control of a Subcontractor or Supplier shall be deemed to be A. OWNER, ENGINEER, ENGINEER's Condelayswithin the control of CONTRACTOR.sultants, other representatives and personnel of OWNER,independent testing laboratories, and governmental agencies12.05 Delays Beyond OWNER's and CONTRACTOR's with jurisdictional interests will have access to the Site andControl the Work at reasonable times for their observation,inspecting, and testing. CONTRACTOR shall provideA. Where CONTRACTOR is prevented from them proper and safe conditions for such access and advisecompleting any part of the Work within the Contract Times them of CONTRACTOR's Site safety procedures and(or Milestones) due to delay beyond the control of both programs so that they may comply therewith as applicable.OWNER and CONTRACTOR, an extension of theContract Times (or Milestones) in an amount equal to the 13.03 Tests and Inspectionstime lost due to such delay shall be CONTRACTOR's soleand exclusive remedy for such delay. A. CONTRACTOR is responsible for the initial andsubsequent inspections of CONTRACTOR's Work to12.06 Delay Damages ensure that the Work conforms with the ContractDocuments. CONTRACTOR shall give ENGINEERA. In no event shall OWNER or ENGINEER be timely notice of readiness of the Work for all requiredliable to CONTRACTOR, any Subcontractor, any Supplier, inspections, tests, or approvals and shall cooperate withor any other person or organization, or to any surety for or inspection and testing personnel to facilitate requiredemployee or agent of any of them, for damages arising out inspections or tests. The CONTRACTOR shall establishof or resulting from:an inspection program and a testing plan acceptable to theENGINEER and shall maintain complete inspection and1. delays caused by or within the control of CONTRAC- testing records available to ENGINEERTOR; orB. OWNER shall employ and pay for the services of2. delays beyond the control of both OWNER and an independent testing laboratory to perform all non-CONTRACTOR including but not limited to fires, floods, CONTRACTOR inspections, tests, or approvals required byepidemics, abnormal weather conditions, freight embargo. the Contract Documents except:acts of war (declared or not declared), acts of God, or actsor neglect by utility owners or other contractors performing 1. for inspections, tests, or approvals covered byother work as contemplated by Article 7: or-paragraphs 13.03.C and 13.03.1 below;3. Acts of Terrorism 2. that costs incurred in connection with tests orinspections conducted pursuant to paragraph 13.04.B shallB. Nothing in this paragraph 12.06 bars a change in be paid as provided in said paragraph 13.04.B; andContract Price pursuant to this Article 12 to compensateCONTRACTOR due to delay, interference, or disruption 3. as otherwise specifically provided in the Contractdirectly attributable to actions or inactions of OWNER or Documents.anyone for whom OWNER is responsible.C. If Laws or Regulations of any public body havingARTICLE 13 - TESTS AND INSPECTIONS jurisdiction require any Work (or part thereof) specificallyCORRECTION, REMOVAL OR ACCEPTANCE OF to be inspected, tested, or approved by an employee or otherDEFECTIVE WORKrepresentative of such public body, CONTRACTOR shallassume fill responsibility for arranging and obtaining such13.01 Notice of Defects inspections, tests, or approvals, pay all costs in connectiontherewith, and furnish ENGINEER the required certificatesA. Prompt notice of all defective Work of which of inspection or approval.OWNER or ENGINEER has actual knowledge will begiven to CONTRACTOR. All defective Work may be D. CONTRACTOR shall be responsible forrejected, corrected, or accepted as provided in this arranging and obtaining and shall pay all costs in connectionArticle 13.with any inspections, tests, or approvals required forOWNER's and ENGINEER's acceptance of materials or13.02 Access to Work equipment to be incorporated in the Work; or acceptance ofmaterials, mix designs, or equipment submitted for approvalprior to CONTRACTOR's purchase thereof forEJCDC No. 1910-8 (1996 Edition) 007200-38w/ JJG Modifications (Rev03/06/08)
