Subject : Pre-bid clarification on queries received from Industry Participants of TPWS: Date-30.06.2011<br />
TENDER NO. WR/S&T/HQ/2010-11/05 Virar (at Km 60)-Vadodara (at Km 397) section<br />
Sr. No. Cl. No. Firm T<br />
y<br />
p<br />
28 Annexure 2<br />
RDSO spec for<br />
TPWS, general<br />
requirements<br />
ch 4.12<br />
Thales<br />
29 Provisional<br />
Acceptance<br />
Certificate 4.39<br />
Point C (Page<br />
No. 68)<br />
Hytronics<br />
Original Text Clarification needed Clarification of <strong>Western</strong> <strong>Railway</strong><br />
TThe brake commands generated by the TPWS shall<br />
-be used for application of service & emergency<br />
Rbrakes of locomotives.<br />
D<br />
S<br />
O<br />
T<br />
GIt is necessary to specify the maximum Purchaser<br />
response time to start testing each sub-section or<br />
rolling stock, after contractor communicates that it is<br />
ready to be handed-over in case the equipment is<br />
performing correctly.<br />
Can you provide us Emergency braking &<br />
service braking details and their deceleration<br />
factor (Min. and Max.)<br />
Suggested amendment, to add the<br />
following: "Purchaser shall provide all<br />
necessary personnel and resources to start<br />
the testing, within 3 days from receiving<br />
advice of completion of one sub-section or<br />
rolling stock from the contractor.<br />
It will be provided after award of<br />
contract.<br />
<strong>Tender</strong> Condition remain unchanged.<br />
30 Liquidated<br />
Damages &<br />
<strong>Railway</strong>'s rights<br />
4.49 (Page No.<br />
75)<br />
Hytronics<br />
GWhat does "<strong>Railway</strong> is not satisfied of the works"<br />
mean Is the satisfaction associated to an objective<br />
and material breach of the Contractor<br />
This Para is self explanatory and<br />
should be read in totality. Overall<br />
performance of TPWS system<br />
should be satisfactory as per<br />
specification and tender conditions.<br />
31 Warranty<br />
maintenance<br />
4.44.1 (Page<br />
No. 72)<br />
Hytronics<br />
Fault rectification and regular preventive<br />
Gmaintenance of the total installation is to be done by<br />
the contractor within the warranty period of Five<br />
Years under warranty<br />
maintenance…………………………………. The<br />
maintenance engineer of the contractor will visit<br />
Master station and all the base stations at least<br />
twice in a month for ensuring implementation of<br />
maintenance plan and attend to any fault on the<br />
systems.<br />
Please clarify what means "regular<br />
preventive maintenance" and if this visit will<br />
be mandatory.<br />
This Para is self explanatory and<br />
should be read in totality.<br />
32 Warranty<br />
maintenance<br />
4.44.1 (Page<br />
No. 72)<br />
Hytronics<br />
GThe penalty as mentioned in Para 4.40.2 will be<br />
applicable for any default on account of nonavailability<br />
of spares.<br />
Please<br />
clarify the details about amount and cap of this<br />
penalty.<br />
This Para is self explanatory and<br />
should be read in totality.<br />
Pre Bid Queries for TPWS 10