19.05.2013 Views

View Document Here - Hanford Site

View Document Here - Hanford Site

View Document Here - Hanford Site

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

f,^N<br />

Appendix E - Detailed Description of Alternative 1: DoFJRL-2001-11<br />

I Full Removal and Disposal Rev. o t DtaU<br />

Redlinc rikeout<br />

1 • Foundation mat<br />

2 • Cell drain header.<br />

3<br />

4 The demolition steps would be even more extensive adjacent to the rail tunnel, adjacent to<br />

5 cell 10, and at each end of the building.<br />

6<br />

7 E.2.1.4 Excavate Outside Building to Foundation Level. After demolition would have<br />

8 reached the anyon dcck , the area on each side of 221-U would be<br />

9 excavated to the foundation level. This would allow continuation of demolition of the building.<br />

10 Clean material removed during this excavation would be stockpiled for later use as site backfill.<br />

S 1 Contaminated soil, if encountered, would be taken to ERDF for disposal.<br />

12<br />

13 E.11.5 Demolish 221-U from Canyon to Foundation Level. Building segments above the<br />

14 foundation mat could be dismantled from both ends, meeting at cells 9 and 10, which would be<br />

15 demolished last. This would Icave the process cells covered to minimize water intrusion and<br />

16 leave the cell drain header collection tank in cell 10 functional for as long as possible.<br />

17<br />

18 The foundation mat varies in thickness from 1.8 to 2.4 m (6 to 8 ft). It would be left in place<br />

19 until the walls of the canyon were completely removed to provide a firm working surface, and to<br />

20 avoid disturbing the cell drain header. The foundation slab would be cracked using expansive<br />

^21 grout. Wire saws would be used to cut slab reinforcement prior to demolition.<br />

22<br />

23 After removal of the foundation mat, the only remaining structure would be the bottom of<br />

24 cell 10, the termination of the cell drain header. The cell walls extend approximately 6 m(20 ft)<br />

25 below the bottom of the foundation. The walls would be exposed, cut, and removed. The cell<br />

26 floor slab would be removed similar to the foundation mat.<br />

27<br />

28 E.2.1.6 Excavate Soil Below 221-U. As part of the demolition of 221-U, the first 0.9 m (3 ft) of<br />

29 soil below the foundation slab would be removed. This removal step would include demolition<br />

30 of the cell drain header. This 0.6-m (2-ft)-diameter clay pipeline is encased in concrete. The<br />

31 pipe would be grouted solid to contain contamination and then removed in blocks for disposal at<br />

32 ERDF.<br />

33<br />

34 E.2.1.7 Demolition of External ['iping Around 221-U. Piping not already addressed in the<br />

35 preparation of the complex step would be removed as part of the demolition steps for 221-U. In<br />

36 addition to the miscellaneous piping to be removed, a portion of the exhaust air tunnel would be<br />

37 removed. This tunnel is a reinforced structure connecting the canyon's air ventilation tunnel to<br />

38 the stack and filter. The tunnel is approximately 60 m(200 ft) long and runs from the end of the<br />

39 air tunnel in building section 3 to the fans. Approximately 23 m(75 ft) of the tunnel would be<br />

40 demolished and removed as part of Alternative 1.<br />

41<br />

42 The ventilation stack is about 60 m (200 ft) from the back wall of the canyon and would not be<br />

(0^'43 demolished in this option.<br />

44<br />

45<br />

Final Feasibility Sradyjor the Canyon DkpoXtion Initiative (221 •U Facility)<br />

^ ltmc:^ E-14

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!