A. When CONTRACTOR considers the entire Work 14.05 Partial Utilizationready for its intended use CONTRACTOR shall notifyOWNER and ENGINEER in writing that the entire Work is A. Use by OWNER at OWNER's option of anysubstantially complete (except for items specifically listed substantially completed part of the Work which hasby CONTRACTOR as incomplete) and request that specifically been identified in the Contract Documents, orENGINEER issue a certificate of Substantial Completion. which OWNER, ENGINEER, and CONTRACTOR agreePromptly thereafter, OWNER, CONTRACTOR, and constitutes a separately functioning and usable part of theENGINEER shall make an inspection of the Work to Work that can be used by OWNER for its intended purposedetermine the status of completion. If ENGINEER does not without significant interference with CONTRACTOR'sconsider the Work substantially complete, ENGINEER will performance of the remainder of the Work, may benotify CONTRACTOR in writing giving the reasons accomplished prior to Substantial Completion of all thetherefor. If ENGINEER considers the Work substantially Work subject to the following conditions.complete, ENGINEER will prepare and deliver to OWNERa tentative certificate of Substantial Completion which shall 1. OWNER at any time may request CONTRACTOR infix the date of Substantial Completion. There shall be writing to permit OWNER to use any such part of the Workattached to the certificate a tentative list of items to be which OWNER believes to be ready for its intended use andcompleted or corrected before final payment. OWNER substantially complete. If CONTRACTOR agrees that suchshall have seven days after receipt of the tentative certificate part of the Work is substantially complete, CONTRACTORduring which to make written objection to ENGINEER as will certify to OWNER and ENGINEER that such part ofto any provisions of the certificate or attached list. If, after the Work is substantially complete and request ENGINEERconsidering such objections, ENGINEER concludes that the to issue a certificate of Substantial Completion for that partWork is not substantially complete, ENGINEER will within of the Work. CONTRACTOR at any time may notify14 days after submission of the tentative certificate to OWNER and ENGINEER in writing that CONTRACTOROWNER notify CONTRACTOR in writing, stating the considers any such part of the Work ready for its intendedreasons therefor. If, after consideration of OWNER's use and substantially complete and request ENGINEER toobjections, ENGINEER considers the Work substantially issue a certificate of Substantial Completion for that part ofcomplete, ENGINEER will within said 14 days execute and the Work. Within a reasonable time after either suchdeliver to OWNER and CONTRACTOR a definitive request, OWNER, CONTRACTOR, and ENGINEER shallcertificate of Substantial Completion (with a revised make an inspection of that part of the Work to determine itstentative list of items to be completed or corrected) status of completion. If ENGINEER does not consider thatreflecting such changes from the tentative certificate as part of the Work to be substantially complete, ENGINEERENGINEER believes justified after consideration of any will notify OWNER and CONTRACTOR in writing givingobjections from OWNER. At the time of delivery of the the masons therefor. If ENGINEER considers that part oftentative certificate of Substantial Completion ENGINEER the Work to be substantially complete, the provisions ofwill deliver to OWNER and CONTRACTOR a written paragraph 14.04 will apply with respect to certification ofrecommendation as to division of responsibilities pending Substantial Completion of that part of the Work and thefinal payment between OWNER and CONTRACTOR with division of responsibility in respect thereof and accessrespect to security, operation, safety, and