AZPDES Stormwater Permit - Continued<br />

Arizona Mining Permitting Guide<br />

EXEMPTIONS:<br />

For the categories at 40 C.F.R. 122.26(b)(14), no permit is needed if industrial activities are<br />

not exposed to stormwater.<br />

FEES:<br />

There is no ADEQ fee at this time.<br />

AVERAGE PROCESSING TIME:<br />

For coverage under ADEQ’s general stormwater permit, discharges are authorized 48 hours<br />

after notice of intent is postmarked, unless otherwise notified by ADEQ.<br />

FORMS:<br />

Guidance and forms:<br />

www.azdeq.gov/environ/water/permits/stormwater.html<br />