Subject : Pre-bid clarification on queries received from Industry Participants of TPWS: Date-30.06.2011<br />

TENDER NO. WR/S&T/HQ/2010-11/05 Virar (at Km 60)-Vadodara (at Km 397) section<br />

Sr. No. Cl. No. Firm T<br />

y<br />

p<br />

28 Annexure 2<br />

RDSO spec for<br />

TPWS, general<br />

requirements<br />

ch 4.12<br />

Thales<br />

29 Provisional<br />

Acceptance<br />

Certificate 4.39<br />

Point C (Page<br />

No. 68)<br />

Hytronics<br />

Original Text Clarification needed Clarification of <strong>Western</strong> <strong>Railway</strong><br />

TThe brake commands generated by the TPWS shall<br />

-be used for application of service & emergency<br />

Rbrakes of locomotives.<br />

D<br />

S<br />

O<br />

T<br />

GIt is necessary to specify the maximum Purchaser<br />

response time to start testing each sub-section or<br />

rolling stock, after contractor communicates that it is<br />

ready to be handed-over in case the equipment is<br />

performing correctly.<br />

Can you provide us Emergency braking &<br />

service braking details and their deceleration<br />

factor (Min. and Max.)<br />

Suggested amendment, to add the<br />

following: "Purchaser shall provide all<br />

necessary personnel and resources to start<br />

the testing, within 3 days from receiving<br />

advice of completion of one sub-section or<br />

rolling stock from the contractor.<br />

It will be provided after award of<br />

contract.<br />

<strong>Tender</strong> Condition remain unchanged.<br />

30 Liquidated<br />

Damages &<br />

<strong>Railway</strong>'s rights<br />

4.49 (Page No.<br />

75)<br />

Hytronics<br />

GWhat does "<strong>Railway</strong> is not satisfied of the works"<br />

mean Is the satisfaction associated to an objective<br />

and material breach of the Contractor<br />

This Para is self explanatory and<br />

should be read in totality. Overall<br />

performance of TPWS system<br />

should be satisfactory as per<br />

specification and tender conditions.<br />

31 Warranty<br />

maintenance<br />

4.44.1 (Page<br />

No. 72)<br />

Hytronics<br />

Fault rectification and regular preventive<br />

Gmaintenance of the total installation is to be done by<br />

the contractor within the warranty period of Five<br />

Years under warranty<br />

maintenance…………………………………. The<br />

maintenance engineer of the contractor will visit<br />

Master station and all the base stations at least<br />

twice in a month for ensuring implementation of<br />

maintenance plan and attend to any fault on the<br />

systems.<br />

Please clarify what means "regular<br />

preventive maintenance" and if this visit will<br />

be mandatory.<br />

This Para is self explanatory and<br />

should be read in totality.<br />

32 Warranty<br />

maintenance<br />

4.44.1 (Page<br />

No. 72)<br />

Hytronics<br />

GThe penalty as mentioned in Para 4.40.2 will be<br />

applicable for any default on account of nonavailability<br />

of spares.<br />

Please<br />

clarify the details about amount and cap of this<br />

penalty.<br />

This Para is self explanatory and<br />

should be read in totality.<br />

Pre Bid Queries for TPWS 10