protection of the thereto.Work, maintenance, heat, utilities, insurance, and warrantiesand guarantees. Unless OWNER and CONTRACTOR 2. No occupancy or separate operation of part of theagree otherwise in writing and so inform ENGINEER in Work may occur prior to compliance with the requirementswriting prior to ENGINEER's issuing the definitive of paragraph 5.10 regarding property insurance.certificate of Substantial Completion, ENGINEER'saforesaid recommendation will be binding on OWNER and 14.06 Final InspectionCONTRACTOR until final payment.A. Upon written notice from CONTRACTOR thatB. OWNER shall have the right to exclude the entire Work or an agreed portion thereof is complete,CONTRACTOR from the Site after the date of Substantial ENGINEER will promptly make a final inspection withCompletion, but OWNER shall allow CONTRACTOR OWNER and CONTRACTOR and will notify CONreasonableaccess to complete or correct items on thetentative list.TRACTOR in writing of all particulars in which thisinspection reveals that the Work is incomplete or defective.CONTRACTOR shall immediately take such measures asare necessary to complete such Work or remedy suchdeficiencies.EJCDC No. 1910-8 (1996 Edition) 007200-44w/ JJG Modifications (Rev03/06/08)
14.07 Final Payment ENGINEER will return the Application for Payment toCONTRACTOR, indicating in writing the reasons forA. Application for Payment refusing to recommend final payment, in which case CON-TRACTOR shall make the necessary corrections and1. After CONTRACTOR has, in the opinion of resubmit the Application for Payment.ENGINEER, satisfactorily completed all correctionsidentified during the final inspection and has delivered, inC. Payment Becomes Dueaccordance with the Contract Documents, all maintenanceand operating instructions, schedules, guarantees, Bonds, 1. Thwii-Fort-Fivc days after the presentation to OWNcertificatesor other evidence of insurance certificates of ER of the Application for Payment and accompanyinginspection, marked-up record documents (as provided in documentation, the amount recommended by ENGINEERparagraph 6.12), and other documents, CONTRACTOR will become due and, when due, will be paid by OWNER tomay make application for final payment following the CONTRACTOR.procedure for progress payments.14.08 Final Completion Delayed2. The final Application for Payment shall be accompanied(except as previously delivered) by: (i) all A. If, through no fault of CONTRACTOR, finaldocumentation called for in the Contract Documents, completion of the Work is significantly delayed, and ifincluding but not limited to the evidence of insurance ENGINEER so confirms, OWNER shall, upon receipt ofrequired by subparagraph 5.04.B.7; (ii) consent of the CONTRACTOR's final Application for Payment andsurety, if any, to final payment; and (iii) complete and recommendation of ENGINEER, and without terminatinglegally effective releases or waivers (satisfactory to the Agreement, make payment of the balance due for thatOWNER) of all Lien rights arising out of or Liens filed in portion of the Work filly completed and accepted. If theconnection with the Work.remaining balance to be held by OWNER for Work notfully completed or corrected is less than the retainage3. In lieu of the releases or waivers of Liens specified in stipulated in the Agreement, and if Bonds have beenparagraph 14.07.A.2 and as approved by OWNER, fimished as required in paragraph 5.01, the written consentCONTRACTOR may furnish receipts or releases in full and of the surety to the payment of the balance due for thatan affidavit of CONTRACTOR that: (i) the releases and portion of the Work fully completed and accepted shall bereceipts include all labor, services, material, and equipment submitted by CONTRACTOR to ENGINEER with thefor which a Lien could be filed; and (ii) all