View Document Here - Hanford Site
View Document Here - Hanford Site
View Document Here - Hanford Site
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Appendix G - Detailed Description of Alternative 4: DoFJRI.-20oI-1t<br />
^ Entombment with Internal and Eirte'rnal Waste Disposal Rev. I Draft n<br />
Redlinc/Strikeout<br />
1 at the ERDF (Casbon 1995). The 3 horizontal to I vertical (horizontal:vertical) slope for the<br />
2 liner system is anticipated to pose construction challenges because it would need to be built in<br />
3 stages as engineered fill is placed around the facility. The liner starts from the intersection of a<br />
4 45-degree line projected from the bottom slab of 221-U and the bottom of the engineered barrier<br />
5 (see Figure G-2). The liner extends downward toward 221-U and transitions into a flat section<br />
6 prior to intersecting the building's exterior face. An impermeable barrier would also be required<br />
7 along the building face above the liner, and a method for transitioning from the wall to the liner<br />
8 would be defined during final design. To serve the operational period, the building face barrier<br />
9 could use a waterproof-type paint system.<br />
10<br />
l I The area of liner system is estimated as 15,100 mz (162,476 ftz), which includes the 3,800 mz<br />
12 (40,100 ftz) of painted wall area. The total volume available for placement in this external waste<br />
13 disposal area is 50,100 0 (65,463 yd).<br />
14<br />
15 The waste envisioned for placement within this disposal area is soil remediation-type waste. It<br />
16 would be delivered and placed in compacted lifts, from a 0.6-m (2-ft)-thick clean working<br />
17 surface, similar to the ERDF operations. Due to the location of the disposal area, lining and<br />
18 placing waste would be difficult. Irke ERDF, the open working area would be limited to reduce<br />
19 the potential for release of contaminants. Upon completion of waste placement, an interim cap<br />
20 would be placed on the waste. Its purpose would be to limit the potential for infiltration during<br />
^ 21 waste placement activities until the engineered barrier could be constructed during closure<br />
22 activities.<br />
23<br />
24 Construction of the liner system for Alternative 4 would be challenging because it must address<br />
25 scheduling requirements to maintain near-equal levels between internal and external waste<br />
26 placement and the technical issues associated with the liner installation. I.iner installation<br />
27 scheduling could present a delay to the placement of waste internally while the liner system was<br />
28 completed. Technical design issues include selection of an appropriate paint system for the<br />
29 canyon exterior, the connection of the liner to the wall, and a liner system that could be installed<br />
30 satisfactorily in "lifts" over an extended period of time.<br />
31<br />
32<br />
33 G3 CLOSE THE COMPLEX<br />
34<br />
35 This function consists of completing construction of the environmental cap over 221-U,<br />
36 demolition debris, and external waste disposal area that was placed immediately adjacent to it. It<br />
37 would also involve restoring the disturbed sites (access roads and equipment staging areas) to a<br />
38 grade consistent with the natural surface topography. Closure of the complex for Alternative 4<br />
39 would also require institutional controls and maintenance of a monitoring system. Institutional<br />
40 controls could consist of both physical and legal barriers to prevent access to contaminants.<br />
41 A closeout report would be prepared for regulatory agency approval.<br />
42<br />
^ 43 G3.1 Construct Environmental Cap<br />
44<br />
Final Feasibility Stady jor rlu Canyon Disposition Initiative (221-U Facility)<br />
„ • 100 G-20