incorporation in the Work. Such inspections, tests, or equipment, or fails to perform the Work in such a way thatapprovals shall be performed by organizations acceptable to the completed Work will conform to the ContractOWNER and ENGINEER.Documents, OWNER may order CONTRACTOR to stopthe Work, or any portion thereof, until the cause for suchE. If any Work (or the work of others) that is to be order has been eliminated; however, this right of OWNERinspected, tested, or approved is covered by CONTRAC- to stop the Work shall not give rise to any duty on the partTOR without written concurrence of ENGINEER, it must, of OWNER to exercise this right for the benefit ofif requested by ENGINEER, be uncovered for observation. CONTRACTOR, any Subcontractor, any Supplier, anyother individual or entity, or any surety for, or employee orF. Uncovering Work as provided in paragraph agent of any of them. If OWNER stops Work under this13.03.E shall be at CONTRACTOR's expense unless CON- paragraph, CONTRACTOR shall not be entitled to anTRACTOR has given ENGINEER timely notice of extension of Contract Time nor increase in Contract Price.CONTRACTOR's intention to cover the same and ENGI-NEER has not acted with reasonable promptness in 13.06 Correction or Removal of Defective Workresponse to such notice.A. CONTRACTOR shall correct all defective Work,13.04 Uncovering Work whether or not fabricated, installed, or completed, or, if theWork has been rejected by ENGINEER, remove it from theA. If any Work is covered contrary to the written Project and replace it with Work that is not defective.request of ENGINEER, it must, if requested by ENGI- CONTRACTOR shall pay all Claims, costs, losses, andNEER, be uncovered for ENGINEER's observation and damages (including but not limited to all fees and charges ofreplaced at CONTRACTOR's expense.engineers, architects, attorneys, and other professionals andall court or arbitration or other dispute resolution costs)B. If ENGINEER considers it necessary or advisable arising out of or relating to such correction or removalthat covered Work be observed by ENGINEER or inspect- (including but not limited to all costs of repair ored or tested by others, CONTRACTOR, at ENGINEER's replacement of work of others). The CONTRACTOR shallrequest, shall uncover, expose, or otherwise make available promptly segregate and remove rejected products from thefor observation, inspection, or testing as ENGINEER may site of the Work.require, that portion of the Work in question, furnishing allnecessary labor, material, and equipment. If it is found that 13.07 Correction Periodsuch Work is defective, CONTRACTOR shall pay allClaims, costs, losses, and damages (including but not A. If within one year after the date of Substantiallimited to all fees and charges of engineers, architects, Completion or such longer period of time as may beattorneys, and other professionals and all court or arbitration prescribed by Laws or Regulations or by the terms of anyor other dispute resolution costs) arising out of or relating to applicable special guarantee required by the Contractsuch uncovering, exposure, observation, inspection, and Documents or by any specific provision of the Contracttesting, and of satisfactory replacement or reconstruction Documents, any Work is found to be defective, or if the(including but not limited to all costs of repair or repair of any damages to the land or areas made