18.06.2013 Views

LIBRARY ı6ıul 0) - Cranfield University

LIBRARY ı6ıul 0) - Cranfield University

LIBRARY ı6ıul 0) - Cranfield University

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

7. Experimental Results<br />

This chapter presents the results obtained with the control system developed<br />

during the project. It starts by showing the ability of the welding process controller to<br />

achieve and maintain process stability when intentionally starting the process in an<br />

unstable region. A comparison of the welds obtained in flat position fillet joints with<br />

and without stand-off control follows. The results obtained with the two controllers<br />

combined together are then presented.<br />

7.1 Tests of the voltage controller<br />

In order to demonstrate the effectiveness of the welding process controller<br />

developed, bead-on plate welding trials were carried out with fixed stand-off, wire<br />

feed speed and welding speed. The initial power source set-up voltages were<br />

purposely chosen such that unstable situations would occur. These tests concentrated<br />

on the dip mode of metal transfer since this is more sensitive to variations of voltage<br />

around the optimum value.<br />

Figure 7.1 shows the bead appearance obtained using constant welding<br />

parameters (WFS, Sw and SO) and inadequate initial power source set-up voltage for<br />

both the non-controlled and controlled process. Figure 7.2 shows the corresponding<br />

welding data and the evolution of both the control (power source set-up and mean<br />

welding voltages) and the controlled (Power Ratio) variables.<br />

Figure 7.3 shows the bead appearance obtained using constant welding<br />

parameters (WFS, Sw and SO) and an excessive initial power source set-up voltage<br />

for both non-controlled and controlled process. Figure 7.4 shows the evolution of the<br />

welding variables along the weld. Note that in both inadequate and excessive initial<br />

power source set-up voltage cases, the process as measured by the Power Ratio was<br />

brought back to stability in less than three seconds.<br />

If the variation in the control variable (power source set-up voltage) is<br />

considered as the indication of when the controller achieved the final stability level, a<br />

different stabilisation time was observed to occur for the inadequate (;:<br />

ý- 4 s) and the<br />

excessive (, t; 6 s) initial set-up voltage cases. This occurred possibly due to the fact<br />

that the difference between the optimum power source voltage setting, as attained by<br />

the controller, and the actual initial value chosen for both the inadequate and the<br />

excessive voltage cases were different, that is, for the inadequate voltage case the<br />

difference was approximately -2.8 volts and for the excessive voltage case, +7.3 volts.<br />

Also, the instability in the latter case is characterised mainly by the level of spatter<br />

generation, the mean voltage level being fairly stable. On the other hand, the<br />

instability in the case of inadequate voltage is characterised by the wire stubbing in the<br />

weld pool, causing large variations in the mean voltage level and therefore in the main<br />

controlled variable, PR. However, despite this difference the resulting controlled weld<br />

beads were still satisfactory (see Figure 7.1 and Figure 7.3).<br />

165

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!