URS Corp.<br />

260 Franklin Street<br />

Boston, MA 02110<br />

PROJECT Mitchell River Bridge Rehabilitation Feasibility Study<br />

<strong>BRIDGE</strong> C-07-001 (437)<br />

MADE BY SUC DATE 1/31/2011 JOB NO. 10160874<br />

CHECKED BY GCP DATE 2/14/2011<br />

Alternate: Minimum Repair Scope of Work<br />

Channel & Channel Protection<br />

Timber Fender System<br />

Fender 0.5 7.6 1.000 66 3009.6 FB<br />

6" x 12" x 41'-0" 0.5 41 1.000 4 984.0 FB<br />

Subtotal: 3993.6 FB<br />

Traffic Safety<br />

Approach Guardrail/Transitions<br />

West Approach Sidewalk Rail 120 2 240.0 FT<br />

East Approach Sidewalk Rail 120 2 240.0 FT<br />

Subtotal: 480.0 FT<br />

Roadway (Milling and Resurfacing) 24 120 2 640.0 SY<br />

Demolition<br />

Spans 1, 8 & 12 31.50 16.125 3 1523.8 SF<br />

Spans 2 & 11 34.50 16.125 2 1112.6 SF<br />

Spans 3, 4, 5, 6, 7, 9 & 10 37.50 16.125 7 4232.8 SF<br />

Subtotal: 6869.3 SF<br />

3/1/2011 Page 5/6 Minimum Scope