equired for permits or licenses for the movement of Contractor‟s personnel.<br />
Should such permits/ licenses be delayed because of objections of<br />
appropriate authorities in respect of specific Contractor‟s persons such<br />
persons should be promptly removed from the list by the Contractor and<br />
replaced by acceptable persons. For any stoppage of operations for such<br />
delays, no day rate will be applicable.<br />
9.0 PAYMENTS:<br />
9.1 Invoices: Mobilization charges will be invoiced only upon completion of<br />
mobilization (after commencing of operation at the first well), submission /<br />
production of appropriate inventory documents, and physical verification by<br />
Company representative.<br />
9.2 Contractor shall send invoice to Company on the day following the end of<br />
each month for all daily or monthly charges due to the Contractor.<br />
9.3 Billings for daily charges will reflect details of time spent (calculated to the<br />
nearest quarter hours) and the rates charged for that time. This should be<br />
in the form of monthly time analysis chart(s). Monthly invoices will be<br />
raised only after commencement of operation at the first well.<br />
9.4 Invoice for reimbursable charges related to the contract will be<br />
accompanied by documents supporting the cost incurred.<br />
9.5 Payment of monthly invoices, if undisputed, shall be made within 30 days<br />
following the date of receipt of invoice by Company excepting for the first<br />
two (2) monthly invoices where some delay (up to one month) may occur.<br />
9.6 Payments of other invoices as set forth in Clause 9.4 shall be made within<br />
60 days following the date of receipt of the invoices by Company.<br />
9.7 Payment of mobilization charges shall be made within 45 days following the<br />
date of receipt of undisputed invoices by Company. Mobilization should be<br />
complete in all respect before raising invoice.<br />
9.8 Payment of demobilization charges shall be made when applicable within<br />
45 days following receipt of invoice by Company accompanied by the<br />
following documents from the Contractor :<br />
a) Audited account up to completion of the Contract.<br />
b) Tax audit report for the above period as required under the <strong>India</strong>n<br />
Tax Laws.<br />
c) Documentary evidence regarding the submission of returns and<br />
payment to taxes for the expatriate personnel engaged by the<br />
Contractor or by its sub-Contractor.<br />
d) Proof of re-export of all items (excepting consumables consumed<br />
during the contract period) and also cancellation of re-export bond if<br />
any.<br />
e) Any other documents as required by applicable <strong>India</strong>n Laws.