19.05.2013 Views

View Document Here - Hanford Site

View Document Here - Hanford Site

View Document Here - Hanford Site

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

..^•. ,<br />

Appendix F- Detailed Description of Alternative 3: DoE/itt.2001-1 t<br />

Entombment with Internal Waste Disposal Rev. e a nr•aft B<br />

iicdlinc/Strikcout<br />

1 F.2.1.6 Grout the Operating Gallery. The concrete slab above this gallery is much thicker<br />

2 than the slab on top of the other two galleries, and a different method for grout placement would<br />

3 be used. Like the ventilation tunnel grouting, angled holes would be drilled through the gallery<br />

4 wall to grout the operating gallery. These holes would be sized and located to allow grouting<br />

5 both inside and around the waste-filled containers.<br />

7 F.2.2 Accept Waste for Placement Within Canyon<br />

8<br />

9 At the same time that the galleries are filling, waste placement would begin on the eenyee<br />

10 epertaEingdeek canyon deck . The waste would be placed on the deck in four separate layers.<br />

I 1 Each layer would be grouted as it is placed, and the waste placement would be completed for the<br />

12 entire canyon length by layer prior to starting the next waste layer. Layers of waste would be<br />

13 separated from each other by an approximately 0.75-m (2.5dt)-thick lift of grout. The grout<br />

14 layer provides important shielding to limit operation staff exposure to radiation from the wastes<br />

15 in the layers below. Grout amendments, such as fly ash or zeolite clays, would be considered for<br />

16 the grout to reduce potential for leaching of radioactive isotopes. A summary of steps involved<br />

17 for this part of Alternative 3 follows.<br />

18<br />

19 F.2.2.1 Modify Canyon End Walls. In preparation for waste placement in the canyon, the end<br />

20 walls of the building must be modified. A gridwork of steel beams would be installed on both<br />

(0**'21 the northeast and southwest end walls. This grid would be designed to resist seismic forces and<br />

22 loads applied during the complex's operation period. For the southwest end wall, the<br />

23 modification would include saw cutting an opening in the concrete wall. This opening would be<br />

24 sized to accept the waste containers moved by a forklift. The opening would be covered with a<br />

25 rollup door. The wall's steel beam gridwork would be designed to allow the rollup door to be<br />

26 moved upwards level by level as the waste is placed within the canyon. The gridwork would be<br />

27 anchored to the roof slab and surrounding reinforced walls. Through-bolting would connect the<br />

28 gridwork to the unreinforced concrete end wall.<br />

29<br />

30 F.2.2.2 Fill Ganyon Canvon deck and Craneway with Waste. The eanyex<br />

31 an n deck would be filled with a total of four layers of waste containers. The<br />

32 first three layers would hold a estimated 160 cargo containers each, for a total of 480 containers.<br />

33 The container placement would start at the northeast end of the canyon and advance towards the<br />

34 southwest end. Each layer would be completed prior to placement beginning on the next layer<br />

35 up. This approach would ensure that there would not be a large differential in loading of<br />

36 adjacent building sections.<br />

37<br />

38 Containers would be grouted both inside the container and around their exterior. It is envisioned<br />

39 that grouting would occur roughly every 12 m (40 ft) of building length. Containers would be<br />

40 placed using a forklift with adequate shielding to limit operator exposure to an acceptable level.<br />

41 The containers would be placed two abreast across the canyon deck width. In this manner, the<br />

42 forklift could place the containers without making a 90-degree turn, which would be difficult in<br />

i^43 the limited width of the canyon deck.<br />

44<br />

Final Feasibility Studyjor the Canyon Dispoiition lnitiqfive (221-U Facility)<br />

un ?003 F-18

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!