8. Project profiles, analysis of risks and ESA considerations<br />
This section follows from the Capital Investment Needs identified in the previous section and provides brief<br />
profiles of select priority projects that need to be executed by Krish-M in the short term. These project profiles<br />
provide a) Need for the project b) Project cost and phasing c) current status and technical assistance<br />
requirements d) possible financial mix and risk factors and e) illustrative classification based on environmental<br />
and social framework adopted by TNUDF.<br />
8.1 Water supply<br />
Project Description Comprehensive water supply scheme for piped water supply in all wards<br />
Project Status DPR under preparation by TWAD.<br />
Need for the project Water supply is only 60 LPCD while less than 63% of assessed properties have<br />
house service connections, indicating the significant gaps in water supply service<br />
levels and coverage. Therefore this project needs to be addressed on priority<br />
Project<br />
Components<br />
Project Cost and<br />
basis<br />
This outlay is based on initial estimates provided by TWAD to Krish- M and exact<br />
components and scope of DPR are not available. Assessments of normative gaps<br />
that need to be addressed are highlighted below.<br />
Supply augmentation, Transmission and primary storage for supply of at<br />
least 10.37 MLD (by 2012) and 12.74 MLD (by 2027)<br />
Local storage and pumping - Additional 2.19 ML of storage capacity by 2012<br />
and another 0.38 MLD by 2027.<br />
Investments in pumping and distribution network - Comprehensive<br />
provision of protected piped water supply in all wards covering about 44 km of<br />
roads in the short term.<br />
Rapid scale up in House service connections – which would potentially<br />
need to increase nearly 8-fold in the next 5 years to more than 15500<br />
connections<br />
Estimated at Rs. 6657 crore.<br />
Based on discussions with Krish- M, initial estimate provided by TWAD .It is likely<br />
to get escalated.<br />
Revenue impact Direct incremental revenue impact as Krish- M intends to levy house connection<br />
deposits and user charges. However, it has still not been decided whether Krish-<br />
M or TWAD would be handling the maintenance of water supply<br />
Financing mix Would be structured as a combination of grant, loan and own funds based on a<br />
detailed appraisal of potential revenues and other possible credit enhancements<br />
including escrow of part of property tax receivables and user charges and creation<br />
of debt service reserve.<br />
Risk factors and<br />
other remarks.<br />
ESA analysis and<br />
tentative rating<br />
Given the large size and the complexity of the project, it is important to follow best<br />
practices in contracting out this project. Stringent quality considerations must be<br />
adopted in selecting contractors. The contract could be structured on a BOT format<br />
where the contractor is also responsible for maintaining the network, so that that<br />
the risk of non-performance is shared. Further incentives and penalties should be<br />
built into the contract to ensure timely completion of the project. To ensure<br />
scalability, TWAD should ideally make the design amenable for 24x7 supply in the<br />
future; even it does not envisage 24x7 supply in the short term.<br />
E2 -Expected to have only moderate environmental issues. Mostly generic impacts<br />
in nature<br />
S3 - No social issues expected. Hence socially benign no social mitigation<br />
measures required, need to submit SSR<br />
CCP cum BP - Krishnagiri <strong>Municipal</strong>ity 70