D-3. Product Support Management (continued)<br />

Evaluation Criteria<br />

• Is a Business Case Analysis (BCA) used to support individual PBL<br />

decisions Does that BCA estimate costs, describe the benefits of<br />

alternative product support strategies (e.g., buying a predetermined level<br />

of availability to meet warfighter’s objectives) and has it been validated<br />

by the Air Force Cost Analysis Agency<br />

Milestone<br />

B C FRP<br />

X U U<br />

• Are reviews scheduled in time to support programmatic reviews X U U<br />

• Is the PBL Product Support Integrator (PSI) identified and is a long-term X U U<br />

agreement finalized that:<br />

o Identifies all stakeholder roles and responsibilities<br />

o Identifies sources and data to collect and use<br />

o Establishes review/reporting requirements and dispute resolution<br />

procedures<br />

• Are trade studies conducted on a continuous basis to ensure that<br />

performance and supportability goals are met Do trade studies consider<br />

alternate operating and support concepts, with specific consideration of<br />

performance requirements<br />

X U U<br />

• Is product support included in the life-cycle system engineering approach X U U<br />

to supportability, including information interoperability requirements<br />

• Is public-private partnering (PPP) optimized for best-value support X U U<br />

• Are contract terms sufficient to meet surge requirements and ensure reestablishment<br />

X U U<br />

of organic or commercial support capability as necessary<br />

• Has a risk management program been established that includes both X U U<br />

government and contractor participation and sharing of risks<br />

• Have product support program risks and mitigation strategies been X U U<br />

identified and assessed<br />

• Have post-IOC plans been developed for continued evolution of<br />

X U<br />

sustainment strategies<br />

• Is continued technology refreshment planned to increase reliability and/or X<br />

reduce Operating and Support cost<br />

• Are product support and overall sustainment requirements referenced in X U U<br />

the CDD and CPD<br />

2. Warranty<br />

• Are mutually beneficial incentives established to facilitate long-term<br />

business relationships Is the provider given incentives to meet specified<br />

product quality and performance measures<br />

X U U<br />

• Has cost-benefit analysis been conducted to determine the<br />

appropriateness, affordability, and value of implementing a warranty<br />

plan<br />

• Were warranties considered and integrated to the program's logistics<br />

support strategy, whether PBL or traditional<br />

X U U<br />

X U U<br />

Version 1: Jan 2006 52<br />

Air Force Independent Logistics Assessment <strong>Handbook</strong>