8.0 PROGRAMME<br />
The below-listed programme represents a projection from the current position, based on<br />
anticipated timescales for design development, documentation, and ongoing consultation<br />
It records an overall prolongation of 4 months from the initial programme and, as such, is subject<br />
to client review and approval<br />
Rev B - 16.12.19<br />
ID<br />
Task Task Name Duration <strong>St</strong>art Finish<br />
Mode<br />
1 <strong>RIBA</strong> 1+ 15 days? Mon 01/07/19 Fri 19/07/19<br />
2 <strong>St</strong>art‐Up Meeting 1 day Mon 01/07/19 Mon 01/07/19<br />
5 Masterplan Review 14 days Tue 02/07/19 Fri 19/07/19<br />
3 <strong>Project</strong> Board 1 day? Mon 08/07/19 Mon 08/07/19<br />
4 Cost Review 5 days? Mon 15/07/19 Fri 19/07/19<br />
6 <strong>RIBA</strong> 2 115 days? Mon 22/07/19 Fri 20/12/19<br />
7 On site Review of Proposals 5 days Mon 22/07/19 Fri 26/07/19<br />
8 Scheme Update 15 days Mon 29/07/19 Fri 16/08/19<br />
9 Client Presentation 1 day? Mon 12/08/19 Mon 12/08/19<br />
10 <strong>Project</strong> Board 1 day? Mon 12/08/19 Mon 12/08/19<br />
14 Wider SMR Update 5 days? Tue 13/08/19 Sun 18/08/19<br />
15 Cost Review 6 days Tue 13/08/19 Mon 19/08/19<br />
11 Intervention Details Survey 3 days Mon 19/08/19 Wed 21/08/19<br />
13 Outline Intervention Details 66 days Thu 22/08/19 Mon 18/11/19<br />
12 DAC Pre‐App Meeting 1 day? Wed 28/08/19 Wed 28/08/19<br />
16 Client Presentation 1 day Mon 11/11/19 Mon 11/11/19<br />
17 <strong>Project</strong> Board 1 day? Mon 11/11/19 Mon 11/11/19<br />
18 Engagement with DAC 1 day Mon 11/11/19 Mon 11/11/19<br />
19 Scheme Update 17 days Mon 25/11/19 Mon 16/12/19<br />
20 <strong>RIBA</strong> 3 113 days? Mon 13/01/20 Wed 17/06/20<br />
37 Wider SMR Update 1 day? Mon 10/02/20 Mon 10/02/20<br />
30 Planning / Faculty Scheme<br />
Drawings<br />
25 days Mon 13/01/20 Fri 14/02/20<br />
31 First Draft Visuals 15 days Mon 20/01/20 Fri 07/02/20<br />
33 Client Presentation 1 day? Mon 10/02/20 Mon 10/02/20<br />
38 <strong>Project</strong> Board 1 day? Mon 10/02/20 Mon 10/02/20<br />
32 Wider SMR Update 1 day? Mon 10/02/20 Mon 10/02/20<br />
29 Planning / Faculty Details 15 days Mon 17/02/20 Fri 06/03/20<br />
21 Meeting of PCC 1 day? Mon 24/02/20 Mon 24/02/20<br />
22 <strong>Project</strong> Board 1 day? Mon 09/03/20 Mon 09/03/20<br />
28 First Draft of Drawings Issued 1 day? Mon 09/03/20 Mon 09/03/20<br />
2020<br />
Q2 Q3 Q4 Q1 Q2 Q3<br />
34 Client Review of First Draft 4 days Tue 10/03/20 Fri 13/03/20<br />
35 1:20s / New Details 25 days Mon 16/03/20 Fri 17/04/20<br />
36 <strong>Project</strong> Board 1 day? Mon 13/04/20 Mon 13/04/20<br />
26 DAS / HIA 30 days? Mon 20/04/20 Fri 29/05/20<br />
27 <strong>Project</strong> Board 1 day? Mon 11/05/20 Mon 11/05/20<br />
25 Final Draft of Documentation<br />
Issued<br />
1 day? Mon 01/06/20 Mon 01/06/20<br />
24 Client Review of Final Draft 5 days Tue 02/06/20 Mon 08/06/20<br />
23 Finalising Documentation 4 days Tue 09/06/20 Fri 12/06/20<br />
39 Planning / Faculty Submissions 1 day? Mon 15/06/20 Mon 15/06/20<br />
Task<br />
<strong>Project</strong> Summary<br />
Manual Task<br />
<strong>St</strong>art-only<br />
Deadline<br />
<strong>Project</strong>: SMR<br />
Date: Mon 16/12/19<br />
Split<br />
Milestone<br />
Inactive Task<br />
Inactive Milestone<br />
Duration-only<br />
Manual Summary Rollup<br />
Finish-only<br />
External Tasks<br />
Progress<br />
Manual Progress<br />
Summary<br />
Inactive Summary<br />
Manual Summary<br />
External Milestone<br />
Page 1