Checklist for commissioning a CONCENTO PLUS nurse call system<br />
This checklist contains all activities that must be performed before a CONCENTO PLUS nurse call system is<br />
commissioned. Use the checklist as a guideline for installation.<br />
If initial start-up assistance / commissioning support by the manufacturer has been requested, the checklist must<br />
have been returned completed. Send the fully completed checklist signed to: Service Centre, <strong>Tunstall</strong> <strong>GmbH</strong>, Mrs.<br />
Wera Westfechtel, phone: +49 (0) 2504 701 - 177, Fax: +49 (0) 2504 701 - 199, e-mail: wwestfechtel@tunstall.de<br />
If the activities in the checklist have not been done in full or have not been done in accordance with the agreements<br />
with the manufacturer, we reserve the right not to become involved in your installation, to abort the service job and to<br />
cancel the agreed appointment and invoice you for the costs incurred.<br />
Task Please complete:<br />
1 The nurse call system fitters have been trained:<br />
1a The fitters are trained as nurse call system experts. Done:<br />
1b The fitters have passed a CONCENTO PLUS system training course. Done:<br />
2 The <strong>Technical</strong> <strong>Manual</strong> for the CONCENTO PLUS system (order no. 00881414)<br />
was available to the fitters and was observed during installation.<br />
3 The cable network was prepared in accordance with the <strong>Technical</strong> <strong>Manual</strong><br />
and the valid regulations.<br />
4 The fully prepared cable network was inspected:<br />
<strong>Tunstall</strong> <strong>GmbH</strong> · Orkotten 66 · 48291 Telgte Germany, www.tunstall.de · 08.11.2012<br />
Yes:<br />
Done:<br />
4a Group bus: Line check data, speech, power supply Done:<br />
4b Ward bus: Line check data, speech, power supply Done:<br />
4c Voltage supply: Line check, polarity Done:<br />
5 The functional ground has been connected as per the <strong>Technical</strong> <strong>Manual</strong>. Done:<br />
6 All devices have been installed and connected in accordance with the<br />
product leaflet and the <strong>Technical</strong> <strong>Manual</strong>.<br />
Done:<br />
7a Is the ConLog PLUS Management Software used? Yes:<br />
No:<br />
7b If yes: The PC is completely assembled. The ConLog PLUS Management<br />
Software has been installed. The PC has been connected to the<br />
management interface in accordance with the <strong>Technical</strong> <strong>Manual</strong>.<br />
8 The following have been tested for all rooms: Notification of presence, all call<br />
devices, call cancellation (call in the room, call in the WC), indication on the<br />
room lamp (see “Checking the light call function of each room” in the<br />
<strong>Technical</strong> <strong>Manual</strong>)<br />
Done:<br />
Done:<br />
9 Should external devices / systems be connected to the nurse call system? Yes:<br />
No:<br />
10a If yes: The following devices / systems have been connected and set up in<br />
accordance with the requirements of the <strong>Technical</strong> <strong>Manual</strong>:<br />
10b Separate Terminals, RABs or the Group Electronic have been used for<br />
connecting the external devices / systems.<br />
11 All forms required for commissioning support have been completed in full and<br />
sent back to the service centre: Programming tables, shift table/group coupling.<br />
Place, date<br />
Checklist completed by:<br />
Position in the company:<br />
Yes:<br />
No:<br />
Done: