27.07.2014 Views

Next part of the power scenario of the WBSEB comprises - Infraline

Next part of the power scenario of the WBSEB comprises - Infraline

Next part of the power scenario of the WBSEB comprises - Infraline

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

PURULIA PUMPED STORAGE PROJECT<br />

“Declared MEGA POWER PROJECT by MOP, Govt. <strong>of</strong> India on 6 December 2005”<br />

The State <strong>of</strong> West Bengal and <strong>the</strong> Eastern Region is having predominantly Thermal Power Generation system<br />

with an insignificant capacity <strong>of</strong> Hydro Power. In <strong>the</strong> region <strong>the</strong> Peak demand is suppressed due to shortage<br />

<strong>of</strong> peaking <strong>power</strong> whereas <strong>the</strong>re is surplus energy during night. In <strong>the</strong> present system <strong>the</strong> Hydro Thermal mix<br />

in West Bengal is 04:96 and that <strong>of</strong> Eastern Region is around 14:86 against a desired level <strong>of</strong> 40:60. The<br />

<strong>the</strong>rmal predominant Power generating region has to cater peak, <strong>of</strong>f peak, fluctuating as well as base load<br />

with a serious effect on frequency. Also running <strong>of</strong> <strong>the</strong>rmal <strong>power</strong> station at lower load for considerable period<br />

reduces <strong>the</strong> efficiency drastically and causes severe and quicker wear & tear <strong>of</strong> <strong>the</strong> plant. Also due to high<br />

variable operating cost, slow in load variation response, <strong>the</strong>rmal facilities are not felt a good mean to supply<br />

<strong>the</strong> peak demand. In order to achieve a better generation mix and more efficient electricity supply in <strong>the</strong><br />

region, <strong>the</strong> implementation <strong>of</strong> Purulia Pumped Storage Project <strong>of</strong> capacity 900 MW (4 x 225 MW) is taken up<br />

in Ayodhya hills in <strong>the</strong> Purulia district <strong>of</strong> West Bengal under P.S. Bagmundi.<br />

The field investigation and preparation <strong>of</strong> Detailed Project Report (DPR) was completed by <strong>the</strong> West Bengal<br />

State Electricity Board with <strong>the</strong> loan assistance <strong>of</strong> Japan Bank for International Cooperation (JBIC), erstwhile<br />

Overseas Economic Cooperation Fund (OECF), Japan against Loan Agreement No. ID-P 44 dated 10 February<br />

1988 and <strong>the</strong> same was concluded in February 1993. The DPR <strong>of</strong> <strong>the</strong> project was submitted to CEA by<br />

<strong>WBSEB</strong> in May 1992. The Techno-Economic clearance was accorded by CEA in July 1992 subject to <strong>the</strong><br />

condition <strong>of</strong> Environment and Forest (MOEF) clearance. The Ministry <strong>of</strong> Environment & Forests (MOEF)<br />

cleared <strong>the</strong> Project on 13 October 1993. And finally, <strong>the</strong> project was cleared by <strong>the</strong> Planning Commission on<br />

9 February 1994. M/s. Water & Power Consultancy Services (WAPCOS) in association with Central Electricity<br />

Authority (CEA) and Central Water Commission (CWC) were associated for <strong>the</strong> project as local Consultants<br />

and M/s. Electric Power Development Company (EPDC), Japan as Foreign Consultant.<br />

232.42 ha <strong>of</strong> forest land (including submergence area <strong>of</strong> 185.80 ha for two Reservoirs and 46.62 ha for <strong>part</strong> <strong>of</strong><br />

road, ancillary facilities etc.) was diverted to <strong>the</strong> Project in first phase in December 1997. Fur<strong>the</strong>r, formal<br />

clearance for diversion <strong>of</strong> 131.67 ha <strong>of</strong> additional forest land (required for Quarry/Stockpile Yard & Processing<br />

Area/Construction facility/Transmission Lines etc.) was accorded by <strong>the</strong> MOEF/Govt. <strong>of</strong> India in February<br />

2002. Thereafter, formal clearance for ano<strong>the</strong>r 9.07 ha forest land for rock quarry for Upper Dam <strong>of</strong> <strong>the</strong> Project<br />

was accorded by <strong>the</strong> Ministry on April 2003. Thus aggregated total forest land diverted to <strong>the</strong> Project became<br />

382.27 ha. In addition to above, possission <strong>of</strong> 14.67 ha <strong>of</strong> private land and 1.655 ha <strong>of</strong> vested land in Mouza-<br />

Barriya, PS. Bagmundi, required for Clay Core Quarry <strong>of</strong> Upper Dam has already been received. It would be<br />

worthwhile to mention here that no family has lost any land or any house and no historical or cultural moments<br />

were affected due to diversion <strong>of</strong> <strong>the</strong> forest land. Also, <strong>WBSEB</strong> agreed that an area <strong>of</strong> 113.945 ha (9.915 ha in<br />

Phase-I and 104.03 ha in Phase-II) <strong>of</strong> prime forest land to be returned to <strong>the</strong> Forest De<strong>part</strong>ment on demand<br />

after completion <strong>of</strong> <strong>the</strong> Project and after reclamation <strong>of</strong> <strong>the</strong> said land. And, as such, exchange <strong>of</strong> 2.25 acre<br />

forest land, near Lower Dam, is going on.<br />

The implementation <strong>of</strong> <strong>the</strong> Project is now under progress with loan assistance <strong>of</strong> Japan Bank for International<br />

Cooperation (JBIC) erstwhile Overseas Economic Cooperation Fund (OECF). The original estimated cost <strong>of</strong><br />

<strong>the</strong> project was 1,07,150 Million Yen (Rs. 3188.90 crore) covering <strong>the</strong> element <strong>of</strong> escalation, contingencies<br />

and IDC till commissioning <strong>of</strong> <strong>the</strong> Project.<br />

Out <strong>of</strong> <strong>the</strong> above, <strong>the</strong> JBIC had sanctioned 20,520 Million Japanese Yen (Rs. 610.7 crore) in first tranche. The<br />

loan Agreement (No. ID-P 98) was signed on 28 February 1995 with date <strong>of</strong> effectuation as 12 April 1995 and<br />

final date <strong>of</strong> disbursement as 12 December 2004. And within <strong>the</strong> stipulated date, PPSP-<strong>WBSEB</strong> finally utilized<br />

20,388 MY (99.36%) <strong>of</strong> it.<br />

The Second Tranche Loan Agreement (No. ID-P152) dated 31 March 2004 was effectuated on and from 18<br />

June 2004 with sanctioned amount <strong>of</strong> 23,578 MY (Rs. 910.3 crore) and final date <strong>of</strong> disbursement as 18 June<br />

2009. And till 20 March 2007, PPSP-<strong>WBSEB</strong> has already utilized 23,052,059 MY (98%) <strong>of</strong> it.<br />

There was a need for <strong>the</strong> Third Tranche Loan from JBIC at <strong>the</strong> right time slot. There stands a formal Project<br />

proposal by <strong>the</strong> Govt. <strong>of</strong> India seeking financial assistance from Govt. <strong>of</strong> Japan. And finally Draft Minutes <strong>of</strong><br />

Discussion (MOD) amongst JBIC, Govt. <strong>of</strong> India, Govt. <strong>of</strong> West Bengal and <strong>WBSEB</strong> has been signed on 29<br />

November 2005. The latest anticipated Project cost at <strong>the</strong> time <strong>of</strong> appraisal <strong>of</strong> PPSP III became 73,521 Million<br />

Annual Report 2006-2007<br />

27

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!