Subject : Pre-bid clarification on queries received from Industry Participants of TPWS: Date-30.06.2011<br />
TENDER NO. WR/S&T/HQ/2010-11/05 Virar (at Km 60)-Vadodara (at Km 397) section<br />
Sr. No. Cl. No. Firm T<br />
Original Text Clarification needed Clarification of <strong>Western</strong> <strong>Railway</strong><br />
y<br />
p<br />
After clearance of the on board equipment installed<br />
for safe working Loco /MEMU and fit for<br />
commercial run, the TPWS system will be made<br />
functional in the concerned Loco / MEMU. After<br />
completion of installation, testing and successful<br />
commissioning of TPWS system in the Loco /<br />
MEMU with the on board supply for each batch (as<br />
per Para 4.6 of SCC) of supplied equipments, a<br />
„Provisional Acceptance Certificate‟ (PAC) will be<br />
issued for that batch of equipments after<br />
observance period of one month.<br />
II. Track Side Equipments & Accessories<br />
(a) Immediately after completion of the work at each<br />
sub-sections (i.e.100 Kms, 100Kms, 140 Kms on<br />
Virar -Vadodara section) or still shorter, the<br />
contractor shall certify and advise the <strong>Railway</strong>s in<br />
writing that the installation is (i) complete, (ii) ready<br />
for satisfactory service and (iii) ready to be handed<br />
over. He will also place at the disposal of the<br />
purchaser the required staff for inspection, testing<br />
and putting it into operation.<br />
(b) The test or tests specified in Technical<br />
specification will be conducted jointly by the<br />
<strong>Railway</strong>s and contractor as soon as possible after<br />
receipt of advice regarding completion of one sub -<br />
section by the contractor. The test schedule shall be<br />
furnished by the contractor which will be modified by<br />
mutual discussion between the contractor and<br />
<strong>Railway</strong> before finalization. Any component,<br />
modules, sub-assemblies or equipment failing<br />
during the commissioning test shall be<br />
replaced/repaired free of cost by contractor.<br />
Pre Bid Queries for TPWS 29