COUNTRY BACKGROUND - Gross National Happiness Commission
COUNTRY BACKGROUND - Gross National Happiness Commission
COUNTRY BACKGROUND - Gross National Happiness Commission
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Energy Sector<br />
Chhukha Tail Race Chhukha Tail Race<br />
20.41 Although the Chhukha Hydel Plant was originally designed to have an installed capacity of 336 MW, it can<br />
be operated only to a maximum of 320 MW because the water level in the tail race tunnel reaches above the<br />
maximum designed level. In practice, the generation has been restricted to 310 MW for safety reason. The<br />
construction of an additional tail race tunnel would enable the Chhukha Hydel Corporation to generate power at the<br />
rated capacity. The construction will take 2 and a half years and the maximum additional revenue per annum at Nu<br />
0.27 per kwh will be Nu 24.93 m.<br />
Bunakha Reservoir SchemeBunakha Reservoir Scheme<br />
20.42 This scheme is intended to build extra storage capacity for additional power generation during lean months<br />
to increase peaking capacity in Chhukha Hydro Power Station. Construction of a 140 m dam at Bunakha is<br />
considered feasible. However, it will take 2 years to complete hydrological investigation and another 3 to 4 years<br />
for construction phase. The reservoir if constructed is expected to generate an extra 185 Mu of energy per year and<br />
rise the Chhukha power revenue by about Nu 50 m at Nu. 0.27 per kWh.<br />
Chhukha II and Chhukha IIIChhukha II and Chhukha III<br />
20.43 Investigations for two large projects downstream from Chhukha will be completed in the early part of<br />
7FYP. One of them will be a 1000 MW run of the river scheme with a diversion structure below Mebri and an<br />
underground power house below Tala. The other located near the border will have a 200 m high dam with a surface<br />
power station with an installed capacity of 600 MW. Regardless of which scheme is selected for implementation,<br />
project implementation will start only at the closing years of 7FYP and commissioned in the 8FYP.<br />
Rural ElectrificationRural Electrification<br />
20.44 The Plan provides for the expansion of rural electrification during the 7FYP. The existing network will be<br />
extended into rural areas wherever there is excess power. However, much of the rural electrification programmes<br />
will depend firstly on the execution of generation projects and secondly on the installation of high voltage<br />
transmission lines to which low voltage subtransmission and distribution lines can be connected.<br />
Transmission lines and associated substations, subtransmission and distribution linesTransmission lines and<br />
associated substations, subtransmission and distribution lines<br />
20.45 High voltage transmission and associated substations are estimated to cost about Nu 1030 m. This cost<br />
includes the installation cost of the Eastern region grid, Central region grid, Simtokha-Basachu line and Basachu-<br />
Geylegphug line. The Subtransmission and distribution programme covers the establishment of low-voltage<br />
networks in the urban areas. A provision has been kept for the expansion of townships as well as emergence of new<br />
townships and realignments of lines where new townships are likely.<br />
Power Master Plan and Hydrology InvestigationsPower Master Plan and Hydrology Investigations<br />
20.46 The formulation of Power Master Plan was started in 1990 and will be completed by 1993. It will guide the<br />
future actions in the power sector. The Master Plan will produce a ranked list of potential hydro-power project sites.<br />
These sites have to be investigated in detail for investment decisions. In addition to investigation for power<br />
projects, hydrological investigation will include collection and dissemination of hydrological and meteorological<br />
data, both for use by the Department of Power and other agencies.<br />
Unspecified Power SchemesUnspecified Power Schemes<br />
20.47 Unspecified Power Schemes refers to three types of expenditure: (1) projects which are not yet firm and<br />
further details needs to be worked out; (2) expenditure on recommissioning of existing power plants; and (3) solar<br />
energy projects, wind and biogas energy projects and minihydro plants ( such as the proposed Chhalori mini hydel<br />
project in pema Gatshel and Dongdichu mini hydel project in Tashi Yangtsi. Expenditure items on recommissioning<br />
8