06.12.2012 Views

COUNTRY BACKGROUND - Gross National Happiness Commission

COUNTRY BACKGROUND - Gross National Happiness Commission

COUNTRY BACKGROUND - Gross National Happiness Commission

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Energy Sector<br />

4<br />

· increase Government revenues through the generation of power for sale to India; and<br />

· promote regional balance by investment in power projects, particularly in Eastern Bhutan.<br />

· work towards the goal of providing electricity to all parts of the country<br />

B. Achievement of ObjectivesB. Achievement of Objectives<br />

Table 20.3 6FYP Outlay and Actual Expenditure for the Department of Power<br />

Power GenerationPower Generation<br />

20.18 The major achievement in the 6FYP was the commissioning of the Chukka Hydel Corporation with an<br />

installed capacity of 336 MW. Revenue earning by 1991 from the sale of power to India has risen to Nu. 384m a<br />

year. Along with the commissioning of Chhukha Hydel Corporation, a number of high voltage transmission lines<br />

and substations were also completed. The western part of the Kingdom is now covered by a well established grid. A<br />

total of 12 micro hydels (includes Khaling min hydel 3x0.2 MW, Gyetsa mini hydel 3x0.5 MW, Tamshing micro<br />

hydel 30.0 kw, Thinley gang micro hydel 30.0.kw, Surey micro hydel 70.0 kw, Kekhar micro hydel 20.0 kw, Bubja<br />

micro hydel 30.0 kw, Tongsa micro hydel 50.0 kw, Rukubji micro hydel 40.0 kw, Tansibji micro hydel 30.0 kw,<br />

Ura micro hydel 50.0 kw, Yadi micro hydel 30.0) were commissioned. Micro hydels at Dagana (200 kw) and<br />

Damphu (200 kw) and Tintibi will be completed in the plan period.<br />

High Voltage Transmission and SubstationsHigh Voltage Transmission and Substations<br />

20.19 According to the 6FYP targets, 320 km of transmission lines were to be established. However, most of the<br />

transmission lines depended on the establishment of power projects such as the Kurichu Power Project which were<br />

not implemented. As of December 1990, 119 km of transmission line had been established in the following places:<br />

between Phuntsholing - Pasakha, Phuntsholing -Penden, Chuzum - Paro, Chuzum - Haa, Simtokha -<br />

Wangdiphodrang. Along with the high voltage transmission routes, several sub-stations were also established.<br />

Sub-transmission and DistributionSub-transmission and Distribution<br />

20.20 Major works were completed in Thimphu and Paro, with most of the sub-transmission and distribution<br />

network in Thimphu being buried underground. The overhead lines were made more stable and reliable. Some<br />

minor works were also completed in Phuntsholing, Tashigang, Bumthang and Samdrup Jongkhar.<br />

Rural ElectrificationRural Electrification<br />

Schemes Financial outlay Expenditure by Oct'90<br />

Generation 39.66 53.60<br />

High Voltage Transmission 2.77 92.41<br />

Subtransmission and Distribution 102.04 85.86<br />

Rural Electrification 132.36 47.00<br />

Survey and Investigations 31.00 5.17<br />

Central Establishment 40.13 100.76<br />

Total 347.95 384.80

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!