8.0 PROGRAMME<br />

The below-listed programme represents a projection from the current position, based on<br />

anticipated timescales for design development, documentation, and ongoing consultation<br />

It records an overall prolongation of 4 months from the initial programme and, as such, is subject<br />

to client review and approval<br />

Rev B - 16.12.19<br />

ID<br />

Task Task Name Duration <strong>St</strong>art Finish<br />

Mode<br />

1 <strong>RIBA</strong> 1+ 15 days? Mon 01/07/19 Fri 19/07/19<br />

2 <strong>St</strong>art‐Up Meeting 1 day Mon 01/07/19 Mon 01/07/19<br />

5 Masterplan Review 14 days Tue 02/07/19 Fri 19/07/19<br />

3 <strong>Project</strong> Board 1 day? Mon 08/07/19 Mon 08/07/19<br />

4 Cost Review 5 days? Mon 15/07/19 Fri 19/07/19<br />

6 <strong>RIBA</strong> 2 115 days? Mon 22/07/19 Fri 20/12/19<br />

7 On site Review of Proposals 5 days Mon 22/07/19 Fri 26/07/19<br />

8 Scheme Update 15 days Mon 29/07/19 Fri 16/08/19<br />

9 Client Presentation 1 day? Mon 12/08/19 Mon 12/08/19<br />

10 <strong>Project</strong> Board 1 day? Mon 12/08/19 Mon 12/08/19<br />

14 Wider SMR Update 5 days? Tue 13/08/19 Sun 18/08/19<br />

15 Cost Review 6 days Tue 13/08/19 Mon 19/08/19<br />

11 Intervention Details Survey 3 days Mon 19/08/19 Wed 21/08/19<br />

13 Outline Intervention Details 66 days Thu 22/08/19 Mon 18/11/19<br />

12 DAC Pre‐App Meeting 1 day? Wed 28/08/19 Wed 28/08/19<br />

16 Client Presentation 1 day Mon 11/11/19 Mon 11/11/19<br />

17 <strong>Project</strong> Board 1 day? Mon 11/11/19 Mon 11/11/19<br />

18 Engagement with DAC 1 day Mon 11/11/19 Mon 11/11/19<br />

19 Scheme Update 17 days Mon 25/11/19 Mon 16/12/19<br />

20 <strong>RIBA</strong> 3 113 days? Mon 13/01/20 Wed 17/06/20<br />

37 Wider SMR Update 1 day? Mon 10/02/20 Mon 10/02/20<br />

30 Planning / Faculty Scheme<br />

Drawings<br />

25 days Mon 13/01/20 Fri 14/02/20<br />

31 First Draft Visuals 15 days Mon 20/01/20 Fri 07/02/20<br />

33 Client Presentation 1 day? Mon 10/02/20 Mon 10/02/20<br />

38 <strong>Project</strong> Board 1 day? Mon 10/02/20 Mon 10/02/20<br />

32 Wider SMR Update 1 day? Mon 10/02/20 Mon 10/02/20<br />

29 Planning / Faculty Details 15 days Mon 17/02/20 Fri 06/03/20<br />

21 Meeting of PCC 1 day? Mon 24/02/20 Mon 24/02/20<br />

22 <strong>Project</strong> Board 1 day? Mon 09/03/20 Mon 09/03/20<br />

28 First Draft of Drawings Issued 1 day? Mon 09/03/20 Mon 09/03/20<br />

2020<br />

Q2 Q3 Q4 Q1 Q2 Q3<br />

34 Client Review of First Draft 4 days Tue 10/03/20 Fri 13/03/20<br />

35 1:20s / New Details 25 days Mon 16/03/20 Fri 17/04/20<br />

36 <strong>Project</strong> Board 1 day? Mon 13/04/20 Mon 13/04/20<br />

26 DAS / HIA 30 days? Mon 20/04/20 Fri 29/05/20<br />

27 <strong>Project</strong> Board 1 day? Mon 11/05/20 Mon 11/05/20<br />

25 Final Draft of Documentation<br />

Issued<br />

1 day? Mon 01/06/20 Mon 01/06/20<br />

24 Client Review of Final Draft 5 days Tue 02/06/20 Mon 08/06/20<br />

23 Finalising Documentation 4 days Tue 09/06/20 Fri 12/06/20<br />

39 Planning / Faculty Submissions 1 day? Mon 15/06/20 Mon 15/06/20<br />

Task<br />

<strong>Project</strong> Summary<br />

Manual Task<br />

<strong>St</strong>art-only<br />

Deadline<br />

<strong>Project</strong>: SMR<br />

Date: Mon 16/12/19<br />

Split<br />

Milestone<br />

Inactive Task<br />

Inactive Milestone<br />

Duration-only<br />

Manual Summary Rollup<br />

Finish-only<br />

External Tasks<br />

Progress<br />

Manual Progress<br />

Summary<br />

Inactive Summary<br />

Manual Summary<br />

External Milestone<br />

Page 1