19.05.2013 Views

View Document Here - Hanford Site

View Document Here - Hanford Site

View Document Here - Hanford Site

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

.. . .,. .. .<br />

Appendix G- Detailed Description of Alternative 4: DoEIRt.-2003-11<br />

Entombment with Internal and External Waste Disposal Rev. l DraftJ<br />

RedlinrlStrikeout<br />

I separated from each other by an approximately 0.75-m (2.5-ft)-thick lift of grout. The grout<br />

2 layer provides important shielding to limit operation staff exposure to radiation from the wastes<br />

3 in the layers below. Grout amendments, such as fly ash or zeolite clays, would be considered for<br />

4 the grout to reduce potential for leaching of radioactive isotopes. A summary of steps involved<br />

S for this part of Alternative 4 follows.<br />

6<br />

7 G.2.2.I Modify Canyon End Walls. In preparation for waste placement in the canyon, the end<br />

8 walls of the building must be modified. A gridwork of steel bcams would be installed on both<br />

9 the northeast and southwest end walls. This grid would be dcsigned to resist seismic forces and<br />

10 loads applied during the complex's operation pcriod. For the southwest end wall, the<br />

11 modification would include saw cutting an opening in the concrete wall. This opening would be<br />

12 sized to accept the waste containers moved by a forklift. The opening would be covered with a<br />

13 rollup door. The wall's steel beam gridwork would be designed to allow the rollup door to be<br />

14 moved upwards level by level as the waste is placed within the canyon. The gridwork would be<br />

15 anchored to the roof siab and surrounding reinforced walls. 71rough-bolting would connect the<br />

16 gridwork to the unreinforced concrete end wall.<br />

17<br />

18 G.2.2.2 Fill Ganyan Canvon deck and Craneway with Waste. The eaxyen<br />

19 canvon deck would be filled with a total of four layers of waste containers. The<br />

20 first three layers would hold a estimated 160 cargo containers each, for a total of 480 containers.<br />

21 The container placement would start at the northeast end of the canyon and advance towards the<br />

22 southwest end. Each layer would be completed prior to placement beginning on the next layer<br />

23 up. This approach would ensure that them is not a large differential in loading of adjacent<br />

24 building sections.<br />

25<br />

26 Containers would be grouted both inside the container and around their exterior. It is envisioned<br />

27 that grouting would occur roughly every 12 m (40 ft) of building length. Containers would be<br />

28 placed using a forklift with adequate shielding to limit operator exposure to an acceptable level.<br />

29 The containers would be placed two abreast across the canyon deck width. In this manner, the<br />

30 forklift could place the containers without making a 90-degree turn, which would be difficult in<br />

31 the limited width of the canyon deck.<br />

32<br />

33 As part of the grouting effort, a 0.75-m (2.5-ft)-thick layer of grout would be placed on top of the<br />

34 filled containers. This layer would act as both shielding and a working surface for the next layer<br />

35 of containers. Grout amendments, such as fly ash or zeolite clays, would be considered for the<br />

36 grout to reduce potential for leaching of radioactive isotopes. In the final design, a reinforced<br />

37 concrete slab may be installed as the top section of the grout layer. The concrete slab provides a<br />

38 smoother surface for operation of the forklifts during waste placement of the next layer. The<br />

39 grout, or possibly reinforced concrete slab, would be designed for the whccl loads of the forklift.<br />

40<br />

41 The next waste placement would be inside the craneway. An opening in the southwest end wall<br />

42 would be cut to provide access to the cranaway. Guide rails would be installed and cargo<br />

(-,\43 containers delivered into the craneway similar to waste placement in the galleries.<br />

44 Approximately 39 containers could be placed in the craneway. The containers would be grouted<br />

45 inside and out as was done in the galleries.<br />

Final Feasibility Study jor Jhe Canyon Disposition )nitiativt (22 )-U Facility)<br />

^ Ivte 1!tL^ G-18

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!