assessment process. Each team member should also review program documentation affecting<br />
their assigned area. The Documentation Request List provided in Appendix C should be used<br />
as a baseline for forming the documentation request and tailored to match the program and<br />
acquisition phase. The scope and depth of logistics support information in these documents<br />
can vary significantly from program to program and by acquisition phase. The PO is<br />
responsible for providing the required information to the <strong>ILA</strong> team. The requested<br />
documentation should be received by the <strong>ILA</strong> team no later than four weeks before the <strong>ILA</strong>.<br />
This will minimize time spent obtaining documentation time during the actual review period<br />
and provide team members the opportunity to review the documents in advance of the <strong>ILA</strong>.<br />
5.4. Meetings and Presentations.<br />
Before, during, and at the completion of an <strong>ILA</strong>, it is critical that meetings and<br />
presentations be conducted to communicate expectations and should include PM<br />
presentations, updates, and discussions. A discussion of these meetings and presentations is<br />
provided in Appendix H to ensure there is a standard <strong>ILA</strong> assessment and reporting process in<br />
place.<br />
5.5. <strong>ILA</strong> Final Report.<br />
The <strong>ILA</strong> team leader is responsible for preparing the <strong>ILA</strong> final report, coordinating it<br />
with the PO, and submitting it to the PM, as well as the appropriate PEO, Product <strong>Center</strong><br />
Commander and/or ALC Commander. The MDA should use the report to verify the adequacy<br />
of the program’s product support planning and implementation prior to the milestone decision.<br />
The <strong>ILA</strong> team leader will provide information copies of the final report to AFMC/LG,<br />
Secretary of the Air Force (SAF)/AQ, SAF/IE, AF/IL, and appropriate warfighter<br />
stakeholders.<br />
5.5.1. The Final Report should clearly distinguish issues that need to be resolved and<br />
the time frame for resolution (e.g., before the acquisition milestone decision, contract<br />
award, release of the request for proposal, or operational evaluation). All engineering<br />
issues should be resolved before release of the RFP and subsequent contract award.<br />
The report should contain, at a minimum, the following information:<br />
• Purpose, scope, and dates of the assessment<br />
• A summary of the ratings for each sustainment element<br />
• Overall assessment of the program’s product support planning and<br />
implementation<br />
• Brief description of the system/equipment<br />
• Listing of team members and areas covered<br />
• All deficiencies/issues identified during the assessment citing specific criteria<br />
• Recommended corrective actions and timelines<br />
• Best practices and other processes of note<br />
• Process or policy barriers that require attention<br />
Version 1: January 2006 10<br />