19.05.2013 Views

View Document Here - Hanford Site

View Document Here - Hanford Site

View Document Here - Hanford Site

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Appendix G- Detailed Description of Altemative 4: DoE(Rlr20o1-t 1<br />

^ Entombment with Internal and Extei•nal Waste Disposal Rev. I t>mtt s<br />

RedlinelStrikeout<br />

1 would be the best location to do these activities because it is a closed facility for controlling<br />

2 contamination spread. The most significant contribution to worker exposure under Alternative 4<br />

3 would be the size reduction of the contaminated legacy equipment that is currently slered-on the<br />

4 operating deck. Estimated worker dose for these activities alone is nearly 36 person-tem (I3111<br />

5 2001a). If all of the legacy equipment on the operating deck is substantially reduced in size and<br />

6 volume for placement into the process cells, significant worker time and resulting higher<br />

7 exposures would occur. This activity, even with latest technologies available, would be<br />

8 performed in personal protective equipment-required work areas ( i.e., contaminated areas and<br />

9 airborne areas). Significant engineering controls would be required to reduce worker exposure<br />

10 from external and internal exposure sources. Worker turnover could increase due to harsher<br />

11 working conditions.<br />

12<br />

13 During final design, it is anticipated that emerging size and volume reduction technologies would<br />

14 be evaluated for use. For this final FS, use of conventional size- and volume-reduction<br />

15 technologies is assumed. Disassembly activities would include mechanical cutting, hydraulic<br />

16 shearing, and manual methods. Additional technologies that could be applied are described in<br />

17 Appendix I.<br />

18<br />

19 After the equipment is placed into the process cells, each cell would be coated with a fixative for<br />

20 control of loose surface contamination. Cement grout would be placed in lifts into each process<br />

(0^'21 cell to fill voids. Each lift would be allowed to cura before placing additional lifts. As each<br />

22 process cell is filled, the cover blocks would be placed back int6 position. The volume of void<br />

23 space to be filled within the process cells is conservatively estimated as 50% of total cell volume.<br />

24 Therefore, the grout volume needed to fill the process cells is 3,400 m3 (4,400 yd3). After the<br />

25 process cell cover blocks are in place, holes would be drilled through the covers and any voids<br />

26 under and around the edges of the blocks would be filled by pressure grouting. The cover lifting<br />

27 bails would be removed after pressure grouting is complete.<br />

28<br />

29 In the Phase I FS, consideration had been given to reserving the process cells only for disposal of<br />

30 Class C wastes at 22I-U because of the high degree of isolation and shielding provided by the<br />

31 process cells. However, in this final FS, there is a need to clear the sanyen epereting<br />

32 deekcanvon deck to support building demolition. The removal and disposal of legacy equipment<br />

33 to the process cells would be the most efficient means of achieving this objective. Moreover,<br />

34 while the process cells provide a significant amount of isolation in 221-U as it is currently<br />

35 configumd, after closure activities for Alternative 4, all parts of the 221-U Facility containing<br />

36 waste fill, regardless of the class of waste within, would be equally protected (contained) by an<br />

37 engineered barrier. Therefore, from the standpoint of long-term protectiveness, there is no<br />

38 advantage in reserving the process cells exclusively for Class C waste. However, cell 3, may<br />

39 have room for placement of avaste n+etefiais waste in addition to legacy waste from the canyon<br />

40 #leerdcck.<br />

41<br />

42 All equipment and materials inside the operating gallery must be removed to support placement<br />

("\43 of containerized waste into this gallery. There is a substantial amount of piping in this gallery<br />

44 that requires removal. Conversely, very little equipment and piping would need to be removed<br />

45 to prepare the pipe and electrical galleries ready for waste container placement.<br />

Final Feasibifity StnCy jor llre Canyon Disporition lniriarive (22!•U Faeiirry)<br />

1 00l G-11

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!