View Document Here - Hanford Site
View Document Here - Hanford Site
View Document Here - Hanford Site
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
.. . .,. .. .<br />
Appendix G- Detailed Description of Alternative 4: DoEIRt.-2003-11<br />
Entombment with Internal and External Waste Disposal Rev. l DraftJ<br />
RedlinrlStrikeout<br />
I separated from each other by an approximately 0.75-m (2.5-ft)-thick lift of grout. The grout<br />
2 layer provides important shielding to limit operation staff exposure to radiation from the wastes<br />
3 in the layers below. Grout amendments, such as fly ash or zeolite clays, would be considered for<br />
4 the grout to reduce potential for leaching of radioactive isotopes. A summary of steps involved<br />
S for this part of Alternative 4 follows.<br />
6<br />
7 G.2.2.I Modify Canyon End Walls. In preparation for waste placement in the canyon, the end<br />
8 walls of the building must be modified. A gridwork of steel bcams would be installed on both<br />
9 the northeast and southwest end walls. This grid would be dcsigned to resist seismic forces and<br />
10 loads applied during the complex's operation pcriod. For the southwest end wall, the<br />
11 modification would include saw cutting an opening in the concrete wall. This opening would be<br />
12 sized to accept the waste containers moved by a forklift. The opening would be covered with a<br />
13 rollup door. The wall's steel beam gridwork would be designed to allow the rollup door to be<br />
14 moved upwards level by level as the waste is placed within the canyon. The gridwork would be<br />
15 anchored to the roof siab and surrounding reinforced walls. 71rough-bolting would connect the<br />
16 gridwork to the unreinforced concrete end wall.<br />
17<br />
18 G.2.2.2 Fill Ganyan Canvon deck and Craneway with Waste. The eaxyen<br />
19 canvon deck would be filled with a total of four layers of waste containers. The<br />
20 first three layers would hold a estimated 160 cargo containers each, for a total of 480 containers.<br />
21 The container placement would start at the northeast end of the canyon and advance towards the<br />
22 southwest end. Each layer would be completed prior to placement beginning on the next layer<br />
23 up. This approach would ensure that them is not a large differential in loading of adjacent<br />
24 building sections.<br />
25<br />
26 Containers would be grouted both inside the container and around their exterior. It is envisioned<br />
27 that grouting would occur roughly every 12 m (40 ft) of building length. Containers would be<br />
28 placed using a forklift with adequate shielding to limit operator exposure to an acceptable level.<br />
29 The containers would be placed two abreast across the canyon deck width. In this manner, the<br />
30 forklift could place the containers without making a 90-degree turn, which would be difficult in<br />
31 the limited width of the canyon deck.<br />
32<br />
33 As part of the grouting effort, a 0.75-m (2.5-ft)-thick layer of grout would be placed on top of the<br />
34 filled containers. This layer would act as both shielding and a working surface for the next layer<br />
35 of containers. Grout amendments, such as fly ash or zeolite clays, would be considered for the<br />
36 grout to reduce potential for leaching of radioactive isotopes. In the final design, a reinforced<br />
37 concrete slab may be installed as the top section of the grout layer. The concrete slab provides a<br />
38 smoother surface for operation of the forklifts during waste placement of the next layer. The<br />
39 grout, or possibly reinforced concrete slab, would be designed for the whccl loads of the forklift.<br />
40<br />
41 The next waste placement would be inside the craneway. An opening in the southwest end wall<br />
42 would be cut to provide access to the cranaway. Guide rails would be installed and cargo<br />
(-,\43 containers delivered into the craneway similar to waste placement in the galleries.<br />
44 Approximately 39 containers could be placed in the craneway. The containers would be grouted<br />
45 inside and out as was done in the galleries.<br />
Final Feasibility Study jor Jhe Canyon Disposition )nitiativt (22 )-U Facility)<br />
^ Ivte 1!tL^ G-18