5CSL0-06B<br />

2.9 Trial test run operation<br />

2.9.1 Test run procedure<br />

Check the following before turning power on<br />

Wrong power wiring , loosed screws<br />

Wrong control transmission wiring , loose screws<br />

Piping size , presence <strong>of</strong> thermal insulation<br />

Measurement <strong>of</strong> main power circuit insulation<br />

Addition or refrigerant if required<br />

Fully open respective stop valves on liquid, gas<br />

Turn on outdoor unit power<br />

Use a mega-tester<br />

Be sure to record the additional<br />

quantity <strong>of</strong> refrigerant<br />

2.9.2 Evaluation performance<br />

Evaluation <strong>of</strong> the performance<br />

Operate unit for 15~20 minutes, then check the system<br />

refrigerant charge:<br />

1. Measure the pressure <strong>of</strong> the gas side service valve.<br />

2. Measure the temperature <strong>of</strong> the intake and discharge <strong>of</strong> air.<br />

3. Ensure the difference between the intake temperature<br />

and the discharge is more than 8°C<br />

4. For reference, the gas side pressure <strong>of</strong> optimum condition<br />

is as below. (Cooling)<br />

Refrigerant<br />

Discharge air<br />

Outside ambient<br />

Temp.<br />

Intake temperature<br />

Discharge<br />

temperature<br />

The pressure <strong>of</strong> the gas side<br />

service valve.<br />

R410A 35°C (95°F) 8.0~10.0kg/cm 2 G<br />

NOTE<br />

Trial test run operation<br />

: If the actual pressure is higher than shown, the system is<br />

most likely overcharged so extra refrigerant should be<br />

removed.<br />

If the actual pressure is lower than shown, the system is<br />

most likely undercharged so extra refrigerant should be<br />

added.<br />

The air conditioner is now ready for use.<br />

2.9.3 Transfer to customer with ex<strong>pl</strong>anation<br />

1. Operational step<br />

Com<strong>pl</strong>ete test run<br />

Ex<strong>pl</strong>ain how to<br />

operate and<br />

maintain equipment<br />

Make final report<br />

(test run<br />

inspection sheet)<br />

Hand over<br />

relevant printed<br />

materials<br />

a) The measurements taken during the test run should be<br />

recorded and kept on a test run inspection sheet.<br />

b) Do not forget to record the length <strong>of</strong> the refrigerant piping<br />

and the refrigerant additional charging volume on the<br />

<strong>pl</strong>ate on the back <strong>of</strong> the outdoor unit external notice<br />

board, as this information will be required for servicing<br />

the system.<br />

c) Ex<strong>pl</strong>ain to the customer how to operate and maintain the<br />

equipment and let him try it.<br />

d) Assemble all the relevant diagrams and other printed<br />

matter which is required to operate the system and hand<br />

over to the customer (on the spot) and request him to<br />

keep it handy.<br />

e) Service contact address.<br />

List <strong>of</strong> equipment which has been delivered<br />

Installation drawing<br />

It is essential to prepare a control wiring diagram<br />

which clarifies the refrigerant system and the<br />

control system.<br />

1 set <strong>of</strong> operation manuals<br />

Names <strong>of</strong> those responsible for the<br />

work (emergency contact address)<br />

Equipment guarantees.<br />

Guideline for each installation process 317