19.05.2013 Views

View Document Here - Hanford Site

View Document Here - Hanford Site

View Document Here - Hanford Site

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Appendix E - Detailed Description of Alternative 1: Do&R[.-2001-11<br />

I Full Removal and Disposal Rev. 61 Draft<br />

^ Redline/Strikeout<br />

I Removing the roof panel above the end wall, with the end wall in place, could damage the plain<br />

2 concrete, with the risk of collapsing it. The southwest end wall would be dealt with similarly,<br />

3 anytime prior to removal of the adjacent roof panel.<br />

4<br />

5 Wire saws would be used to cut the roof panels from their connection to the walls. The roof<br />

6 panels would be removed from the building as a full (12-m [40-ftl) section. Wire saws would be<br />

7 used on the panel once on the ground to size reduce the panel to an acceptable size for hauling to<br />

8 ERDF.<br />

9<br />

10 Demolition activities would make extensive use of large-capacity cranes for building section<br />

11 removal as each section is cut free by the diamond wire sawing process. Scaffolding would be<br />

12 needed on both sides of each building segment to support the cable-cutting machines.<br />

13<br />

14 Steel beams would be attached lengthwise, on each side of the building, inward from the roof<br />

15 edge, to distribute the lifting forces for the roof slab removal. Bearing plates would probably be<br />

16 required on the bottom of the roof, inside of the canyon, to distribute the lifting forces to the<br />

17 concrete slab. As the cut progresses, wedges or clamps must be placed in the cut to provide<br />

18 vertical support and lateral stability for all concrete sections as cutting continues.<br />

19<br />

20 1 E.2.73 Remove Canyon Walls to Canvon deck Level. Wire saws<br />

.I would be used to cut the wall sections into blocks and the cranes would remove these blocks. A<br />

22 step-by-step approach was evaluated for this removal. The following list provides the<br />

23 approximate order of removal for concrete sections in each building segment:<br />

24<br />

25 • Roof panel as a single section for size reduction on the ground<br />

26 • Bridge cranes<br />

27 • Upper gallery (crane) wall<br />

28 • Upper crane shield wall<br />

29 • Crane gallery floor<br />

30 • Rear (southwest) outside wall (pipe trench side)<br />

31 • Crane gallery floor<br />

32 • Operating gallery outer wall<br />

33 • Operating gallery shield wall<br />

34 • Operating gallery floor<br />

35 • Pipe gallery floor<br />

36 • Outer wall for pipe and electrical gallcries<br />

37 . Cell cover blocks<br />

38 • Cell end walls<br />

39 • Celi dividing walls<br />

40 • Lower gallery shield wall<br />

41 • Pipe trench floor<br />

^42 • Inner pipe trench wall<br />

43 • Exterior pipe trench wall<br />

Flnal Fearlbillty Slady for die Canyon Pirpmirion Iniiiarive (221-U Facility)<br />

June 1003 E-13

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!