SECTION 4.0<br />

BLACKBURN TREATMENT OPTIONS<br />

The following seven options have been identified for upgrading the <strong>Blackburn</strong><br />

sewage collection area and WWTP:<br />

4.1 OPTION 1 - DECOMMISSION EXISTING BLACKBURN WWTP AND<br />

ROUTE ALL FLOW TO LANSDOWNE ROAD WWTP MA<br />

FORCEMAINlGRAVITY SEWER CONNECTION<br />

4.1.1 Outline<br />

In this option the existing sewage lagoons would be decommissioned and all<br />

flows transferred for treatment at the Lansdowne Road WWTP via a new<br />

forcemain and trunk gravity sewer from the Mackus Road pumpstation. A<br />

schematic representation of this option is presented in Figure 4.1. An VI<br />

reduction program is to be initiated and completed to reduce the volume of<br />

wasfewater being transferred during wet weather and snowmelt conditions.<br />

The existing Mackus Road pumpstation would be upgraded and a new, small<br />

pumpstation would be constructed at the Blackbum WWTP site. It is believed<br />

that the Lansdowne Road WWTP has sufficient capacity to handIe the<br />

projected future hydraulic and BODflSS loadings from the Blackbum sewage<br />

collection area.<br />

Key activities or capital works associated with this option are as follows:<br />

Implement and complete I/I reduction program.<br />

Decommission lagoons and rehabilitate site for other use.<br />

<strong>Upgrade</strong> Mackus Road pumpstation to handle projected increased flows.<br />

Construct t ~nk gravity sewer and/or forcemain to transfer all flows from<br />

Blackbum sewerage area to Lansdowne Road WWTP.<br />

<strong>Upgrade</strong> downtown sewage collection pipework to handle increased flows<br />

from Blackbum sewerage area<br />

Construct sewage pumpstation at Blackbum WWTP site and construct<br />

connecting forcemain discharging to Mackus Road pumpstation.