Subject : Pre-bid clarification on queries received from Industry Participants of TPWS: Date-30.06.2011<br />

TENDER NO. WR/S&T/HQ/2010-11/05 Virar (at Km 60)-Vadodara (at Km 397) section<br />

Sr. No. Cl. No. Firm T<br />

y<br />

p<br />

24 Ch 4.3.2 (VII) Thales TIn case of distributed assets, Contactor has to lay Do LEU shall be made centralized. If yes, is<br />

-power cable from the Relay Room/Relay Hut to LEU the relay room is AC or Non Ac where LEU<br />

Wlocation in trench as per technical specification / site cabinet is going to be placed or installed. It<br />

S requirement and derive 110 Volt AC for LEU power will be helpful for calculating the Reliability<br />

Tsupply , with the help of 230/110 Volt transformer , and Availability of the LEU system.<br />

-to be installed in location box or at suitable location.<br />

RThe installation of location box will be done by<br />

Dcontractor as per site requirement. However, at<br />

Ssome locations <strong>Railway</strong> may decide to keep LEUs<br />

Oinside Relay Room/Relay Hut and power supply for<br />

LEUs may be taken from 110 V or 230 V AC power<br />

supply arrangement. <strong>Tender</strong>er should indicate the<br />

power (voltage, current and power consumption)<br />

requirement of the equipments.<br />

Original Text Clarification needed Clarification of <strong>Western</strong> <strong>Railway</strong><br />

LEU shall be centralized in Non-AC<br />

Relay room / Equipment Room /<br />

Relay huts to the extent possible.<br />

25 ch 4.3.2 (VII) -<br />

We think it is<br />

editorial<br />

mistake in<br />

numbering the<br />

points in the<br />

tender<br />

Thales<br />

Installation practices of all signalling gears should be<br />

Gas per the Signal Engineering Manual (New) of<br />

Indian <strong>Railway</strong> and to suit the latest correction slips,<br />

<strong>Western</strong> <strong>Railway</strong> and OEM‟s practices in vogue.<br />

The tenderer shall do no work that may interfere<br />

with train traffic until adequate protection has been<br />

arranged as per the instruction of the Engineer in<br />

charge. All the tools & Measuring Instruments,<br />

required for installation & Testing will have to be<br />

brought by the tenderer at his own cost.<br />

Can you please provide us the Signal<br />

Engineering manual and also the latest<br />

correction slip details.<br />

Can you also provide the time table of the<br />

trains so that we can schedule our<br />

installation activities in such a way there will<br />

not be any interference with train traffic.<br />

1. Signal Engineering Manuals can<br />

be seen on the website<br />

www.indianrailways.gov.in 2. Timetable<br />

can be purchased from <strong>Railway</strong><br />

Book stall.<br />

26 ch 6 A 4.2 Thales TProvision of testing facility at Electric Loco /MEMU<br />

-Shed / simulation /Training centre (Vadodara) each<br />

Rlot consisting of following Items:-<br />

D<br />

SDriver MMI-ETCS Level1( for both cabs) (CENLEC<br />

O Type) - Number of qty - 1 No<br />

T<br />

27 Annexure 2 Thales GInformation to be supplied by the purchaser.<br />

RDSO spec for<br />

Relevant G & SR rules applicable along with speed<br />

TPWS, ch 14 g<br />

restriction limits.<br />

Is one MMI is sufficient enough for testing<br />

and fulfilling the requirements as the WAP 4<br />

loco is twin cab and MEMU is double sided<br />

cab.<br />

Can WR provide us the G&SR rules<br />

In the Loco Shed, testing may be<br />

done on the MMI installed on<br />

locomotive/MEMU. However, this<br />

requirement is for training and<br />

simulation purpose.<br />

It will be provided after award of<br />

contract.<br />

Pre Bid Queries for TPWS 9