Arizona Mining Permitting Guide<br />

Water and/or Wastewater Facilities - Approval to Operate<br />

Arizona Department of Environmental Quality<br />

Groundwater Section<br />

1110 West Washington Street<br />

Phoenix, AZ 85007<br />

602-771-4428<br />

www.azdeq.gov/environ/water/index.html<br />

PERMITS, AUTHORIZATIONS OR FILINGS:<br />

Water and/or Wastewater Facilities - Approval to Operate (Approval of<br />

Construction)<br />

LEGAL AUTHORITY:<br />

A.R.S. § 49-353<br />

A.R.S. § 49-361<br />

CONDITIONS REQUIRING PERMITS, AUTHORIZATIONS OR FILINGS:<br />

This approval ensures that new or modified water and/or wastewater facilities are constructed<br />

in accordance with plans and specifications approved by the ADEQ, as described by an<br />

Approval to Construct Certificate.<br />

A submittal of the following by a Professional Engineer registered in the State of Arizona,<br />

responsible for project construction supervision:<br />

1) Engineer’s Certificate of Completion.<br />

2) As-built plans.<br />

3) Final Operation and Maintenance Manual (if required).<br />

4) Construction and pre-operational inspection and testing data.<br />

5) Other support information to demonstrate proper construction.<br />

Facilities requiring permit approvals by ADEQ may be subject to review for adherence to the<br />

applicable local and/or regional Water Quality Management Plan (208 Plan).<br />

EXEMPTIONS:<br />

None<br />

FEES:<br />

Initial fees range from $500 to $1,000. Final billing and refund is based on the time spent by<br />

ADEQ in processing the application.<br />

AVERAGE PROCESSING TIME:<br />

Typically from two to eight weeks. Simple projects without operation and maintenance<br />

manuals typically are permitted within two weeks. Complex projects receive final approval<br />

within four to eight weeks. Projects with incomplete documentation and major construction<br />

deficiencies should expect a processing time of eight weeks or more.<br />

FORMS:<br />

www.azdeq.gov/environ/water/engineering/oss.html#forms<br />