View Document Here - Hanford Site
View Document Here - Hanford Site
View Document Here - Hanford Site
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Appendix G- Detailed Description of Altemative 4: DoE(Rlr20o1-t 1<br />
^ Entombment with Internal and Extei•nal Waste Disposal Rev. I t>mtt s<br />
RedlinelStrikeout<br />
1 would be the best location to do these activities because it is a closed facility for controlling<br />
2 contamination spread. The most significant contribution to worker exposure under Alternative 4<br />
3 would be the size reduction of the contaminated legacy equipment that is currently slered-on the<br />
4 operating deck. Estimated worker dose for these activities alone is nearly 36 person-tem (I3111<br />
5 2001a). If all of the legacy equipment on the operating deck is substantially reduced in size and<br />
6 volume for placement into the process cells, significant worker time and resulting higher<br />
7 exposures would occur. This activity, even with latest technologies available, would be<br />
8 performed in personal protective equipment-required work areas ( i.e., contaminated areas and<br />
9 airborne areas). Significant engineering controls would be required to reduce worker exposure<br />
10 from external and internal exposure sources. Worker turnover could increase due to harsher<br />
11 working conditions.<br />
12<br />
13 During final design, it is anticipated that emerging size and volume reduction technologies would<br />
14 be evaluated for use. For this final FS, use of conventional size- and volume-reduction<br />
15 technologies is assumed. Disassembly activities would include mechanical cutting, hydraulic<br />
16 shearing, and manual methods. Additional technologies that could be applied are described in<br />
17 Appendix I.<br />
18<br />
19 After the equipment is placed into the process cells, each cell would be coated with a fixative for<br />
20 control of loose surface contamination. Cement grout would be placed in lifts into each process<br />
(0^'21 cell to fill voids. Each lift would be allowed to cura before placing additional lifts. As each<br />
22 process cell is filled, the cover blocks would be placed back int6 position. The volume of void<br />
23 space to be filled within the process cells is conservatively estimated as 50% of total cell volume.<br />
24 Therefore, the grout volume needed to fill the process cells is 3,400 m3 (4,400 yd3). After the<br />
25 process cell cover blocks are in place, holes would be drilled through the covers and any voids<br />
26 under and around the edges of the blocks would be filled by pressure grouting. The cover lifting<br />
27 bails would be removed after pressure grouting is complete.<br />
28<br />
29 In the Phase I FS, consideration had been given to reserving the process cells only for disposal of<br />
30 Class C wastes at 22I-U because of the high degree of isolation and shielding provided by the<br />
31 process cells. However, in this final FS, there is a need to clear the sanyen epereting<br />
32 deekcanvon deck to support building demolition. The removal and disposal of legacy equipment<br />
33 to the process cells would be the most efficient means of achieving this objective. Moreover,<br />
34 while the process cells provide a significant amount of isolation in 221-U as it is currently<br />
35 configumd, after closure activities for Alternative 4, all parts of the 221-U Facility containing<br />
36 waste fill, regardless of the class of waste within, would be equally protected (contained) by an<br />
37 engineered barrier. Therefore, from the standpoint of long-term protectiveness, there is no<br />
38 advantage in reserving the process cells exclusively for Class C waste. However, cell 3, may<br />
39 have room for placement of avaste n+etefiais waste in addition to legacy waste from the canyon<br />
40 #leerdcck.<br />
41<br />
42 All equipment and materials inside the operating gallery must be removed to support placement<br />
("\43 of containerized waste into this gallery. There is a substantial amount of piping in this gallery<br />
44 that requires removal. Conversely, very little equipment and piping would need to be removed<br />
45 to prepare the pipe and electrical galleries ready for waste container placement.<br />
Final Feasibifity StnCy jor llre Canyon Disporition lniriarive (22!•U Faeiirry)<br />
1 00l G-11