availablereplacement of work of others); and OWNER shall be for CONTRACTOR's use by OWNER or permitted byentitled to an appropriate decrease in the Contract Price. If Laws and Regulations as contemplated in paragraph 6.11 .Athe parties are unable to agree as to the amount thereof, is found to be defective, CONTRACTOR shall promptly,OWNER may make a Claim therefor as provided in without cost to OWNER and in accordance with OWNER'sparagraph 10.05. If, however, such Work is not found to be written instructions: (i) repair such defective land or areas,defective, CONTRACTOR shall be allowed an increase in or (ii) correct such defective Work or, if the defective Workthe Contract Price or an extension of the Contract Times (or has been rejected by OWNER, remove it from the ProjectMilestones), or both, directly attributable to such and replace it with Work that is not defective, and (iii)uncovering, exposure, observation, inspection, testing, satisfactorily correct or repair or remove and replace anyreplacement, and reconstruction. If the parties are unable to damage to other Work, to the work of others or other landagree as to the amount or extent thereof, CONTRACTOR or areas resulting therefrom. If CONTRACTOR does notmay make a Claim therefor as provided in paragraph 10.05. promptly comply with the terms of such instructions, or inan emergency where delay would cause serious risk of loss13.05 OWNER May Stop the Work or damage, OWNER may have the defective Workcorrected or repaired or may have the rejected Work re-A. If the Work is defective, or CONTRACTOR fails moved and replaced, and all Claims, costs, losses, andto supply sufficient skilled workers or suitable materials or damages (including but not limited to all fees and charges ofEJCDC No. 1910-8 (1996 Edition) 007200-39w/ JJG Modifications (Rev03/06/08)
- Page 1 and 2:
ADDENDUM XDATE: May 19, 2008TO:FROM
- Page 3 and 4:
( 0ORO t'The Unified Government of
- Page 5 and 6:
R: No change to bid date.3- Q: (AG)
- Page 7 and 8:
Part IGeneralSection 01 57 00Enviro
- Page 9 and 10:
005700-3Environmental and Property
- Page 11 and 12:
JORDANJONES &SGOULDINGList of Planh
- Page 13 and 14:
List of Planholders, Athens North O
- Page 15 and 16:
RADDENDUM IXDATE: May 16, 2008TO:FR
- Page 17 and 18:
AGREEMENT BETWEENBUYER AND SELLERFO
- Page 19 and 20:
* Delete page 00520-5 and replace w
- Page 21 and 22:
otherwise.F. Should either party re
- Page 23 and 24:
4gas well as construction of the la
- Page 25 and 26:
QUESTIONS AND RESPONSES NO. 5NORTH
- Page 27 and 28:
Also on drawing 05-CD-1 typical roa
- Page 29 and 30:
R: No change will be made to the do
- Page 31 and 32:
R: Apply protective liner to all in
- Page 33 and 34:
16. Q: (AS)Section 0421.13 - Page 5
- Page 35 and 36:
induction motor data sheet.a) Is th
- Page 37 and 38:
conduit size for P39 to be 1-1/2".
- Page 39 and 40:
R: No change will be made to the do
- Page 41 and 42:
(TC)(TDC)(TDH)(TF)(TI)(TJL)(WGH)(WS
- Page 43 and 44:
(1)Section 00 41 00BidTO:UNIFIED GO
- Page 45 and 46:
004100-3Bidf. Utility Location Allo
- Page 47 and 48:
004100-5BidIte No Decito Qty uni Un
- Page 49 and 50:
0041 00-7BidIte No. Decito t.UiSUi
- Page 51 and 52:
004100-9BidMAJOR PRODUCT OR SYSTEM
- Page 53 and 54:
0041 00-11BidThe Bidder agrees here
- Page 55 and 56:
EQUIPMENT ALLOWANCE SCOPE OF WORKRE
- Page 57 and 58:
March 7, 2008 Amended May 13, 2008T
- Page 59 and 60:
System Controls:Not included in thi
- Page 61 and 62:
* No performance and laboratory tes
- Page 63 and 64:
C. Seller is familiar with and is s
- Page 65 and 66:
Project: Athens, GA North Oconee Ma
- Page 67 and 68:
ARTICLE 4 -BASIS OF PROPOSAL4.01 Pr
- Page 69 and 70:
Weir Specialty PumpsP.O. Box209 (84
- Page 71 and 72:
ATHENS, GA 7 NORTH OCONEE May 12,20
- Page 73 and 74:
