQUIPMENT
- Page 183 and 184: ARTICLE 4 - BASIS OF PROPOSAL4.01 P
- Page 185 and 186: PARKSON CORPORATIONUnanimous Writte
- Page 187 and 188: Hanson, RickFrom:MAHONEY770@aol.com
- Page 189 and 190: Furt-her,.p ease advise me ifyou wi
- Page 191 and 192: Copyright 02000National Society of
- Page 193 and 194: AGREEMENTTHIS AGREEMENT is between(
- Page 195 and 196: 6.04 Seller and Buyer shalt execute
- Page 197 and 198: ARTICLE 11 - MISCELLANEOUS11.01 Def
- Page 199 and 200: ATTACHMENT ASpecificationsSection T
- Page 201 and 202: SIEMENSCOST PROPOSALOdor Control (B
- Page 203 and 204: SIEMENSTABLE OF CONTENTSNo.Item Des
- Page 205 and 206: ARTICLE 1- PROPOSAL RECIPIENT1.01 T
- Page 207 and 208: 6,02 The following documents are in
- Page 209 and 210: SIEMENSSECTION 2SIEMENS' DETAILED S
- Page 211 and 212: SIEMENSTransfbrmer, Circuit breaker