1.13 “Facility” means and includes all property of Company owned or hired, to<br />

be made available for services under this Contract and as described in this<br />

agreement which is or will be a part of the Company.<br />

1.14 “Certificate of Completion” means certificate issued by the Company to the<br />

Contractor stating that he has successfully completed the jobs/works<br />

assigned to him and submitted all necessary reports as required by the<br />

Company.<br />

1.15 “Base camp” means the camp where the Contractor‟s personnel shall reside<br />

for carrying out the operations along with specified Company‟s personnel as<br />

per the contract.<br />

1.16 “Inter-location movement” means transferring of complete rig materials<br />

from present location after rig release till the completion of rig up at the<br />

next location and the well is ready for killing after preparation of killing<br />

fluid.<br />

1.17 “Work over Operation” means all operations required to be carried out<br />

pursuant to this contract.<br />

2.0 MOBILIZATION<br />

2.1 The mobilization of the Work over Unit and associated services shall<br />

commence on the date of receipt of the „Letter of Award‟ awarding the<br />

Contract and continue until the complete Work over unit is properly<br />

positioned at the first location, rig-up of rig is completed and the well is<br />

ready for killing operation.<br />

2.2 The Contractor will advise readiness for commencement of mobilisation /<br />

shipment to Company after the Effective Date, at least 3 days before actual<br />

mobilisation / shipment commences.<br />

2.3 Mobilization charges will be payable after the commencement date as<br />

certified by the Company.<br />

2.4 Company at its discretion may allow commencing the operation without<br />

complete mobilization, however necessary deduction for short supplied<br />

items will be made as per cost evaluated by OIL.<br />

(i)<br />

(ii)<br />

(iii)<br />

For any items supplied by the Company, rental will be calculated<br />

after amortizing the cost of the item over a period of 5 years applying<br />

15% PTRR (Post tax rate of return). Similar deductions will also be<br />

made for short supplied items (neither supplied by Company nor by<br />

the Contractor).<br />

Deduction will be calculated based on Company‟s determined cost,<br />

which shall be treated as final, basis of which shall provided to the<br />

Contractor.<br />

Notwithstanding this provision for partial mobilization bidder must<br />

quote in accordance with relevant clauses for full mobilization.