Siemens City Vienna<br />

Dipl.-Ing. Dr. Martin Kaltenberger<br />

Siemens City Vienna<br />

On 10th of March 2008, JV Porr/Strabag were employed<br />

as building contractors for the erection of<br />

Siemens City Vienna. This office building provides<br />

3,000 jobs, a canteen, a conference hall, underground<br />

parking and spacious outdoor facilities. It is<br />

situated directly beside the train station at Siemens<br />

Street, Floridsdorf in Vienna.<br />

Shaping the buildings architecture is an elliptical „Forum“,<br />

an H-shaped „tower“ with an angled facade,<br />

a rectangular “Nordspange” with angular front sides<br />

and „Comline“, a glass covered connecting area.<br />

With approximately 85,000 m 2 of gross floor area<br />

and approximately 15,000 m 2 of basement area, the<br />

site currently belongs to one of the largest buildings<br />

in the Vienna area.<br />

The production of the large dimensioned bored piles<br />

as foundation for the tower was partly carried out<br />

using water as ballast to prevent the intrusion of<br />

stray sand into the groundwater. Energy lines in the<br />

ground piles in conjunction with the concrete core<br />

activation in the floor slabs support the cooling and<br />

heating of the building.<br />

The cantilevered 7 th Floor of the Tower which projects<br />

out 12 m, was fixed with threaded poles in<br />

strained piles on a steel framework to the roof, which<br />

in turn is supported by centrifugally casted concrete<br />

piles and transferred down into the pile foundation.<br />

For reasons of weight reduction hollow plastic balls<br />

were placed in the floor slabs.<br />

One of the biggest challenges was the short construction<br />

time frame and the implementation of the<br />

architectural features such as the cantilever, the inclined<br />

parts, the circular stairways and the slender<br />

columns.<br />

Foto: <strong>PORR</strong>-Archiv<br />

Luftbild Südansicht<br />

38<br />

<strong>PORR</strong>-<strong>NACHRICHTEN</strong> . <strong>158</strong>-<strong>2010</strong>

Hurra! Ihre Datei wurde hochgeladen und ist bereit für die Veröffentlichung.

Erfolgreich gespeichert!

Leider ist etwas schief gelaufen!