payrolls, Application for such payment. Such payment shall be madematerial and equipment bills, and other indebtedness under the terms and conditions governing final payment,connected with the Work for which OWNER or OWNER'sproperty might in any way be responsible have been paid orotherwise satisfied. If any Subcontractor or Supplier fhls to 14.09 Waiver of Claimsfurnish such a release or receipt in full, CONTRACTORexcept that it shall not constitute a waiver of Claims.may furnish a Bond or other collateral satisfactory to A. The making and acceptance of final payment willOWNER to indenify OWNER against any Lien.constitute:B. Review ofApplication and Acceptance 1. a waiver of all Claims by OWNER againstCONTRACTOR, except Claims arising from unsettled1. If, on the basis of ENGINEER's observation of the Liens, from defective Work appearing after final inspectionWork during construction and final inspection, and pursuant to paragraph 14.06, from failure to comply withENGINEER's review of the final Application for Payment the Contract Documents or the terms of any specialand accompanying documentation as required by the guarantees specified therein, or from CONTRACTOR'sContract Documents, ENGINEER is satisfied that the Work continuing obligations under the Contract Documents; andhas been completed and CONTRACTOR's otherobligations under the Contract Documents have been 2. a waiver of all Claims by CONTRACTOR againstfulfilled, ENGINEER will, within ten days after receipt of OWNER other than those previously made in writing whichthe final Application for Payment, indicate in writingENGINEER's recommendation of payment and present theApplication for Payment to OWNER for payment. At thesame time ENGINEER will also give written notice toOWNER and CONTRACTOR that the Work is acceptablesubject to the provisions of paragraph 14,09. Otherwise,are still unsettled.EJCDC No. 1910-8 (1996 Edition) 007200-45w/ JiG Modifications (Rev03/06/08)
- Page 1 and 2:
ADDENDUM XDATE: May 19, 2008TO:FROM
- Page 3 and 4:
( 0ORO t'The Unified Government of
- Page 5 and 6:
R: No change to bid date.3- Q: (AG)
- Page 7 and 8:
Part IGeneralSection 01 57 00Enviro
- Page 9 and 10:
005700-3Environmental and Property
- Page 11 and 12:
JORDANJONES &SGOULDINGList of Planh
- Page 13 and 14:
List of Planholders, Athens North O
- Page 15 and 16:
RADDENDUM IXDATE: May 16, 2008TO:FR
- Page 17 and 18:
AGREEMENT BETWEENBUYER AND SELLERFO
- Page 19 and 20:
* Delete page 00520-5 and replace w
- Page 21 and 22:
otherwise.F. Should either party re
- Page 23 and 24:
4gas well as construction of the la
- Page 25 and 26:
QUESTIONS AND RESPONSES NO. 5NORTH
- Page 27 and 28:
Also on drawing 05-CD-1 typical roa
- Page 29 and 30:
R: No change will be made to the do
- Page 31 and 32:
R: Apply protective liner to all in
- Page 33 and 34:
16. Q: (AS)Section 0421.13 - Page 5
- Page 35 and 36:
induction motor data sheet.a) Is th
- Page 37 and 38:
conduit size for P39 to be 1-1/2".
- Page 39 and 40:
R: No change will be made to the do
- Page 41 and 42:
(TC)(TDC)(TDH)(TF)(TI)(TJL)(WGH)(WS
- Page 43 and 44:
(1)Section 00 41 00BidTO:UNIFIED GO
- Page 45 and 46:
004100-3Bidf. Utility Location Allo
- Page 47 and 48:
004100-5BidIte No Decito Qty uni Un
- Page 49 and 50:
0041 00-7BidIte No. Decito t.UiSUi
- Page 51 and 52:
004100-9BidMAJOR PRODUCT OR SYSTEM
- Page 53 and 54:
0041 00-11BidThe Bidder agrees here
- Page 55 and 56:
EQUIPMENT ALLOWANCE SCOPE OF WORKRE
- Page 57 and 58:
March 7, 2008 Amended May 13, 2008T
- Page 59 and 60:
System Controls:Not included in thi
- Page 61 and 62:
* No performance and laboratory tes
- Page 63 and 64:
C. Seller is familiar with and is s
- Page 65 and 66:
Project: Athens, GA North Oconee Ma
- Page 67 and 68:
ARTICLE 4 -BASIS OF PROPOSAL4.01 Pr
- Page 69 and 70:
Weir Specialty PumpsP.O. Box209 (84
- Page 71 and 72:
