COUNTRY BACKGROUND - Gross National Happiness Commission
COUNTRY BACKGROUND - Gross National Happiness Commission
COUNTRY BACKGROUND - Gross National Happiness Commission
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Energy Sector<br />
4<br />
· increase Government revenues through the generation of power for sale to India; and<br />
· promote regional balance by investment in power projects, particularly in Eastern Bhutan.<br />
· work towards the goal of providing electricity to all parts of the country<br />
B. Achievement of ObjectivesB. Achievement of Objectives<br />
Table 20.3 6FYP Outlay and Actual Expenditure for the Department of Power<br />
Power GenerationPower Generation<br />
20.18 The major achievement in the 6FYP was the commissioning of the Chukka Hydel Corporation with an<br />
installed capacity of 336 MW. Revenue earning by 1991 from the sale of power to India has risen to Nu. 384m a<br />
year. Along with the commissioning of Chhukha Hydel Corporation, a number of high voltage transmission lines<br />
and substations were also completed. The western part of the Kingdom is now covered by a well established grid. A<br />
total of 12 micro hydels (includes Khaling min hydel 3x0.2 MW, Gyetsa mini hydel 3x0.5 MW, Tamshing micro<br />
hydel 30.0 kw, Thinley gang micro hydel 30.0.kw, Surey micro hydel 70.0 kw, Kekhar micro hydel 20.0 kw, Bubja<br />
micro hydel 30.0 kw, Tongsa micro hydel 50.0 kw, Rukubji micro hydel 40.0 kw, Tansibji micro hydel 30.0 kw,<br />
Ura micro hydel 50.0 kw, Yadi micro hydel 30.0) were commissioned. Micro hydels at Dagana (200 kw) and<br />
Damphu (200 kw) and Tintibi will be completed in the plan period.<br />
High Voltage Transmission and SubstationsHigh Voltage Transmission and Substations<br />
20.19 According to the 6FYP targets, 320 km of transmission lines were to be established. However, most of the<br />
transmission lines depended on the establishment of power projects such as the Kurichu Power Project which were<br />
not implemented. As of December 1990, 119 km of transmission line had been established in the following places:<br />
between Phuntsholing - Pasakha, Phuntsholing -Penden, Chuzum - Paro, Chuzum - Haa, Simtokha -<br />
Wangdiphodrang. Along with the high voltage transmission routes, several sub-stations were also established.<br />
Sub-transmission and DistributionSub-transmission and Distribution<br />
20.20 Major works were completed in Thimphu and Paro, with most of the sub-transmission and distribution<br />
network in Thimphu being buried underground. The overhead lines were made more stable and reliable. Some<br />
minor works were also completed in Phuntsholing, Tashigang, Bumthang and Samdrup Jongkhar.<br />
Rural ElectrificationRural Electrification<br />
Schemes Financial outlay Expenditure by Oct'90<br />
Generation 39.66 53.60<br />
High Voltage Transmission 2.77 92.41<br />
Subtransmission and Distribution 102.04 85.86<br />
Rural Electrification 132.36 47.00<br />
Survey and Investigations 31.00 5.17<br />
Central Establishment 40.13 100.76<br />
Total 347.95 384.80