SECTION - I<br />
GENERAL CONDITIONS OF CONTRACT<br />
1.0 DEFINITIONS:<br />
1.1 In the contract, the following terms shall be interpreted as indicated:<br />
(a)<br />
"The Contract" means agreement entered into between Company and<br />
Contractor, as recorded in the contract Form signed by the parties,<br />
including all attachments and appendices thereto and all documents<br />
incorporated by reference therein;<br />
(b) "The Contract Price" means the price payable to Contractor under the<br />
contract for the full and proper performance of its contractual<br />
obligations;<br />
(c)<br />
(d)<br />
(e)<br />
(f)<br />
(g)<br />
"The Work" means each and every activity required for the successful<br />
performance of the services described in Section II, the Terms of<br />
Reference.<br />
"Company" or “OIL” means <strong>Oil</strong> <strong>India</strong> <strong>Limited</strong>;<br />
"Contractor" means the Contractor performing the work under this<br />
Contract.<br />
"Contractor's Personnel" means the personnel to be provided by the<br />
Contractor to provide services as per the contract.<br />
"Company’s Personnel" means the personnel to be provided by OIL or<br />
OIL's Contractor (other than the Contractor executing the Contract).<br />
The Company representatives of OIL are also included in the<br />
Company's personnel.<br />
2.0 EFFECTIVE DATE, MOBILISATION TIME, DATE OF COMMENCEMENT<br />
OF THE CONTRACT AND DURATION OF CONTRACT:<br />
2.1 EFFECTIVE DATE OF CONTRACT : The contract shall become effective as<br />
of the date, Company notifies the successful bidder, in writing through<br />
Letter of Awards (LOA) that it has been awarded the contract. This date of<br />
issue of LOA shall be treated as the Effective Date of Contract.<br />
2.2 MOBILISATION TIME : The mobilization of equipment, personnel etc.<br />
should be completed by Contractor within 4 months from the effective date<br />
of the contract. Mobilization shall be deemed to be completed when<br />
Contractor‟s equipment and manpower are placed at the nominated location<br />
in readiness to commence Work as envisaged under the Contract duly<br />
certified by the Company‟s authorized representative.<br />
2.3 DATE OF COMMENCEMENT OF CONTRACT: The date on which the<br />
mobilization is completed in all respects is treated as date of<br />
commencement of Contract.