8.11 CONSTRUCTION DEMOLITION AND<br />
DISPOSAL (continued)<br />
8<br />
Controls<br />
Management of wastes, chemicals and fuel<br />
Storage of hazardous and dangerous liquids<br />
15 The following controls apply to the storage of hazardous and<br />
dangerous liquids:<br />
i) Storage areas must be located well away from drains;<br />
ii) Bunding capable of retaining the full stored capacity must be<br />
constructed around the perimeter of all liquid storage areas;<br />
iii) Where possible, liquids must be stored indoors;<br />
iv) Outdoor storage areas for liquids must be roofed to prevent<br />
rainwater ente<strong>ring</strong> the bunded area unless roofing the area<br />
would render it unsafe; and<br />
v) Storage of liquids must be in accordance with AS1940: The<br />
Storage and Handling of Flammable and Combustible Liquids or<br />
any standard replacing that standard.<br />
Note: Under the POEO Act 1997, it is an offence to store hazardous and<br />
dangerous liquids (including oils, solvents, fuels, acids and paints) in such a<br />
way as to allow any water pollution incident to occur.<br />
Disposal of Wastewater<br />
16 Wastewater must be kept separate from stormwater. Wastewater<br />
must not enter any stormwater system either on or off the property.<br />
17 Washing and cleaning activities on commercial or industrial<br />
premises must be undertaken only within the confines of a bunded<br />
area.<br />
18 Wastewater must be retained on site and treated prior to disposal in<br />
accordance with NSW Department of Environment, Climate Change<br />
and Water and Sydney Water requirements.<br />
Environmental Site Management Plan<br />
19 A preliminary Environmental Site Management Plan (ESMP) must be<br />
prepared to accompany all development applications in accordance<br />
with the ‘Blue Book’, the environmental controls contained in this<br />
DCP and in accordance with <strong>Council</strong>’s DA Guide.<br />
20 The preliminary ESMP must demonstrate consideration by the<br />
applicant of the environmental effects of the proposed construction<br />
works and the means by which the construction site will be<br />
maintained throughout the construction process to ensure the<br />
optimum environmental outcome for the project.<br />
Once Consent is Granted<br />
21 A final Erosion and Sediment Control Plan(s) is (are) to be prepared<br />
in accordance with the ‘Blue Book’ and the conditions of consent.<br />
BUILDING DESIGN & SUSTAINABILITY<br />
Draft <strong>Ku</strong>-<strong>ring</strong>-<strong>gai</strong> <strong>Pymble</strong> <strong>Business</strong> <strong>Park</strong> Development Control Plan 2012<br />
p 115