Subject : Pre-bid clarification on queries received from Industry Participants of TPWS: Date-30.06.2011<br />

TENDER NO. WR/S&T/HQ/2010-11/05 Virar (at Km 60)-Vadodara (at Km 397) section<br />

Sr. No. Cl. No. Firm T<br />

y<br />

p<br />

117 Page no.89,<br />

14.0 c<br />

118 Page no.89,<br />

14.0 e<br />

119 Page no.89,<br />

14.0 e & f<br />

120 Page no.90,<br />

14.0 (j)<br />

121 Page no.90,<br />

14.0 (k)<br />

122 Page no.90,<br />

14.0 (n) iv &<br />

Page No<br />

101,B1.2<br />

123 <strong>Tender</strong> Notice<br />

Page-1<br />

Siemens<br />

Siemens<br />

Siemens<br />

Siemens<br />

Siemens<br />

T<br />

-<br />

W<br />

S<br />

T<br />

-<br />

W<br />

E<br />

T<br />

-<br />

W<br />

S<br />

T<br />

-<br />

R<br />

D<br />

S<br />

T<br />

-<br />

W<br />

S<br />

E<br />

T<br />

-<br />

W<br />

S<br />

T<br />

-<br />

W<br />

S<br />

Original Text Clarification needed Clarification of <strong>Western</strong> <strong>Railway</strong><br />

Please provide the Signaling Role plan for<br />

proposed section, in order to optimize<br />

quantities of LEU & Balises.<br />

Power supply for the On-board mentioned<br />

only 110V, whether it is AC or DC<br />

Power supply for track side will be provided<br />

as 110V AC.<br />

Since our LEU module internally converts<br />

AC to required DC voltages, the additional<br />

conversion of AC to DC power supply (as<br />

per RDSO specification 6.26) may not<br />

require. Also the back up power supply<br />

arrangement can be provided accordingly<br />

As per 14.0 (i) the CENELEC DMI‟s to be<br />

provided, hence 8 position switch may not<br />

require, since this feature is covered as per<br />

RDSO clause 6.18.1.2 (V).<br />

Please provide the Signaling Role plan for<br />

proposed section, in order to meet the<br />

requirement as per cl 4.5 to 4.10<br />

Signaling Roll plan for proposed<br />

section is being made part of tender<br />

document.<br />

The nominal supply is 110 Volts DC<br />

with variation from 70 V to 136V.<br />

For track side : The Nominal votage<br />

is 110 Volts AC 50 Hz with variation<br />

of -30% to +20% over the nominal<br />

voltage. The back up is to be<br />

provided as per amended clause<br />

14.0(f) issued by RDSO. The changes<br />

in this regard will be notified,<br />

subsequently.<br />

For CENELEC- DMI, the 8 position<br />

switch is not required, necessary<br />

amendment in this regard will be<br />

issued.<br />

Signaling Roll plan for proposed<br />

section is being made part of tender<br />

document.<br />

Siemens<br />

Please clarify the location of LEU will be LEU shall be centrallised in Relay<br />

centralized or near the signal. This is room / Equipment Room / Relay<br />

required to arrive at the quantity of types of huts, as far as possible.<br />

LEU cabinets.<br />

Siemens<br />

T<br />

G Please make completion period of 24 month The completion period for this is 18<br />

months. However, any change in this<br />

regard will be notified, subsequently.<br />

124 SCC Section<br />

4.40 Page no<br />

68<br />

125 SCC Section<br />

4.44 Page No<br />

70.<br />

Siemens<br />

Siemens<br />

T<br />

-<br />

W<br />

S<br />

T<br />

-<br />

R<br />

D<br />

S<br />

O<br />

T<br />

Can the Maintenance period of 1 year<br />

started immediately after commissioning of<br />

each section<br />

Request for warranty period to be reduced to<br />

24 months instead 60 month.<br />

The Maintenance period will start<br />

after issue of PAC.<br />

<strong>Tender</strong> Condition remain<br />

unchanged.Warranty for a period of<br />

Five years should be given by the<br />

contractor/OEM from the date of<br />

issue of Final Acceptance Certificate<br />

Pre Bid Queries for TPWS 49