1.13 “Facility” means and includes all property of Company owned or hired, to<br />
be made available for services under this Contract and as described in this<br />
agreement which is or will be a part of the Company.<br />
1.14 “Certificate of Completion” means certificate issued by the Company to the<br />
Contractor stating that he has successfully completed the jobs/works<br />
assigned to him and submitted all necessary reports as required by the<br />
Company.<br />
1.15 “Base camp” means the camp where the Contractor‟s personnel shall reside<br />
for carrying out the operations along with specified Company‟s personnel as<br />
per the contract.<br />
1.16 “Inter-location movement” means transferring of complete rig materials<br />
from present location after rig release till the completion of rig up at the<br />
next location and the well is ready for killing after preparation of killing<br />
fluid.<br />
1.17 “Work over Operation” means all operations required to be carried out<br />
pursuant to this contract.<br />
2.0 MOBILIZATION<br />
2.1 The mobilization of the Work over Unit and associated services shall<br />
commence on the date of receipt of the „Letter of Award‟ awarding the<br />
Contract and continue until the complete Work over unit is properly<br />
positioned at the first location, rig-up of rig is completed and the well is<br />
ready for killing operation.<br />
2.2 The Contractor will advise readiness for commencement of mobilisation /<br />
shipment to Company after the Effective Date, at least 3 days before actual<br />
mobilisation / shipment commences.<br />
2.3 Mobilization charges will be payable after the commencement date as<br />
certified by the Company.<br />
2.4 Company at its discretion may allow commencing the operation without<br />
complete mobilization, however necessary deduction for short supplied<br />
items will be made as per cost evaluated by OIL.<br />
(i)<br />
(ii)<br />
(iii)<br />
For any items supplied by the Company, rental will be calculated<br />
after amortizing the cost of the item over a period of 5 years applying<br />
15% PTRR (Post tax rate of return). Similar deductions will also be<br />
made for short supplied items (neither supplied by Company nor by<br />
the Contractor).<br />
Deduction will be calculated based on Company‟s determined cost,<br />
which shall be treated as final, basis of which shall provided to the<br />
Contractor.<br />
Notwithstanding this provision for partial mobilization bidder must<br />
quote in accordance with relevant clauses for full mobilization.