Subject : Pre-bid clarification on queries received from Industry Participants of TPWS: Date-30.06.2011<br />
TENDER NO. WR/S&T/HQ/2010-11/05 Virar (at Km 60)-Vadodara (at Km 397) section<br />
Sr. No. Cl. No. Firm T<br />
y<br />
p<br />
33 3.1 General<br />
condition of<br />
contract (Page<br />
No. 38)<br />
Hytronics<br />
Original Text Clarification needed Clarification of <strong>Western</strong> <strong>Railway</strong><br />
GIt is stated that General Conditions of Contract<br />
(GCC) Works Hand Book Parts I & II August 98<br />
edition / latest edition (with latest amendments), may<br />
be purchased by <strong>Tender</strong>er(s) from Engineering<br />
Depts. Of <strong>Western</strong> <strong>Railway</strong> at their own cost.<br />
Can you provide us a copy Please specify<br />
the method to purchase it.<br />
The General Conditions of Contract<br />
(GCC) along with corrction slips can<br />
be seen on the website<br />
www.indianrailways.gov.in<br />
34 4.61 Insurance<br />
of Materials &<br />
Installations<br />
(Page No. 81)<br />
Hytronics<br />
GThe contractor shall take out and keep in force a<br />
policy or policies of insurance for all materials<br />
including <strong>Railway</strong> supply materials equipment until<br />
such works are provisionally handed over to the<br />
<strong>Railway</strong>s. For this purpose the works are deemed to<br />
have been provisionally handed over when<br />
Provisional acceptance certificate is issued for the<br />
Sub-section as per Para 4.39 of SCC..................<br />
Please clarify when does property transfer There no issue of property transfer.<br />
happens, from Contractor to Customer Des The contractor will be responsible<br />
property transfer happens at PAC for proper up-keep of equipments<br />
supplied and installed till warranty<br />
period is over.<br />
35 Schedule of<br />
Supply and<br />
Installation Part<br />
A), Point A3<br />
(Page No. 99)<br />
Hytronics<br />
36 Schedule 'A' - Hytronics<br />
Clause B1.1<br />
(Page No. 115)<br />
37 Chapter 4<br />
SCC, Cl 4.3.1,<br />
page no. 39<br />
Invensys<br />
TWhat is meant exactly for "diagnostic software,<br />
-maintenance / diagnostic tool" Is diagnostic<br />
Rsoftware and hardware included in scope of supply<br />
DOr only software Where is the diagnostic data<br />
Sforeseen to be used: on site or at remote location<br />
O We could not find any diagnostic software or<br />
Thardware items included in the Rate Schedules / Bill<br />
-of Quantities at Section III of <strong>Tender</strong> <strong>Document</strong>s.<br />
W<br />
S<br />
T<br />
We understand that each Line side cabinet<br />
-<br />
is designed to accommodate one LEU<br />
R<br />
module.<br />
Is it<br />
D<br />
possible to install more than one LEU<br />
S<br />
module inside a Line side electronic unit<br />
O<br />
cabinet or Line side electronic unit rack<br />
T<br />
If it is possible, how will WR manage the<br />
-<br />
payment of this solution<br />
W<br />
TAt present, the section contains approximately 835 Please clarify the extent of minor changes,<br />
-Signals including Automatic & Station signals in UP in terms of no. of signals / level crossings<br />
Wand Down direction for passenger running lines. etc.<br />
SThere are 49 Nos of Station (including Virar &<br />
Vadodara), 117 Interlocked gates in the section<br />
and there can be minor changes with time<br />
This Para is self explanatory and<br />
should be read in totality. It includes<br />
software and hardware both. The<br />
diagnostic data is required to be<br />
seen at site and remote location.<br />
Please quote as per Schedule.<br />
However, based on RDSO guidelines,<br />
if any, the schedule is likely to be<br />
amended . Future corrigendum may<br />
be seen in this regard.<br />
Minor changes may likely to happen<br />
in terms of no. of signals / level<br />
crossings. However, if there are<br />
changes in supply & execution items,<br />
it will be governed by Para 4.46 of<br />
SCC.<br />
Pre Bid Queries for TPWS 11