Start-Up, Operation, and Maintenance Instructions
Start-Up, Operation, and Maintenance Instructions
Start-Up, Operation, and Maintenance Instructions
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
102<br />
LEGEND NOTES:<br />
1. Remote device.<br />
2. Transformer connected for 480 v primary 120 v secondary. For other<br />
voltages see chart:<br />
PRIMARY SECONDARY<br />
H1-H2 H1-H3 H1-H4 H1-H5 X1-X2 X1-X3 X1-X4<br />
240 416 480 600 99 120 130<br />
230 400 460 575 95 115 125<br />
LL — Control Power Supply<br />
M — Contactor<br />
OP — Oil Pump<br />
PFCC — Power Factor Correction Capacitor<br />
RES — Resistor<br />
S — Contactor<br />
ST — Shunt Trip<br />
TB — Terminal Block<br />
TC — Transition Contactor<br />
VL — Wire Label<br />
C — Contactor<br />
CB — Circuit Breaker<br />
CP — Control Power<br />
CT — Current Transformer<br />
DS — Disconnect Switch<br />
FU — Fuse<br />
GRD — Ground<br />
HPR — High Pressure Relay<br />
ISM — Integrated <strong>Start</strong>er Module<br />
L — Main Supply Power<br />
220 380 440 550 91 110 120<br />
208 500 85 100 110<br />
3. Current transformer<br />
•amps nameplate ratio<br />
•amps effective ratio with primary turns<br />
•polarity marking<br />
Be sure to connect per polarity markings.<br />
4. “S” - “2M” contactors are electrically <strong>and</strong> mechanically interlocked.<br />
5. Live capacitor unit. Deenergize starter. Wait one (1) minute <strong>and</strong> ground<br />
terminals before servicing.<br />
6. All control wiring 14 gage red except as noted.<br />
Fig. 45 — Allen-Bradley Wye-Delta Unit-Mounted <strong>Start</strong>er (cont)