Table 7.1 - Solar Projects<br />
KWH generated DC KWH<br />
City Hall 148,848 106.425<br />
Municipal Services Center 177,372 128.945<br />
Materials Recovery Facility 49,539 36.08<br />
Water Resources Center 170,130 122.59<br />
total 545,889 394.04<br />
Projected annual savings in kg <strong>of</strong> CO 2 610,667<br />
The City is incorporating the use <strong>of</strong> renewable solar electri<strong>city</strong> into its Corralitos water supply project<br />
designs. This new Corralitos Creek Water Supply and Fisheries Enhancement Project will host solar<br />
panels providing approximately 65% <strong>of</strong> the electri<strong>city</strong> needed to operate, estimated at 620,000 kilowatthours<br />
(kWh). The solar electri<strong>city</strong> will be used entirely on-site. The new facility, by design, <strong>of</strong>fsets<br />
groundwater pumping with use <strong>of</strong> a surface water membrane filtration plant, reducing power needs by<br />
40%. This efficiency improvement is an important design step for solar electri<strong>city</strong>. First, the project<br />
reduces total energy use and then replaces a portion <strong>of</strong> the future energy usage with renewable energy.<br />
The City will procure solar electri<strong>city</strong> by entering into a Power Purchase Agreement (PPA). A PPA with a<br />
third-party provider is preferable to direct purchase and ownership <strong>of</strong> the solar photovoltaic (PV) system<br />
because it does not require a large capital outlay. A PPA does, however, give the City the option <strong>of</strong><br />
ownership through buyout at the end <strong>of</strong> the contract period. A PPA further mitigates ownership risk to<br />
the City by eliminating performance degradation risks, design and construction contingencies, and<br />
ongoing maintenance.<br />
Overview <strong>of</strong> Power Purchase Agreement<br />
The selected PPA contractor will provide all capital (photovoltaic equipment, installation) and O&M<br />
related activities (power monitoring and equipment maintenance), while the City will provide the<br />
necessary land and ro<strong>of</strong> access at the treatment plant site. The parties will negotiate a price at which the<br />
City would purchase the power back from the solar operator. The City plans to cover the existing<br />
filter/sedimentation basin and the new membrane building with a solar photovoltaic system. The<br />
combined 37,700 square feet will provide enough space to support a photovoltaic system <strong>of</strong><br />
approximately 322 kW producing approximately 400,000 kWhs, as described below. Future expansion <strong>of</strong><br />
the photovoltaic system is planned as the plant increases in capa<strong>city</strong>.<br />
A typical PPA lasts for 10 to 20 years. The City can either renew the PPA or “buy out” the remaining<br />
value <strong>of</strong> the system, thereby taking ownership <strong>of</strong> the equipment and ending the contract arrangement<br />
with the provider. The PPA provider will install the PV system with no capital cost to the City. The<br />
provider will coordinate financing for the project and will design, construct, operate and maintain the<br />
system for the duration <strong>of</strong> the agreement. The energy from the project will be sold to the City at a fixed<br />
58