APPENDIX E<br />
3 ATTACHMENT El -FUNCTIONAL HIERARCHY<br />
4<br />
5<br />
6 E.1 PREPARE EXISTING COMPLEX<br />
7 E.1.1 Control hazards<br />
DOEIRL-2001-1 l<br />
Rev. 0 1 Draft D<br />
&dlinc/Strikenut<br />
8 E.1.1.1 Establish hazards protection<br />
9 E.1.1.t.1 Control heaith and safety hazards<br />
10 E.1.1.1.2 Control environmental hazards<br />
11 E.1.1.2 Manage hazardous materials<br />
12 E.1.1.2.1 Characterize hazardous materials<br />
13 E.1.1.2.2 Dccontaminate areas and systems<br />
14 E.1.1.2.3 Prepare hazardous materials for processing and disposition<br />
15 E.1.2 Establish inftastruMure<br />
16 E.1.2.1 Modify existing infrastruture<br />
17 E.1.2.1.1 Water<br />
18 E.1.2.1.2 Sewer<br />
(--N19 E.1.2.1.3 Electrical<br />
20 E.1.2.1.4 HVAC<br />
21 E.1.2.1.5 Lighting<br />
22 E.1.2.1.6 Recertify main bridge crane<br />
23 E.1.2.1.7 Install new roof system<br />
24 E.1.2.2 Establish support facilities<br />
25 E.1.2.2.1 Modifications to the existing building<br />
26 E.1.2.2.2 Install mobile office units<br />
27 E.1.2.3 Establish staging areas<br />
28 E.1.2.3.1 Establish personnel staging areas (change rooms, operations,<br />
29 lunchroom, first aid, emergency, offices...)<br />
30 E.1.2.3.2 Establish equipment staging areas (maintenance, repair,<br />
31 decontamination, packaging, waste shipping, haul vehicle<br />
32 frisking, parking,...)<br />
33 E.1.2.3.3 Add ramp and truck door to 221-U<br />
34 E.1.3 Modify Facility<br />
35 111.3.1 Prepare facility for use<br />
36 E.1.3.1.1 Inspect 271-U for its role during preparing the complex<br />
37 E.1.3.1.2 Identify 221-U building modifications, if any, required for its<br />
38 support during first phase of Altetnative 1<br />
/^39<br />
E.1.3.2 D&D Railroad Tunnel<br />
f 40 E.1.3.2.1 Remove soil cover<br />
41 E.1.3.2.2 Fix contamination on tunnel interior<br />
Final Feasibility Smdy/or the Canyon DLrpwUiai Initiative (271-U Facility)<br />
mc'+001 E-19