Appropriations of Surface Water - Continued<br />

FEES:<br />

A.A.C. R12-15-151 establishes various fees for processing applications for permits. To<br />

appropriate surface water for an application in excess of 50 acre-feet per year, the application<br />

fee is $75 plus $50 for issuance of the certificate. An application to sever and transfer a water<br />

right is $500.<br />

AVERAGE PROCESSING TIME:<br />

A permit to appropriate water must be reviewed for completeness within 30 days and a<br />

substantive review must be completed in 420 days, totaling an overall time frame of 450 days.<br />

Permits for reservoir storage must be reviewed for completeness within 30 days and<br />

substantive review completed by 420 days. Severance and transfer of water rights must be<br />

completed in an overall time frame of 420 days, including 30 days for completeness review<br />

and 390 days for substantive review.<br />

FORMS:<br />

www.azwater.gov/azdwr/SurfaceWater/SurfaceWaterRights/documents/ApplicationGuideline<br />

s.pdf<br />

54