A. MAJOR WORK TO BE DONE DURING 2007-08<br />

Sl. Description Present status Remarks<br />

No.<br />

<strong>of</strong> work progress<br />

1. Rishra-Jeerat 220 KV D/C Line To be completed<br />

in 2007-08<br />

2. LILO <strong>of</strong> 220 KV Santaldihi-Durgapur 220 KV line at <strong>the</strong> 96% To be completed<br />

proposed Asansol 220 KV Sub-Stn. in 2007-08<br />

3. 132 KV Tr. Line on D/C Tower by tapping <strong>of</strong> one Ckt. <strong>of</strong> 30% To be completed<br />

Malda-Gokarna 132 KV Tr. Line for Bulk Power supply to in 2007-08<br />

Ambuja Cement Eastern Ltd. with construction <strong>of</strong><br />

132 KV Line Bay at M/s. Ambuja Cement Eastern Ltd.,<br />

Farakka and future Sub-Stn. <strong>of</strong> <strong>WBSEB</strong>.<br />

4. Construction <strong>of</strong> 2 nos. 132 KV Bays at Raghunathganj 35% To be completed<br />

132/33 KV Sub-Stn. by LILO <strong>of</strong> 1st Ckt. <strong>of</strong> in 2007-08<br />

Gokarna - Malda 132 KV D/C Line.<br />

5. Traction <strong>power</strong> supply <strong>of</strong> M/s. Easter Railway 80% To be completed<br />

at Cossimbazar. in 2007-08<br />

6. Construction <strong>of</strong> 2 nos. 132 KV Bays at Dhulian 30% To be completed<br />

132 KV Sub-Stn. as incoming Feeder. in 2007-08<br />

7. Construction <strong>of</strong> 132 KV Line Bays at NBU and 30% To be completed<br />

Siliguri 132 KV Sub-Stn. in 2007-08<br />

8. Bulk <strong>power</strong> supply to Binnaguri MES by drawal <strong>of</strong> 70% To be completed<br />

S/C KV Line from Banerhat to Binnaguri. in 2007-08<br />

9. Erection <strong>of</strong> one 220 KV Bay at KTPP 400/220/132 KV 96% To be completed<br />

Sub-Stn. for KTPP - Haldia D/C Line at KTPP end. in 2007-08<br />

10. Traction <strong>power</strong> supply to SER at Tamluk. 20% To be completed<br />

in 2007-08<br />

11. Bulk Power supply to Hooghly Metcoke & Power 60% To be completed<br />

Supply Co. at Haldia. in 2007-08<br />

12. Augmentation <strong>of</strong> 132/33 KV existing Sub-Stn. at KLC 10% To be completed<br />

to 220/132/33 KV along with construction <strong>of</strong> 220 KV in 2007-08<br />

D/C Tr. Line by single circuit LILO <strong>of</strong> Jeerat -<br />

Lakmikantapur 220 KV D/C Line.<br />

Annual Report 2006-2007<br />

37