88.1.1 All measurements shall be recorded in sextuplicate on standard<br />

measurement sheets supplied by EMPLOYER and submitted<br />

to EMPLOYER/CONSULTANT <strong>for</strong> scrutiny and passing.<br />

88.1.2 EMPLOYER/CONSULTANT shall scrutinise and check the<br />

measurements recorded on the sheets and shall certify<br />

correctness <strong>of</strong> the same on the measurement sheets.<br />

88.1.3 ENGINEER-IN-CHARGE shall pass the bills after carrying<br />

out the comprehensive checks in accordance with the terms<br />

and conditions <strong>of</strong> the CONTRACTS, within 7 days <strong>of</strong><br />

submission <strong>of</strong> the bills, complete in all respects and send the<br />

same to the Employer to effect payment to the<br />

CONTRACTOR.<br />

88.1.4 <strong>GAIL</strong> shall make all endeavour to make payments <strong>of</strong><br />

undisputed amount <strong>of</strong> the bills submitted based on the joint<br />

measurements within 15 (Fifteen) days from the date <strong>of</strong><br />

certification by the Engineer-in-Charge.<br />

88.1.5 Measurements shall be recorded as per the methods <strong>of</strong><br />

measurement spelt out in EMPLOYER/CONSULTANT<br />

SPECIFICATIONS /CONTRACT DOCUMENT.<br />

EMPLOYER/CONSULTANT shall be fully responsible <strong>for</strong><br />

checking the measurements quantitatively and qualitatively as<br />

recorded in the Measurement Books/ Bills.<br />

88.1.6 While preparing the final bills overall measurements will not<br />

be taken again. Only volume <strong>of</strong> work executed since the last<br />

measured bill alongwith summary <strong>of</strong> final measurements will<br />

be considered <strong>for</strong> the final bill. However, a detailed check<br />

shall be made as to missing measurements and in case there<br />

are any missing items or measurements the same shall be<br />

recorded.<br />

88.2 SECURED ADVANCE ON MATERIAL:<br />

Unless otherwise provided elsewhere in the tender, no<br />

`Secured Advance' on security <strong>of</strong> materials brought to site <strong>for</strong><br />

execution <strong>of</strong> contracted items(s) shall be paid to the<br />

Contractor whatsoever.<br />

88.3 DISPUTE IN MODE OF MEASUREMENT:<br />

In case <strong>of</strong> any dispute as to the mode <strong>of</strong> measurement not<br />

covered by the CONTRACT to be adopted <strong>for</strong> any item <strong>of</strong><br />

WORK, mode <strong>of</strong> measurement as per latest Indian Standard<br />

Specifications shall be followed.<br />

88.4 ROUNDING OF AMOUNTS:<br />