Reclaimed Water Permit - Continued<br />

Arizona Mining Permitting Guide<br />

hearing is held. Public notice and a 30 day comment period are required. Type 1 general<br />

permits required no notification to ADEQ. Type 2 general permits are approved upon receipt<br />

of a complete notice of intent. The overall time frame for Type 3 general permits is 81 days.<br />

Reclaimed water individual and general permits must be renewed every five years to continue<br />

coverage.<br />

FORMS:<br />

Water permits site:<br />

www.azdeq.gov/environ/water/permits/index.html<br />

Individual Reclaimed Water Permit:<br />

www.azdeq.gov/environ/water/permits/download/individual.pdf<br />

Type 1 General Permit:<br />

www.azdeq.gov/environ/water/permits/reclaimed.html#1<br />

Type 2 General Permit:<br />

http://www.azdeq.gov/environ/water/permits/reclaimed.html#2<br />

Type 3 General Permit<br />

www.azdeq.gov/environ/water/permits/reclaimed.html#3<br />