ATHENS, GA 7 NORTH OCONEE May 12,20
- Page 73 and 74:
Weir Specialty PumpsWEiRco PUMPWEMI
- Page 75 and 76:
1635W. Walnut StreetTU R B LEX Spri
- Page 77 and 78:
B. $ 33,658.00 The Seller's monthly
- Page 79 and 80:
Quotation # 08RAS-027-01Yancey Powe
- Page 81 and 82:
-k 0Quotation # O8RAS-027-01Yancey
- Page 83 and 84:
Quotation # OBRAS-027-01Yaney Power
- Page 85 and 86:
- Quotation # O8RAS-027-01Yaney pow
- Page 87 and 88:
Quotation #- OSRAS-027-01' Yancey25
- Page 89 and 90:
Quotation # 08RAS-027-01Yancey Povw
- Page 91 and 92:
NPMwerSystms.259 I.eeilndustrW Bilv
- Page 93 and 94:
Dubin, GregFrom:Sent:To:Cc:Subject:
- Page 95 and 96:
SUPPLEMENTARY CONDITIONS (Rev. 1)Th
- Page 97 and 98:
SC 15: Add the followtng paragraph:
- Page 99 and 100:
0 0 0C3) cm C C Ccm 0ES 20 ESw'-a m
- Page 101 and 102:
U) SL ct )0 nm 0UCV 0 LC,9 . Q o1 f
- Page 103 and 104:
QUESTIONS AND RESPONSES NO. 4NORTH
- Page 105 and 106:
would the OCP policy not be enough
- Page 107 and 108:
properties used in it methods allow
- Page 109 and 110:
12. Q: (TC) SECTION 31 23 60 - 5 ME
- Page 111 and 112: R: Refer to 05-CU drawings and Spec
- Page 113 and 114: R: See subsequent addenda.Zone 2 84
- Page 115 and 116: actually a refractor 545 or if a re
- Page 117 and 118: ~vRk0 oRADDENDUM IIDATE: April 15,
- Page 119 and 120: STANDARDGENERAL CONDITIONSOF THECON
- Page 121 and 122: GENERAL CONDITIONSARTICLE 1 - DEFIN
- Page 123 and 124: 29. Notice to Proceed--A written no
- Page 125 and 126: within the Contract Time, or extend
- Page 127 and 128: others as appropriate will be held
- Page 129 and 130: 3.04 Amending and Supplementing Con
- Page 131 and 132: a. reviewing and checking all such
- Page 133 and 134: Documents. CONTRACTOR shall also fu
- Page 135 and 136: 5. allow for partial utilization of
- Page 137 and 138: ARTICLE 6 - CONTRACTOR'S RESPONSIBI
- Page 139 and 140: substitte item will perform adequat
- Page 141 and 142: permits and licenses. CONTRACTOR sh
- Page 143 and 144: esponse to such an emergency, a Wor
- Page 145 and 146: 1. is attributable to bodily injury
- Page 147 and 148: 8-05 Lands andEasements; Reports an
- Page 149 and 150: accordance with the provisions of p
- Page 151 and 152: such Claim, dispute, or other matte
- Page 153 and 154: equipment brought to the Project if
- Page 155 and 156: the ENGINEER and the other party to
- Page 157 and 158: incorporation in the Work. Such ins
- Page 159 and 160: ARTICLE 14 - PAYMENTS TO CONTRACTOR
- Page 161: 2. Should CONTRACTOR neglect to pay
- Page 165 and 166: Documents in connection with uncomp
- Page 167 and 168: ADDENDUM VillDATE: May 15, 2008TO:F
- Page 169 and 170: tRkzZRDrawings1. Delete Sheet 05-SE
- Page 171 and 172: Copyright C 2 000National Society o
- Page 173 and 174: AGREEMENT... THIS AGREEMENTi betwee
- Page 175 and 176: 6.04 Seller and Buyer shall execute
- Page 177 and 178: D. The Contract Documents may only
- Page 179 and 180: ATTACHMENT ASnecificationsSection T
- Page 181 and 182: PROPOSAL FORMPRESELECTED EQUIPMENT
- Page 183 and 184: ARTICLE 4 - BASIS OF PROPOSAL4.01 P
- Page 185 and 186: PARKSON CORPORATIONUnanimous Writte
- Page 187 and 188: Hanson, RickFrom:MAHONEY770@aol.com
- Page 189 and 190: Furt-her,.p ease advise me ifyou wi
- Page 191 and 192: Copyright 02000National Society of
- Page 193 and 194: AGREEMENTTHIS AGREEMENT is between(
- Page 195 and 196: 6.04 Seller and Buyer shalt execute
- Page 197 and 198: ARTICLE 11 - MISCELLANEOUS11.01 Def
- Page 199 and 200: ATTACHMENT ASpecificationsSection T
- Page 201 and 202: SIEMENSCOST PROPOSALOdor Control (B
- Page 203 and 204: SIEMENSTABLE OF CONTENTSNo.Item Des
- Page 205 and 206: ARTICLE 1- PROPOSAL RECIPIENT1.01 T
- Page 207 and 208: 6,02 The following documents are in
- Page 209 and 210: SIEMENSSECTION 2SIEMENS' DETAILED S
- Page 211 and 212: SIEMENSTransfbrmer, Circuit breaker