Tender Documents - Oil India Limited
Tender Documents - Oil India Limited
Tender Documents - Oil India Limited
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
4 Standby Charge Day 365 d.4 D.4= d.4 x 365<br />
5 TOTAL T.D = D.1 + D.2 + D.3 + D.4<br />
E) 20 MT CRANE<br />
1 Mobilization Charges Lump sum 1 e.1 E.1= e.1 x 1<br />
2 De-Mobilization Charge Lump sum 1 e.2 E.2= e.2 x 1<br />
3<br />
Monthly Operational/Rental Charges<br />
(including crew for round the clock<br />
duty and fuel) Month 24 e.3 E.3= e.3 x 24<br />
4 Running (movement) Charges Km 5000 e.4 E.4= e.4 x 5000<br />
5 TOTAL T.E = E.1 + E.2 + E.3 + E.4<br />
F) LIGHT DUTY TRUCK<br />
1 Mobilization Charges Lump sum 1 f.1 F.1= f.1 x 1<br />
2 De-Mobilization Charge Lump sum 1 f.2 F.2= f.2 x 1<br />
1<br />
Monthly Rental (including crew for<br />
round the clock duty) Month 24 f.3 F.3= f.3 x 24<br />
2 Running Charge Km 75000 f.4 F.4= f.4 x 75000<br />
3 TOTAL T.F = F.1 + F.2 + F.3 + F.4<br />
TOTAL FOR ADDITIONAL ITEMS TADD = T.A+T.B+T.C+T.D+T.E+T.F<br />
TOTAL ESTIMATED CONTRACT VALUE FOR 2 YEARS OPERATION OF 2<br />
RIGS INCLUDING ALL TAXES & DUTIES EXCEPT CUSTOMS DUTY AND<br />
SERVICE TAX WHICH ARE EXTRA TO OIL<br />
RESTRICTIONS:<br />
T = TCRO x 2 + TADD<br />
1 Mobilization Charges of each rig (TM) TM should not exceed 7.1/2% of TCRO<br />
2<br />
3<br />
4<br />
5<br />
6<br />
7<br />
Mobilization Charges for Tubulars etc.<br />
Mobilization Charges for Welding Machine<br />
Mobilization Charges for Mud Plant<br />
Mobilization Charges for Mud Testing Lab<br />
Mobilization Charges for Crane<br />
Mobilization Charges for Light Truck<br />
A.1 should not exceed 7.1/2% of T.A<br />
B.1 should not exceed 7.1/2% of T.B<br />
C.1 should not exceed 7.1/2% of T.C<br />
D.1 should not exceed 7.1/2% of T.D<br />
E.1 should not exceed 7.1/2% of T.E<br />
F.1 should not exceed 7.1/2% of T.F<br />
NOTE: 1) In case the offered charges exceeds the specified RESTRICTED amount then OIL shall pay the<br />
excess amount after completion of the Contract.<br />
2) Bidders should quote against rates for one rig under item I. Total cost for 2 rigs would be arrived at by<br />
multiplying the rates by 2 as shown in BEC.<br />
3) Bidder need not to quote for Standby rate, Repair rate & Force Majeure rate as the same will be payable as<br />
fixed % age of operating Day Rate as shown in the Schedule of Rates/Payment: Section -IV<br />
SIGNATURE OF THE BIDDER