Weir Specialty PumpsWEiRco PUMPWEMI
- Page 75 and 76:
1635W. Walnut StreetTU R B LEX Spri
- Page 77 and 78:
B. $ 33,658.00 The Seller's monthly
- Page 79 and 80:
Quotation # 08RAS-027-01Yancey Powe
- Page 81 and 82:
-k 0Quotation # O8RAS-027-01Yancey
- Page 83 and 84:
Quotation # OBRAS-027-01Yaney Power
- Page 85 and 86:
- Quotation # O8RAS-027-01Yaney pow
- Page 87 and 88:
Quotation #- OSRAS-027-01' Yancey25
- Page 89 and 90:
Quotation # 08RAS-027-01Yancey Povw
- Page 91 and 92:
NPMwerSystms.259 I.eeilndustrW Bilv
- Page 93 and 94:
Dubin, GregFrom:Sent:To:Cc:Subject:
- Page 95 and 96:
SUPPLEMENTARY CONDITIONS (Rev. 1)Th
- Page 97 and 98:
SC 15: Add the followtng paragraph:
- Page 99 and 100:
0 0 0C3) cm C C Ccm 0ES 20 ESw'-a m
- Page 101 and 102:
U) SL ct )0 nm 0UCV 0 LC,9 . Q o1 f
- Page 103 and 104:
QUESTIONS AND RESPONSES NO. 4NORTH
- Page 105 and 106: would the OCP policy not be enough
- Page 107 and 108: properties used in it methods allow
- Page 109 and 110: 12. Q: (TC) SECTION 31 23 60 - 5 ME
- Page 111 and 112: R: Refer to 05-CU drawings and Spec
- Page 113 and 114: R: See subsequent addenda.Zone 2 84
- Page 115 and 116: actually a refractor 545 or if a re
- Page 117 and 118: ~vRk0 oRADDENDUM IIDATE: April 15,
- Page 119 and 120: STANDARDGENERAL CONDITIONSOF THECON
- Page 121 and 122: GENERAL CONDITIONSARTICLE 1 - DEFIN
- Page 123 and 124: 29. Notice to Proceed--A written no
- Page 125 and 126: within the Contract Time, or extend
- Page 127 and 128: others as appropriate will be held
- Page 129 and 130: 3.04 Amending and Supplementing Con
- Page 131 and 132: a. reviewing and checking all such
- Page 133 and 134: Documents. CONTRACTOR shall also fu
- Page 135 and 136: 5. allow for partial utilization of
- Page 137 and 138: ARTICLE 6 - CONTRACTOR'S RESPONSIBI
- Page 139 and 140: substitte item will perform adequat
- Page 141 and 142: permits and licenses. CONTRACTOR sh
- Page 143 and 144: esponse to such an emergency, a Wor
- Page 145 and 146: 1. is attributable to bodily injury
- Page 147 and 148: 8-05 Lands andEasements; Reports an
- Page 149 and 150: accordance with the provisions of p
- Page 151 and 152: such Claim, dispute, or other matte
- Page 153 and 154: equipment brought to the Project if
- Page 155: the ENGINEER and the other party to
- Page 159 and 160: ARTICLE 14 - PAYMENTS TO CONTRACTOR
- Page 161 and 162: 2. Should CONTRACTOR neglect to pay
- Page 163 and 164: 14.07 Final Payment ENGINEER will r
- Page 165 and 166: Documents in connection with uncomp
- Page 167 and 168: ADDENDUM VillDATE: May 15, 2008TO:F
- Page 169 and 170: tRkzZRDrawings1. Delete Sheet 05-SE
- Page 171 and 172: Copyright C 2 000National Society o
- Page 173 and 174: AGREEMENT... THIS AGREEMENTi betwee
- Page 175 and 176: 6.04 Seller and Buyer shall execute
- Page 177 and 178: D. The Contract Documents may only
- Page 179 and 180: ATTACHMENT ASnecificationsSection T
- Page 181 and 182: PROPOSAL FORMPRESELECTED EQUIPMENT
- Page 183 and 184: ARTICLE 4 - BASIS OF PROPOSAL4.01 P
- Page 185 and 186: PARKSON CORPORATIONUnanimous Writte
- Page 187 and 188: Hanson, RickFrom:MAHONEY770@aol.com
- Page 189 and 190: Furt-her,.p ease advise me ifyou wi
- Page 191 and 192: Copyright 02000National Society of
- Page 193 and 194: AGREEMENTTHIS AGREEMENT is between(
- Page 195 and 196: 6.04 Seller and Buyer shalt execute
- Page 197 and 198: ARTICLE 11 - MISCELLANEOUS11.01 Def
- Page 199 and 200: ATTACHMENT ASpecificationsSection T
- Page 201 and 202: SIEMENSCOST PROPOSALOdor Control (B
- Page 203 and 204: SIEMENSTABLE OF CONTENTSNo.Item Des
- Page 205 and 206: ARTICLE 1- PROPOSAL RECIPIENT1.01 T
- Page 207 and 208:
6,02 The following documents are in
- Page 209 and 210:
SIEMENSSECTION 2SIEMENS' DETAILED S
- Page 211 and 212:
SIEMENSTransfbrmer, Circuit breaker