4) Repairing :<br />
a) Intruments : 137<br />
b) Relays : 208<br />
c) Megger : 132<br />
d) Winding <strong>of</strong> coils : 103<br />
5) a) Cable testing, H.P. Testing & Special Testing : 13<br />
b) Cable fault locations at different places : 56<br />
c) Transformer testing at manufacturers, premises : 12,761<br />
d) Transformer oil testing at manufacturers, premises : 1200 KL<br />
e) Dynamic short-ckt. & impulse testing witnessed : 19<br />
6) Repair/Reconditioning <strong>of</strong> Transformer/CT/DT etc. :<br />
i) No. <strong>of</strong> Transformers repaired (Workshop) : 14<br />
ii) Aggregate MVA <strong>of</strong> (i) : 51<br />
iii) No. <strong>of</strong> CT’s rep/reconditioned at Workshop : 12<br />
iv) No. <strong>of</strong> PT’s repaired/reconditioned at Workshop : Nil<br />
v) No. <strong>of</strong> Bushing/repaired/reconditioned at Workshop : 3<br />
vi) No. <strong>of</strong> Transformer repaired at site : 8<br />
vii) Aggregate MVA <strong>of</strong> (vi) : 57.5<br />
viii) Survey <strong>of</strong> defective transformer at site : 10 (269.6 MVA)<br />
7) Centralised & Decentralised bulk consumers’ meters & accessories :<br />
i) No. <strong>of</strong> TOD meters tested at Laboratory : 950<br />
ii) No. <strong>of</strong> bulk consumers, tariff meters attended : 2123<br />
iii) As found test <strong>of</strong> Energy Meter : 5<br />
iv) No. <strong>of</strong> meters tested outside agency work : 14<br />
v) Testing <strong>of</strong> Inter-organisational meters : 85<br />
vi) No. <strong>of</strong> Accucheck tested at lab : 23<br />
vii) No. <strong>of</strong> Sub-Stations attended for energy audit metering : 107<br />
Annual Report 2006-2007<br />
147