<strong>Project</strong> <strong>450</strong> - <strong>St</strong> <strong>Mary</strong> <strong>Redcliffe</strong> Church, Bristol<br />

<strong>RIBA</strong> <strong>St</strong>age 2 <strong>Report</strong><br />

Overall Outline Cost Plan Summary No 1 20/01/2020<br />

Ref<br />

A<br />

Scope of Works Description<br />

Church Yard North<br />

Approx.<br />

GIFA (m2)<br />

Current Costs Previous Costs Movement Comments<br />

£ £ £<br />

SUMMARY<br />

<strong>RIBA</strong> 2 Total Construction Cost<br />

<strong>RIBA</strong> 1 Total Construction Cost<br />

£8,345,961 (ex VAT)<br />

1 New facilities comprising new café & kitchen, gallery & exhibition space 1,098 £3,579,054 £2,939,000 £640,054<br />

B<br />

Church Yard South<br />

1 Education/Learning Building including new access lift/steps 212 £861,844 £562,200 £299,644<br />

2 Events Building including hard & soft landscaping 381 £1,183,259 £1,010,300 £172,959<br />

C<br />

Consequential Improvements to satisfy Building Regulations<br />

1 Allowance Excl Excl £0 To be confirmed<br />

D<br />

Other Works<br />

1 Proposals for storage and office at Nave Level & Volunteer room £0 £140,500 -£140,500 Works now included in A1 above<br />

2 Proposed Internal Porch to West Door £30,000 £0 £30,000 Additional Works added<br />

3 Allowance to provide new internal exhibition space £50,000 £0 £50,000 Allowance pending scope agreement<br />

4 New Armoire £50,000 £0 £50,000 Part included in D1 previously<br />

£5,754,157 £4,652,000 £1,102,157<br />

D Main Contractor's Preliminaries 16% £923,000 £930,400 -£7,400 Assumes South Church Yard projects share site management facilities<br />

£6,677,157 £5,582,400 £1,094,757<br />

E Main Contractor's Overheads & Profit 7.5% £491,037 £418,680 £72,357<br />

£7,168,194 £6,001,080 £1,167,114<br />

F Professional, Legal, Planning & Building Regulation Fees 16% £1,177,767 £1,086,946 £90,821 18% included for South Church Yard projects & 16% for Undercroft & Hogarth<br />

G<br />

H<br />

Design Development & Construction Risks<br />

Inflation<br />

SUB TOTAL: Facilitating and Building Works<br />

Sub-total<br />

TOTAL: Building Works Estimate<br />

Base Cost Estimate<br />

£8,345,961 £7,088,026 £1,257,935<br />

0.1 Design Development Risks 12% £991,006 £900,162 £90,844<br />

0.2 Construction Risks 0% £0 £0 £0 Included in Design Development Risk above<br />

0.3 Employer Change Risks 5% £0 £345,062 -£345,062 Allocated to building works above<br />

Total Risk Allowance Estimate<br />

Cost Estimate (excluding inflation)<br />

£991,006 £1,245,224 -£254,218<br />

£9,336,968 £8,333,250 £1,003,718<br />

0.1 Tender Inflation 0% Excl Excl £0<br />

0.2 Construction Inflation 0% Excl Excl £0<br />

Cost Estimate (including inflation)<br />

£9,336,968 £8,333,250 £1,003,718<br />

I VAT 20% £1,867,394 £1,666,650 £200,744<br />

TOTALS (incl VAT & Fees) @ Base Date 1Q20<br />

£11,204,000 £10,000,000 £1,204,000<br />

Base Scheme<br />

£7,088,026 (ex VAT)<br />

Enhanced Scheme £8,236,500 (ex VAT) *<br />

including increased:<br />

i) Events Space<br />

ii) Education Space<br />

iii) Nave Level ‘Armoire’<br />

Given that the <strong>RIBA</strong> 2 scheme includes the above increased<br />

provision, the most accurate comparator is the <strong>RIBA</strong> 1 Enhanced<br />

Scheme and, on this basis, project costs can be seen to have<br />

remained relatively consistent through the <strong>RIBA</strong> 2 design<br />

development<br />

However, the impact of both VAT and Quantified Risk Allowance is<br />

such that the forecast Total <strong>Project</strong> Cost now exceeds the agreed<br />

£10m budget by £1,024,000<br />

In relation to this, and to more adequately define the scope for<br />

<strong>RIBA</strong> 3, it is recommended that SMR:<br />

1. Seeks an update on the funding position from the Fundraising<br />

Consultant and, particularly, clarity on whether the anticipated<br />

£10m maximum relates to total construction or total project<br />

cost<br />

2. Seeks clarity from its Financial Advisors on the project’s VAT<br />

status<br />

3. Ensures the separate fundability of the excluded items, such as<br />

FF&E<br />

4. Considers the early undertaking of the suggested further<br />

surveys and investigations to manage the Quantified Risk<br />

Allowance<br />

5. Utilises the suggested review of the South Churchyard Buildings<br />

to achieve efficiencies wherever possible<br />

* As reported in <strong>RIBA</strong> 1 <strong>Report</strong>, July 2019<br />

T:\BLCM\123\MJQ\<strong>St</strong> <strong>Mary</strong> <strong>Redcliffe</strong> Church\2019\December 2019\<strong>RIBA</strong> <strong>St</strong>age 2 <strong>Report</strong>\Cost Plan Jan 20\Draft V1.xlsx