Arizona Mining Permitting Guide<br />

Section 404 Permit (Dredge and Fill) - Continued<br />

EXEMPTIONS:<br />

Exemptions are limited, assume that a Section 404 permit is required and consult with the<br />

Corp of Engineers.<br />

FEES: n<br />

There is no application filing fee. A fee is charged upon issuance of an individual permit ($10<br />

for non-commercial projects, $100 for commercial/industrial projects). No fee is charged for<br />

general permit authorizations or Letters of Permission.<br />

AVERAGE PROCESSING TIME:<br />

It takes 30-60 days for most general permits and letters of permission. Individual permits<br />

typically require 180 days processing time. Longer processing times may be expected for<br />

complex projects or instances where there are endangered species or cultural resource<br />

concerns.<br />

FORMS:<br />

www.spl.usace.army.mil/regulatory/eng4345a.pdf<br />

Additional Nationwide Permits<br />

www.usace.army.mil/CECW/Pages/nw_permits.aspx<br />