Arizona Mining Permitting Guide<br />

Discharge Authorization for a Type 4 General Aquifer Protection Permit - Continued<br />

the Notice of Intent should be submitted. All other applications should be submitted to ADEQ<br />

for processing.<br />

EXEMPTIONS:<br />

None<br />

FEES:<br />

Application fees vary depending on the type of on-site wastewater treatment components or<br />

size of sewage collection system. An applicant should consult the ADEQ website to<br />

determine the applicable fee.<br />

AVERAGE PROCESSING TIME:<br />

Review may take 73 to 136 business days depending on the Type 4 General APP. Additional<br />

time may be added for more complex facilities.<br />

FORMS:<br />

Information:<br />

www.azdeq.gov/environ/water/engineering/ltf.html<br />

Information and links to forms:<br />

www.azdeq.gov/environ/water/permits/app.html<br />