Exhibit 10 below summarizes the top 10 proposed projects for the next Fiscal Year. See the<br />

attached listing for the complete project list.<br />

Top 10 Proposed Projects for FY 2011/12<br />

Exhibit 10<br />

Dept-Fund Rate Project Description<br />

PW-305 1b<br />

Freedom Blvd<br />

Reconstruction Ph 1<br />

Sewer-710 2<br />

Manana Ln & Easements Replace 3900 LF <strong>of</strong> 15" sewer from<br />

Sanitary Sewer<br />

easement along creek<br />

Water-720 2<br />

Well 4A Design &<br />

Design & Construct Well 4A Including<br />

Construction<br />

Pump Station & Controls<br />

Water-720 2 Harkin Slough Prv Project<br />

Install pipeline across bridge and<br />

install Zone 2 To 1 Prv<br />

Water-720 1a<br />

Freedom Blvd. Water Main Replace 4,340 LF <strong>of</strong> old cast iron<br />

Replacement<br />

pipes with new 10" Ductile Iron Pipe<br />

Water-720 1b<br />

Zone 1 Enhancement Replace Well Motors, Pumps, and<br />

Project<br />

install Stand-By Generator and Vfd<br />

Sewer-710 2 Pajaro River Care Project<br />

Satisfies conditional permit for<br />

Watsonville Area Recycling Plant<br />

Sewer-710 1a<br />

Freedom Blvd. Water Main Replacement <strong>of</strong> 2000 LF 6" sewer<br />

Replacement<br />

from Buena Vista Dr. to 200 LF past<br />

Water-720 2<br />

Water Main Replacement Construct new water mains including<br />

for PW street projects services to coincide with street<br />

Water-720 2 Flexnet System<br />

Install 1,200 new meters and flexnet<br />

transmitters<br />

Of particular community interest is the Freedom Blvd road reconstruction project contained within<br />

the 5-year CIP plan that intends to reconstruct most <strong>of</strong> the roadway from the North-West City<br />

limits for several miles to Callaghan park. In total, $6.6 Million is estimated to be allocated for this<br />

project using Gas Tax funds. However, due to funding limitations, the project is anticipated to be<br />

done in phases throughout this 5-year plan. The City will also be strategically coordinating<br />

underground utility upgrades prior to the reconstruction. The City has applied and will continue to<br />

seek out Federal and State grant opportunities to move up the construction schedule for this<br />

primary transportation corridor.<br />

As mentioned previously in this report, the Capital Projects within most <strong>of</strong> the funds result in net<br />

operating deficits as shown in Exhibit 11. Staff will continue to monitor grant awards and cash<br />

balances before proceeding with many <strong>of</strong> the projects.<br />

City <strong>of</strong> Watsonville<br />

Proposed Operating Budget: Consolidated Fund Summary<br />

(amounts shown in millions)<br />

General Special Debt Enterprise Internal<br />

Fund Revenue Service Funds Service<br />

FY 2011-2012<br />

Net Operations $ - $ 2.0 $ 2.4 $ 2.8 0.1<br />

Total Net Operations $ (0.2) $ (13.4) $ 2.4 $ (43.5) $ (0.3) $ (55.0)<br />

Page 9 <strong>of</strong> 15<br />

Pimentel 6/9/2011 4:26:10 PM<br />

P:\budget 2011-2013\Presentations-Reports\2011-0614\SR-BudgetF2_2011-0614.docx<br />

Project<br />

Manager<br />

Total All<br />

Funds<br />

Estimated<br />

Cost<br />

High St to Broadis Street Fontes $ 1,600,000<br />

Swain 1,500,000<br />

Swain 1,500,000<br />

Hernandez 550,000<br />

Swain 550,000<br />

Hernandez 500,000<br />

Silviera 424,000<br />

Swain 400,000<br />

Swain 400,000<br />

Wolf 364,000<br />

FY 2011-2012 Top 10 sub-total $ 7,788,000<br />

Exhibit 11<br />

$ $ 7.3<br />

New Capital - (4.6) - (7.5) (0.1) (12.2)<br />

Prior Capital in Progress (0.2) (10.8) - (38.8) (0.3) (50.1)<br />

Total Capital (0.2) (15.4) - (46.3) (0.4) (62.3)